Interrogatory responses
Answers to questions 379, 380, 381, 382, 383
Files11
EOE-379_Final.pdf
PDF · 181 KB · 5 pagesText searchable
Download EOE-379_Final.pdfRead the text of EOE-379_Final.pdf
EOE-379 Attachment 1.pdf
PDF · 1.2 MB · 2 pagesText searchable
Download EOE-379 Attachment 1.pdfRead the text of EOE-379 Attachment 1.pdf
EOE-380_Final.pdf
PDF · 96 KB · 3 pagesText searchable
Download EOE-380_Final.pdfRead the text of EOE-380_Final.pdf
EOE-381_Final.pdf
PDF · 89 KB · 2 pagesText searchable
Download EOE-381_Final.pdfRead the text of EOE-381_Final.pdf
EOE-382_Final.pdf
PDF · 86 KB · 1 pageText searchable
Download EOE-382_Final.pdfRead the text of EOE-382_Final.pdf
EOE-383_Final.pdf
PDF · 133 KB · 4 pagesText searchable
Download EOE-383_Final.pdfRead the text of EOE-383_Final.pdf
EOE-383 Attachment 1.pdf
PDF · 1.3 MB · 125 pagesText searchable
Download EOE-383 Attachment 1.pdfRead the text of EOE-383 Attachment 1.pdf
EOE-383 Attachment 2.pdf
PDF · 3.5 MB · 182 pagesText searchable
Download EOE-383 Attachment 2.pdfRead the text of EOE-383 Attachment 2.pdf
EOE-383 Attachment 3.pdf
PDF · 3.5 MB · 55 pagesText searchable
Download EOE-383 Attachment 3.pdfRead the text of EOE-383 Attachment 3.pdf
EOE-383 Attachment 4.pdf
PDF · 715 KB · 2 pagesText searchable
Download EOE-383 Attachment 4.pdfRead the text of EOE-383 Attachment 4.pdf
EOE-383 Attachment 5.pdf
PDF · 730 KB · 7 pagesText searchable
Download EOE-383 Attachment 5.pdfRead the text of EOE-383 Attachment 5.pdf
Text of EOE-381_Final.pdf
Extracted from the file · 2 pages · 3,490 characters
Text of EOE-382_Final.pdf
Extracted from the file · 1 page · 2,648 characters
Text of EOE-383_Final.pdf
Extracted from the file · 4 pages · 10,383 characters
Page 116 of 125
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 116 of 125 Docket No. 11-09-09 Page 112 The following excerpts from the transcript illustrate the problems the companies experienced in trying to communicate with CL&P: (Heritage) “So we would just like to talk to someone so that they know that, number one, they know that we have a problem; number two, we would want them to know that we're one customer, but by not taking care of us, you've got 600 customers that are going to be without water very shortly if you don't something, that type of thing. And unfortunately, we don't get to talk to anyone about it. And the information when we did talk to someone, the information we got was totally bogus. Yeah, we'll be there by the end of the day, and the end of the day came and the next day came and the next day came. It's like, you know, let us know exactly what's going on so we can do what we have to do accordingly. Don't give us bogus information that doesn't help our situation. So it was very frustrating.” Tr. 3/26/12, pp. 717 and 718. (Hazardville/Jewett City) “We usually have a liaison or a contact, but that seems to always change whenever you need it, that number doesn't work or the contact is not there or it's a different person.” Tr. 3/26/12, p. 718. (United) “We contacted CL&P by phone numerous times. We went to their locations on numerous times to try to get answers, and we were unsuccessful. I felt that we were getting pushed aside. We just wanted to know what they were doing, because we could work together. We weren't even successful in that.” Tr. 3/26/12, p. 736. Based on the evidence in the record, and the difficulty the water companies experienced in trying to obtain accurate and needed communication from CL&P during the outages, the Authority determines that CL&P’s communication with these service providers was less than suitable and adequate. b. Wireless Communications It was nearly unanimous that cellular phones were the primary means of communication within the companies. Id., pp. 97 and 98. Valley primarily used 2-way radio and others had pagers for back-up purposes. Id., p. 95. There were no complaints with Verizon and few with Sprint. However, some of the companies complained about AT&T Mobility. Id., pp. 696 and 697. The inability to communicate by cell phone while in remote locations made it necessary for company personnel to meet at strategic locations to discuss recovery operations. United Response to Interrogatory EN-11. 4. Company Deficiencies and areas of Concern for the Authority a. Insufficient Generation and Appurtenances Avon and United were in a situation where their usual number of portable generators was insufficient, even when rotation of the units between facilities wasPage 117 of 125
