Answers to questions 379, 380, 381, 382, 383

ResponseFiled by Connecticut Light and Power Company dba Eversource Energy11 files
Part of docket 26-05-10Open
  • Electric
Application of The Connecticut Light and Power Company d/b/a Eversource Energy to Amend its Rate Schedules

Files11

Search terms highlighted
Eversource rate increase is on 18 pages across 3 files of the text below, highlighted. Go to the first matchClear highlighting
Words on different pages
Words on different pages
Words on different pages

Text of EOE-381_Final.pdf

Extracted from the file · 2 pages · 3,490 characters

Words on different pagesRead the text of EOE-381_Final.pdf

Text of EOE-382_Final.pdf

Extracted from the file · 1 page · 2,648 characters

Words on different pagesRead the text of EOE-382_Final.pdf

Text of EOE-383_Final.pdf

Extracted from the file · 4 pages · 10,383 characters

Words on different pagesRead the text of EOE-383_Final.pdf
6 pages match
  1. Page 17 of 125Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 17 of 125 Docket No. 11-09-09 Page 13 during a large outage or storm. Moreover, it should rigorously test call-handling technology, website, and the outage management system to ensure the technologies operate to expectations and specifications. 2. The results of UI’s efforts to procure outside resources were disappointing. UI should affiliate with more than one mutual assistance group and work with EEI and other Mutual Assistance Groups to improve the present process. 3. UI could not provide restoration estimates or restoration status to customers in a timely basis. UI should pursue technology and process enhancements that will facilitate real-time update of restoration status information in the outage system and enable more timely estimated restoration times. 4. UI management did not have proper control over the “Cut/Clear, Make Safe” work done with the towns. It should work with the towns, other utilities, and emergency agencies to establish specific guidelines as to the work to be done in the “Cut/Clear, Make Safe” effort with the towns. 5. Hazard trees contributed to the effects of the storms. The hazard-tree removal budget has not had consistent funding in past years. The current budget rate allows the removal of only very high priority hazard trees. 6. UI tree trims single-phase circuits every eight years. While it conducts some reliability centered maintenance on these lines, the eight-year cycle allows for increased vegetation density that will cause storm outages. Liberty Report, Summary of Findings, pp. 1 and 2. III. AUTHORITY ANALYSIS A. OCC AND AG CLAIMS FOR FINDINGS OF IMPRUDENCE The Office of the Attorney General (AG) asserts that CL&P was imprudent with regard to a number of storm related activities. AG Brief, pp. 1, 2, and 49-53. In particular, the AG states that CL&P: 1. Inadequately prepared for major storms, and failed to exercise or drill its emergency response plans and evaluate the results for at least five years prior to the storms; 2. Failed to request the assistance of outside crews in a timely manner and failed to reasonably manage the crews that arrived; 3. Engaged in an unreasonable damage assessment process, including failure to transmit assessment information from the field to operations headquarters efficiently; 4. Failed to train and support municipal liaisons and defer to local restoration priorities;
  2. Page 18 of 125