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 117 of 125 Docket No. 11-09-09 Page 113 effective in prior outage situations. Id., p. 652. Access to the generators was hindered due to down lines and/or trees making relocation of them nearly impossible. The magnitude of the 2011 Storms also increased the demand for generation units where they would have normally been available through affiliated companies. Some companies learned a lesson from Tropical Storm Irene and by the time of the October Storm, they were prepared. United was generally harder hit by the October Storm, and coupled with not having made changes as a result of Tropical Storm Irene, had a very difficult time with their operations. Additionally, provisions of appurtenances, such as not having a receptacle and a run-through switch at a particular location made it difficult to use a generator. Id., pp. 656, 658. The Authority finds this to be a result of lack of planning. The Regulations call for proper controls and connections to be in place prior to a power outage event. United believes that it could have at its disposal sufficient portable generation to supply the needs of most but not all, of its satellite operations. Id., p. 52. This would have worked historically, as the sharing of generation was for shorter durations overall and access was not nearly as difficult. The Regulations require companies to supply the Average Daily Demand to all facilities all of the time. Following the 2011 Storms, United purchased two new generators, conducted a lessons-learned exercise and planned a mock drill. Id., p. 724. b. Use of Outside Electrical Contractor Hazardville/Jewett City hired an outside electrical company to identify downed energized lines in its service area. Those found to be de-energized (at that moment), were moved to allow access to its facilities. Id., p. 14. The companies should be cautioned that although a line is de-energized at one moment, does not necessarily mean it will forever be de-energized, even as it is lying on the ground. There are many reasons why and how a line can be energized, even when it was found to be deenergized moments earlier. c. Personnel Safety - Dams CWC testified that staff was monitoring the dams throughout the 2011 Storm and it was a problem having staff on the dams during the storm.” Id., p. 80. The Authority finds this practice to be dangerous. The Authority is aware that Dam Emergency Operations Plans identify the steps that must be taken to monitor these structures. The Companies should make safety of personnel a priority and should consider alternatives to on-site staffing that streaming video and wireless technologies can bring. 5. Planning for the future a. Permanent Versus Portable Generation With some of the difficulties encountered by the companies with portable generation equipment availability and transport, permanent generation should be considered for more facilities. Each company should make an assessment of the possibility that the company, and its customers, would benefit from permanent versus portable generation at any given site. There were instances where a portable generatorPage 118 of 125
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 118 of 125 Docket No. 11-09-09 Page 114 was needed, while a permanent unit was down for maintenance or repair. Id., p. 666. This is a rare occurrence; however, Companies should be thinking in terms of redundancy for the future. b. SCADA and Remote Operations The continuous communication with remote facilities through SCADA was critical to effective operations. Id., pp. 665-667. The system provides, for example, signals from pump stations and wells for startup, shut down, low and high level alarms. The loss of land-line connections to those facilities emphasizes the importance of continuous communication and many companies are now considering radio controlled communications for the future. The loss of remote communications required the scheduled visits by onsite personnel in some instances around the clock. This also required companies to revert back to automatic controls. Id., p. 70. Typically SCADA uses telephone lines for communication. With the significant numbers of down lines, communications to facilities via SCADA was lost that subsequently required manned operations, which further tasked the busy manpower. Id., pp. 672 and 673. Those companies with radio controlled SCADA retained their effectiveness and all companies using SCADA should consider radio control communication for the future. Id., p. 24. c. Fuel Availability and Proposed Law There is great interest in a fuel availability law. It was strongly recommended by the Companies that legislation be established to prioritize local supplies of gasoline to public utility companies, among other similarly impacted entities. Id., pp. 713 and 714. The companies are encouraged to propose legislation addressing fuel availability during the next legislative session. The Companies should also evaluate additional options such as utilizing temporary above ground fuel tanks for gasoline and fueling their vehicles at municipally owned fueling stations within their service territories that have back up power supply. IV. CONCLUSION AND ORDERS