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 18 of 125 Docket No. 11-09-09 Page 14 5. Failed to reasonably develop estimated restoration times; and 6. Failed to reasonably manage communications with the public and public officials concerning restoration times. The AG states that the PURA should specifically find that CL&P was imprudent in these areas and should disallow any storm-related costs that are the result of this imprudent conduct, while deferring the specific quantification of the amount until CL&P’s next general ratemaking proceeding. In the alternative to disallowing specific quantified costs, the AG suggests that the PURA disallow 30 to 50 percent of all of CL&P’s 2011 Storm restoration and recovery costs or reduce CL&P’s return on equity in a future ratemaking proceeding as a penalty and warning to improve its management practices. AG Brief, p. 53. The Office of Consumer Counsel (OCC) similarly asserts that CL&P’s management practices rose to the level of imprudence. OCC Brief, pp. 12-28. Those areas chiefly related to CL&P’s communications during the restoration period, including: 1. The continued public insistence that it would meet a restoration time that it knew it was unlikely to meet; 2. The implementation of a town liaison program that failed to provide for the flow of information between towns and CL&P; and 3. The failure to implement “lessons learned” from the 2010 storm, including the failure to implement technology to facilitate “real time” updating of information from crews into its operation’s management systems. By way of remedy, the OCC seeks findings of imprudent management and related penalties or disallowance of costs for the imprudent management conduct in future proceedings, including the storm recovery docket resulting from the Merger Settlement and any upcoming CL&P rate proceedings. OCC Brief, p. 14. 1. Authority Discussion An appreciation of the nature and purpose of this proceeding is critical to the issue of regulatory economic disallowances. Conn. Gen. Stat. §16-11 provides the PURA with its general regulatory oversight. In particular, it states that the PURA must “keep fully informed as to the condition of the plant, equipment and manner of operation of all public service companies in respect to their adequacy and suitability to accomplish the duties imposed upon such companies by law.” Further, the PURA “may order such reasonable improvements, repairs or alterations in such plant or equipment, or such changes in the manner of operation, as may be reasonably necessary in the public interest.” Id. In accordance with this statutory obligation, the PURA opened this proceeding on September 14, 2011, to review the preparedness, service response and
  3. Page 19 of 125

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 19 of 125 Docket No. 11-09-09 Page 15 communications of both CL&P and UI with respect to Tropical Storm Irene.2 On November 4, 2011, in the aftermath of the October Storm, the PURA expanded the scope of this proceeding to include a review of that storm. On November 25, 2011, Motion Ruling No. 15, p. 2, the PURA entered a clarifying ruling in response to a request from the AG and the OCC. That clarification, in salient part, stated: [T]his proceeding will be of broad scope and entail a full review and investigation of the outage, impacts and responses of all public service companies, video, voice and cellular providers, to both storms . . . the Authority notes that this proceeding and investigation pursuant to Conn. Gen. Stat. section 16-11 may entail remedial orders affecting public service company improvements, alterations, or changes in the manner of operations, as may be reasonably necessary in the public interest. Thus, the PURA’s intent in this proceeding is to conduct a review and critique of public service company obligations with an aim at identifying deficiencies and impose corrective measures in the method and manner of operations, consistent with the mandate of Conn. Gen. Stat. §16-11. With the input from a broad array of interested participants, measures will be identified and imposed that will ensure that results, where deficient, will not occur again and utilities will be put on a path to provide and restore reliable and safe service in the aftermath of major storms. In this manner, the PURA strives to achieve a higher and greater public good consistent with Conn. Gen. Stat. §16-11. Accordingly, all participants were fully apprised of the nature and scope of this proceeding, and the PURA has carefully clarified the scope and purpose of its investigation. The issue of a prudence review and associated potential cost disallowance as a result of this proceeding was never raised by any participant, until the AG and the OCC presented the issue in their June 18, 2012 Briefs. . In response to the AG and the OCC claims, CL&P contends that the overall record in this matter does not support a finding of imprudence as a matter of fact,3 CL&P Reply Brief, pp. 7 and 8, and that, as a matter of law, this investigatory proceeding was not noticed to implicate either a rate disallowance pursuant to 2 3 “In establishing this docket, the Authority determined to review the Storm Irene event with a focus on the manner of operations of both electric companies having to do with storm readiness, storm restoration, storm damage, tree trimming, system reliability, and communications to municipalities and customer.” November 25, 2011 Ruling No. 15, p. 1. “… restoration of more than 809,000 outages in 11 days is not inconsistent with industry benchmark.” Report of Witt Associates¸ December 1, 2011, p. 11. “… the duration of CL&P’s restoration efforts after the 2011 storms were within industry norms, given the large numbers of outages.” Witt Associates, CL&P Management Performance Audit: 2011 Major Storm Events, June 1, 2012, p. 1. “… restoration was completed within a reasonable timeframe and cost.” Report of Davies Consulting, February 27, 2012, p. 27.
  4. Page 20 of 125

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 20 of 125 Docket No. 11-09-09 Page 16 ratemaking Conn. Gen. Stat. §§16-19 and 16-19e, or assessment of penalty statute, Conn. Gen. Stat. §16-41. CL&P Reply Brief, pp. 54 and 55. 2. Analysis Regarding Findings of Imprudence Because this proceeding was not noticed to include such issues, the Authority will not make determinations on issues of prudent and efficient management or associated cost disallowances. A minimum degree of notice is constitutionally required to uphold due process where an administrative or regulatory agency is attempting to impose a claim that involves the taking of property. A finding of imprudence with associated economic penalties or cost recovery disallowances requires this manner of due process notice. In Rivera v. Liquor Control Commission, 53 Conn. App. 165, 173 (1999), quoting Fleischman v. Board of Examiners in Podiatry, 22 Conn. App. 181, 191 (1990), the Court stated: "The test of whether one is given adequate notice is whether it apprises [the plaintiff] of the claims to be defended against, and on the basis of the notice given, whether [the] plaintiff could anticipate the possible effects of the proceeding." In Fleischman v. Board of Examiners in Podiatry, the Court stated: “[i]f the notice of charges does not fairly apprise the person of the nature of the offense with which he is charged, the court may set aside the order of an agency for deficiency of notice.” Fleischman, 22 Conn. App at 191, citing Murphy v. Berlin Board of Education, 167 Conn. 368, 374-75 (1974). Connecticut courts have also recognized a common-law right to fundamental fairness in administrative hearings. Grimes v. Conservation Comm’n, 243 Conn. 266, 273 (1997). In Grimes, the issue was whether a municipal conservation commission must provide personal notice to an abutting landowner of site inspections when the abutter had no personal interest at stake. Id. at 269-73. The court held that even though no constitutional due process right existed, administrative proceedings shall not violate the fundamentals of natural justice, which require that no one may be deprived of the right to produce relevant evidence or to cross-examine witnesses produced by his adversary. Id. at 273-74. “[D]ue process of law requires that the parties involved have an opportunity to know the facts on which the commission is asked to act . . . and to offer rebuttal evidence." Pizzola v. Planning & Zoning Commission, 167 Conn. 202, 207 (1974). As discussed herein, the notice and scope of this proceeding unmistakenly did not involve issues of imprudence or rate recovery disallowances. CL&P was not afforded the opportunity to participate in this proceeding in a manner that it would have had it known that prudence findings were an issue. Where economic sanctions are an issue, government agencies cannot act in a manner that would introduce an element of surprise to the party being penalized. See Petition of New England Telephone and Telegraph Company for an Alternative Regulatory Plan, 1995 Mass. PUC LEXIS 1, *373-74 (May 12, 1995). However, this is not to say that the PURA will not appropriately address these issues when a claim for recovery of storm related costs in rates is made. In this proceeding, a number of companies requested that they be allowed to defer non-
  5. Page 21 of 125