A. CONCLUSION The Authority concludes that CL&P’s performance in the aftermath of the 2011 Storms was deficient and inadequate in the areas of outage and service restoration preparation of personnel, support of its municipal liaison program, development and communication of restoration times to customers, and overall communication to customers, other service providers and municipalities, as to warrant regulatory sanction. The Authority also concludes that because of CL&P’s failure to obtain adequate assistance in advance of the October Storm, its response to that storm was deficient. The Authority establishes a rebuttable presumption that CL&P should be imposed an appropriate reduction to its allowed return on equity in its next ratemaking proceeding as a penalty for poor management performance and to provide incentives for improvement. In addition, in conformance with the Settlement Agreement between NU and NSTAR, the Authority retains further jurisdictional approval for recovery of anPage 119 of 125
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 119 of 125 Docket No. 11-09-09 Page 115 appropriate level of 2011 storm costs at the time CL&P seeks recovery of any such costs. Similarly, the Authority will exercise its regulatory oversight for the recovery of 2011 storm-related costs at the time UI seeks the recovery of those costs in rates. In considering appropriate reduction to allowed returns on equity in forthcoming ratemaking proceedings and in exercising its jurisdictional approval for recovery of appropriate 2011 storm costs, the Authority will consider and weigh the extent to which CL&P has recognized its shortcomings and taken concrete and measurable steps to embrace the need for aggressive, extensive restructuring of both its attitude toward storm management and establishment of new practices for execution of future storm response. Through the Orders in this Decision, the Authority requires various enhancements to the restorative capabilities of the utility companies in order that they can better face major outage events. The Authority requires CL&P to develop a heightened state of readiness, and document that such a state exists, including assessment of its own line workers, line workers from sister companies, contractors, a statement of the mutual aid assistance organizations to which it belongs, and the resources likely available from these organizations. The Authority also adopts many of Liberty’s findings and recommendations regarding preparation, restoration, and communication. While the Authority determined that telecommunications services, cable, television, gas companies, and water companies of Connecticut were less affected by the 2011 Storms than the electric industry, the PURA makes recommendations in this Decision and creates Orders to improve service reliability in these industries for future events. B. ORDERS For the following Orders, submit an original and two copies of the required documentation to the Executive Secretary, Public Utilities Regulatory Authority, Ten Franklin Square, New Britain, CT 06051, and file an electronic version through the Authority’s website at www.ct.gov/pura. Submissions filed in compliance with Authority Orders must be identified by all three of the following: Docket Number, Title and Order Number. 1. CL&P shall track recommendations resulting from all reviews of the 2011 storms, including this proceeding, the Witt Associates reports, the Davies Consulting report and the Liberty Report. CL&P shall either implement each recommendation or shall provide clear justification for not implementing a recommendation, explaining why it is not being implemented. CL&P shall provide an interim report on the status of its implementation of these recommendations to the Authority by September 30, 2012, and a final report to the Authority by December 28, 2012. 2. Not later than September 30, 2012, CL&P shall submit a report on the effectiveness of enhanced tree trimming on circuit reliability performance. The report shall be submitted in Docket No. 12-06-09.Page 120 of 125
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 120 of 125 Docket No. 11-09-09 Page 116 3. CL&P shall formulate a plan to assure that real-time damage assessment and outage restoration data are available from field crews, including crews from mutual assistance and line crews, and shall take action to ensure that field crews utilize such technologies. CL&P shall submit its report on the actions it has taken and plans to take in its submittals in Order No. 1. 