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 21 of 125 Docket No. 11-09-09 Page 17 recurring costs related to their responses to the 2011 Storms until their next rate case.4 In each ruling to allow such deferral, the PURA stated that the costs may be deferred until the company’s next rate case, at which time the PURA will have the opportunity to review the expenses and proposed method of recovery. The PURA further stated that such deferral does not mean recovery. Rather, the PURA stated: “[a]t that time, the Authority, as well as other participants, will have the opportunity to determine the appropriateness of the recognition, if any, of those expenses for rate-making purposes.” Rulings to Motion Nos. 35, 39, 57, and 64 (emphasis added). The AG, the OCC and other participants will have the opportunity to challenge any request for storm cost recovery at the time of CL&P’s next rate case.5 The settlement agreement in the Decision in Docket No. 12-01-07, Application for Approval of Holding Company Transaction Involving Northeast Utilities and NSTAR (Settlement Agreement), entered into by Northeast Utilities (NU), NSTAR, the AG and the OCC imposed a rate freeze until December 1, 2014.6 The Settlement Agreement further provided that CL&P would file with the PURA for recovery of costs associated with both storms and that “such request will be subject to review and approval by the Authority in an adjudicatory proceeding.” This proceeding, by definition, is not the storm cost recovery proceeding contemplated by the Settlement Agreement. 3. Industry Norms Are Not Dispositive The Authority does not agree with CL&P’s argument that the conclusions from the consultants’ reports verify that CL&P met the required standard of care. Reply Brief of CL&P, pp. 18, 22 and 23. While it is understood that the consultants’ reports suggest CL&P adhered to industry norms in some respects, such as the overall time of full restoration, see Report of Witt Associates¸ December 1, 2011, p. 11; Witt Associates, CL&P Management Performance Audit: 2011 Major Storm Events, June 1, 2012, p. 1; the standard of care in the Authority’s three-part test on prudency is not limited by industry norms, nor limited to the single issue of full restoration timing. The first part of the Authority’s prudency test states “there must be a clearly understood definition of the standard of care by which a utility’s performance can be measured.”7 Decision dated August 6, 2008 in Docket No. 08-02-06, DPUC Investigation into The Connecticut Light and Power Company’s Billing Issues, p. 10; 4 Motions of Aquarion Water Company of Connecticut, No. 35, January 12, 2012; Avon Water Company, No. 39, March 13, 2012; Hazardville Water Company, No. 57, February 21, 2012, and Valley Water Systems, No. 64, March 6, 2012. 5 The Authority, as economic regulator, must ensure that the level and structure of rates charged only reflect “prudent and efficient management of the franchise operations,” pursuant to Conn. Gen. Stat. § 16-19e(a)(5). 6 Settlement Agreement dated March 13, 2012, section 4.3 approved in the Decision, Docket No. 12-01-07. 7 The three part test is as follows: “First, there must be a clearly understood definition of the standard of care by which a utility’s performance can be measured; second, the actions of the utility must be examined to determine if there has been a failure on its part to conform to the standard required; and finally, there must be a reasonably close casual connection between the imprudent conduct, if any, and actual loss or damage.” Docket No. 08-02-06, DPUC Investigation into the Connecticut Light and Power Company’s Billing Issues, Aug. 6, 2008, at 10-11.
  6. Page 22 of 125

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 22 of 125 Docket No. 11-09-09 Page 18 Decision dated July 21, 1988 in Docket No. 87-11-01, Public Hearing to Investigate Whether Charges or Credits Made Under the Purchased Power, Fossil Fuel, Purchased Gas Adjustment and/or Generation Utilization Adjustment Clauses Are Accurate for the Preceding Three Months, p. 11. In this test, there is no reference to industry norms, industry standards, or any other form of industry practices. Such references may be applied in order to determine the standard of care; however, industry norms by themselves are not determinative per se. This view is not only in accordance with the Authority’s test for prudency, but also with numerous other areas of law. In Tug Ocean Prince, Inc. v. United States, the Court held that actions in conformity with industry standards are not conclusive; an industry as a whole can lag behind the standard of reasonable care. 584 F.2d 1151, 1156-57 (2d Cir. N.Y. 1978), cert. denied, 440 U.S. 959 (1979). The customary practice of the industry is relevant, but the standard of care is not limited to complying with usual practices in the industry or trade. Troupe v. Chicago, Duluth & Georgian Bay Transit Co., 234 F.2d 253, 260 (2d Cir. N.Y. 1956). “Compliance with industry standards . . . does not necessarily preclude the existence of an issue of material fact.” Notarino v. City of New Haven, 2010 Conn. Super. LEXIS 1864 (July 15, 2010). At this time, the Authority must legally refrain from making a determination or ruling as to the prudency of CL&P’s 2011 Storm-related costs as that issue and proceeding are for another day. When this issue is determined, industry norms may not insulate CL&P in a moat of immunity as to whether it used and executed prudent and efficient management techniques in all aspects of its storm recovery activities. Further, Witt Associates makes the following clarification on industry norms by noting, “[t]he industry has recognized that such norms themselves are in need of improvement, particularly in the areas of damage assessment and establishment of restoration priorities. Trends in industry best practice are now towards addressing these recurring challenges.” June 1, 2012 CL&P Management Performance Audit: 2011 Major Storm Events by Witt Associates, p. 4. 4. Rebuttable Presumption of ROE Disallowance The record in this case is exceedingly well developed as to CL&P’s planning, reaction, restoration, communication, execution and recovery issues as to the 2011 Storms. Based on the record, the PURA can make a number of findings and recommendations. Most have to do with the manner of operation, but the Authority also does have broad regulatory authority8 and may exercise that authority in a manner that protects the relevant public interests, both existing and foreseeable. For reasons discussed below, the Authority concludes that CL&P’s performance in the areas regarding communication to customers, other service providers and municipalities was so deficient as to be less than adequate and suitable and to warrant regulatory sanction. This deficiency also involves its lack of preparation of personnel, failure to support 8 Conn. Gen. Stat. § 16-11 states that its purpose is to assure to the state of Connecticut its full powers to regulate its public service companies and to increase the powers of the PURA and that the statute is to be construed so as to effectuate these purposes.
  7. Page 23 of 125