4. CL&P shall formulate a plan to establish a heightened state of readiness in anticipation of a major storm. Not later than July 1 of each year, CL&P shall report on its plan to establish the lineworker resources that would be available to it in anticipation of a major storm during the upcoming July 1 through March 31 time period, including its own lineworkers, lineworkers from sister companies and contractors. In this report, CL&P shall both state the lineworker resources likely available during a storm primarily affecting only Connecticut and a regionwide storm. CL&P shall also state the mutual assistance organizations to which it belongs, and state the likely resources those organizations are capable to deliver to CL&P to assist in storm recovery. CL&P shall place primary emphasis on demonstrating a lineworker workforce that would likely be available to CL&P during the first 48 hours of a regional event, so that it is able to establish a heightened state of readiness. Due to the timing of this Decision, the first report is due no later than October 1, 2012. 5. Not later than August 8, 2012, CL&P shall implement a maintenance tree trimming program based on a four-year trim cycle, and shall present the Authority for its plans to do so in Docket No. 12-06-09. 6. CL&P shall participate in discussions with mutual assistance groups and the Edison Electric Institute on ways to improve the mutual assistance process. CL&P shall provide reports on the status of these initiatives in its reporting to the Authority pursuant to Order No. 1 above. 7. No later than October 31, 2012, AT&T shall investigate and develop a method of estimating outage information other than the reliance on customer out-of-service calls. AT&T shall also develop a method to make the outage and restoration information available to its customers. 8. No later than September 28, 2012, AT&T shall confirm in writing to the Authority that it will provide to all of the municipalities it serves, annual correspondence regarding its External Affairs manager, all emergency contact information, and any other storm or emergency communication information. 9. No later than October 31, 2012, Verizon shall develop a webpage that can be accessed by its Connecticut customers that contain storm and other emergency information. 10. No later than October 31, 2012, Cablevision shall develop a webpage that can be accessed by its Connecticut customers that contain storm and other emergency information.Page 121 of 125
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 121 of 125 Docket No. 11-09-09 Page 117 11. No later than October 31, 2012, Charter shall develop a webpage that can be accessed by its Connecticut customers that contain storm and other emergency information. 12. No later than October 31, 2012, Cox shall develop a webpage that can be accessed by its Connecticut customers that contain storm and other emergency information. 13. No later than September 28, 2012, and annually thereafter, AT&T U-Verse shall provide notification to all of the municipalities it serves, of its External Affairs manager, all company emergency contact information, and any other storm or emergency communication information as necessary. 14. No later than October 31, 2012, Verizon FiOS shall develop a webpage that can be accessed by its Connecticut customers that contain storm and other emergency information. 15. UI shall track all recommendations from all reviews of the 2011 storms, including from this proceeding and the Liberty Report. UI shall either implement each recommendation or shall provide clear justification for not implementing a recommendation, explaining why it is not being implemented. UI shall provide an interim report on the status of its implementation of these recommendations to the Authority by September 30, 2012, and a final report to the Authority by December 28, 2012. 16. UI shall participate in discussions with mutual assistance groups and the Edison Electric Institute on ways to improve the mutual assistance process. UI shall provide reports on the status of these initiatives in its reporting to the Authority pursuant to Order No. 15 above. 17. No later than October 31, 2012, UI shall report of the feasibility of establishing a method to provide customer’s name and telephone numbers to emergency personnel if that customer believes he or she requires assistance during emergency situations. 18. No later than October 31, 2012, CL&P shall investigate the feasibility of including to its on-line medical certification form of current health status additional contact information such as a secondary telephone number and e-mail address, if available. 19. No later than October 31, 2012, SCG and CNG shall submit to the Authority a revised medical certification form of current health status that includes a primary and secondary telephone number, as well as an e-mail address, if available. 20. No later than July 1, 2013, and annually thereafter by July 1, each Video Certificate Holder shall file a copy of the notices required pursuant to Conn. Gen. Stat. §§ 16-331j and 16-331u.Page 122 of 125