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 23 of 125 Docket No. 11-09-09 Page 19 municipal liaisons and to reasonably develop and communicate restoration times to customers. In light of the overall substantial weight of evidence developed in this record regarding the performance of CL&P during the 2011 Storms, the PURA will establish a rebuttable presumption that CL&P should be imposed an appropriate basis point reduction to its allowed return on equity (ROE) in its next ratemaking proceeding as a penalty for such poor management performance and to provide incentives for improvement.9 The factual support for this legal presumption as to an ROE penalty is rebuttable: the burden of proof as to management execution and manner of operation as to these deficiencies identified in this proceeding will rest with CL&P. CL&P will have the opportunity to rebut the presumption, supported by the record in this case, as well as the amount of the adjustment to its ROE at its next ratemaking proceeding. B. THE CONNECTICUT LIGHT AND POWER COMPANY 1. Description of Infrastructure a. the Storms, Outages and Damage to CL&P Tropical Storm Irene Beginning on August 23, 2011, CL&P began escalated monitoring of Tropical Storm Irene, which at that time was located in the tropical Atlantic Ocean. On August 26, 2011, CL&P opened its Emergency Operations Center (EOC) in partial activation mode at 8:45 a.m. to support and organize planning and coordination activities. At 12:02 p.m. that same day, the CL&P EOC was opened in full activation mode and it initiated the process of implementing full staffing of the EOC. Also on August 26, 2011, CL&P initiated the process of securing additional resources and establishing logistics to support these resources. CL&P Response to Interrogatory EL-1. CL&P’s pre-storm preparation consisted of the following steps that were taken five days in advance of the approaching storm: Daily storm preparation calls were scheduled to ensure all preparations for the anticipated hurricane were completed on time; Mutual aid conference calls with the New England Mutual Aid Group (NEMAG) and the New York Mutual Aid Group (NYMAG) groups were held daily from August 24, 2011 through August 28, 2011 in anticipation of dealing with the anticipated affects from Hurricane Irene. Conference calls continued until September 7, 2011 to discuss mutual aid options; Line and tree contractors were secured and prepositioned; Helicopters were secured and prepositioned for reconnaissance; 9 For instance, Schedule A-1.0B in Docket No. 09-12-05 indicates that for the rate year ending June 30, 2012, 100 basis points (1 percent in CL&P’s ROE) is equivalent to $22.83 million.
  8. Page 24 of 125