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 122 of 125 Docket No. 11-09-09 Page 118 21. The Natural Gas Companies shall formulate a plan to obtain and dispense gasoline and diesel fuel for vehicles and equipment when events occur like the 2011 storms that limit the ability to maintain vehicles and equipment fueled. This fueling plan shall be incorporated into the Natural Gas Companies’ Emergency Plans. The fueling plan shall be submitted to the Authority by October 1, 2012. 22. YGS shall submit a report discussing the status of each of the action items listed in YGS’ response to Interrogatory GPS-022. The report shall discuss what was done to close the action item or what is being done to address the concern. YGS shall include any additional lessons learned and its associated action items that were considered after review of the reports associated with this Docket, including but not limited to the Witt Report, Davies Report and Liberty Report. The report shall be submitted to the Authority by October 1, 2012. 23. CNG and SCG shall submit a report discussing the status of the lessons learned items from the CNG and SCG response to Interrogatory GPS-022. CNG and SCG shall include any additional lessons learned and their associated action items that were considered after review of the reports associated with this Docket, including but not limited to the Witt Report, Davies Report and Liberty Report. The report shall be submitted to the Authority by October 1, 2012. 24. No later than January 1 of each year beginning January 1, 2013, AT&T and Verizon shall conduct annual live emergency drills for their respective Connecticut operations and report the outcome of the exercises to the Authority. 25. No later than January 1 of each year beginning January 1, 2013, AT&T and Verizon shall file their annual utility pole maintenance practices similar to the EDCs. The utility pole inspection plans should include, but not be limited to, the inspection interval, number of poles inspected, replaced and associated trained personnel involved in the inspection and a detailed description of the inspection techniques that will be applied. 26. No later than November 15, 2012, the Working Group shall submit a status report to the Authority on resolved and outstanding utility pole administration issues. No later than January 31, 2013, the Working Group shall develop and recommend to the Authority a consensus pole administration structure to facilitate utility pole attachments. The above reports should also be submitted in Docket No. 11-03-07.Page 123 of 125
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 123 of 125 Docket No. 11-09-09 Page 119 Attachment A Ctrl + Click to access Attachment A, Liberty Report http://www.dpuc.state.ct.us/Electric.nsf/22d33958d7bd318385256b72006c27ec/b7d58f4 22220d29c85257a4c00553d1e?OpenDocumentPage 124 of 125
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 124 of 125 Docket No. 11-09-09 Page 120 The Connecticut Department of Energy and Environmental Protection is an Affirmative Action/Equal Opportunity Employer that is committed to requirements of the Americans with Disabilities Act. Any person with a disability who may need information in an alternative format may contact the agency’s ADA Coordinator at [phone removed], or at [email removed]. Any person with limited proficiency in English, who may need information in another language, may contact the agency’s Title VI Coordinator at [phone removed], or at [email removed]. Any person with a hearing impairment may call the State of Connecticut relay number – 711. Discrimination complaints may be filed with DEEP’s Title VI Coordinator. Requests for accommodations must be made at least two weeks prior to any agency hearing, program or event.Page 125 of 125
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 125 of 125 DOCKET NO. 11-09-09 PURA INVESTIGATION OF PUBLIC COMPANIES' RESPONSE TO 2011 STORMS SERVICE This Decision is adopted by the following Directors: John W. Betkoski, III Arthur H. House CERTIFICATE OF SERVICE The foregoing is a true and correct copy of the Decision issued by the Public Utilities Regulatory Authority, State of Connecticut, and was forwarded by Certified Mail to all parties of record in this proceeding on the date indicated. Kimberley J. Santopietro Executive Secretary Department of Energy and Environmental Protection Public Utilities Regulatory Authority August 1, 2012 Date
Text of EOE-383 Attachment 2.pdf
Extracted from the file · 182 pages · 461,233 characters
Text of EOE-383 Attachment 3.pdf
Extracted from the file · 55 pages · 132,814 characters
Text of EOE-383 Attachment 4.pdf
Extracted from the file · 2 pages · 4,635 characters
Text of EOE-383 Attachment 5.pdf
Extracted from the file · 7 pages · 11,175 characters
As listed on the current system
Question(s) Answered 379, 380, 381, 382, 383 (Connecticut Light and Power Company dba Eversource Energy) Date Filed: 10/27/2026