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 24 of 125 Docket No. 11-09-09 Page 20 Vacations for all NU employees were cancelled; 100% of CL&P line crews were placed on-call; Calls to Western Massachusetts Electric Company and Public Service of New Hampshire were made regarding crew availability over the weekend; Logistics vendors were prepositioned to prepare staging areas; Confirmed the Mobile Command Center was available for use; Support staff storm assignments were confirmed; Circuit configuration was checked and distribution loop schemes defeated; All facilities were confirmed ready for heavy winds and rain. All outside material was secured to prevent blowing debris; and District storm rooms were checked for readiness. CL&P Tropical Storm Irene report filed September 20, 2011 in Docket No. 86-1118, DPUC Review of Performance of UI, CL&P and SNETCO in Restoring Service After Storm Carl. On August 27, 2011, CL&P continued the process of securing additional resources and monitoring the approaching storm. On the morning of August 28, 2011, Tropical Storm Irene made landfall in Stamford, Connecticut, exposing all of Connecticut to the northeast quadrant of the storm, which encompassed the most severe weather associated with it. The State experienced sustained winds of approximately 40 mph and gusts to 66 mph over the course of most of August 28, 2011. The State experienced up to eight inches of rain, uprooted trees and downed limbs which caused extensive damage to CL&P’s infrastructure. CL&P Response to Interrogatory EL-1. Tropical Storm Irene resulted in outages to 1,024,032 CL&P customers in total, including a peak outage level of 671,000. The following is a customer restoration curve showing customer outages during and after Tropical Storm Irene:
  9. Page 25 of 125

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 25 of 125 Docket No. 11-09-09 Page 21 CL&P Tropical Storm Irene report filed September 20, 2011, in Docket No. 8611-18. Restoration from Tropical Storm Irene was completed on September 6, 2011. b. October Storm CL&P states that beginning on October 27, 2011, weather forecasting services began predicting the possibility of a Nor’easter accompanied by heavy snow for October 29, 2011. As of October 28, 2011, weather forecasts were indicating that a wet snowfall of up to eight inches could be expected on October 29, 2011. CL&P Response to Interrogatory EL-13. CL&P took the following steps in advance of the snowstorm: The event was classified as a level 5 event per the CL&P Emergency Plan;10 Friday October 28, 2011, a storm preparation call was held to ensure all preparations for the anticipated nor’easter were completed on time; Mutual aid conference calls with NEMAG and NYMAG groups were held daily from October 28, 2011 through November 9, 2011, to discuss mutual aid options. Line and tree contractors were secured; Helicopters were secured for reconnaissance; Vacations for all NU employees were cancelled; 10 Level 5 is the most severe level classification and requires commitment of all available company personnel and resources.
  10. Page 26 of 125

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 26 of 125 Docket No. 11-09-09 Page 22 100% of CL&P line crews were placed on-call; Calls to Western Massachusetts Electric Company and Public Service of New Hampshire were made regarding crew availability over the weekend; Logistics vendors were contacted to prepare staging areas; Confirmed the Mobile Command Center was available for use; Support staff storm assignments were confirmed; All facilities were checked ready for a wind, rain, and snow event. Snow removal contractors were confirmed; and District storm rooms were checked for readiness. CL&P Tropical Storm Irene report filed November 23, 2011 in Docket No. 86-1118. On October 29, 2011, at 12:00 p.m., CL&P partially activated its EOC and began requesting external resources. At 1:13 p.m., CL&P fully activated its EOC. CL&P Response to Interrogatory EL-13. Beginning in the afternoon of October 29, 2011, heavy wet snowfall on foliated trees began causing trees and branches to fall on the CL&P electric infrastructure, resulting in outages to customers. By the end of the storm, up to 16 inches of heavy wet snow had fallen in CL&P’s service territory, resulting in severe damage to electric infrastructure and prolonged outages to customers. Following is a customer restoration curve showing customer outages during and after the October Storm: Customer Restoration October 29, 2011 - November 9th, 2011 Nor'easter 900000 800000 700000 500000 400000 300000 200000 100000 11/10/2011 00:00 11/09/2011 17:00 11/09/2011 10:00 11/09/2011 03:00 11/08/2011 20:00 11/08/2011 13:00 11/08/2011 06:00 11/07/2011 23:00 11/07/2011 16:00 11/07/2011 09:00 11/07/2011 02:00 11/06/2011 19:00 11/06/2011 12:00 11/06/2011 05:00 11/05/2011 22:00 11/05/2011 15:00 11/05/2011 08:00 11/05/2011 01:00 11/04/2011 17:00 11/04/2011 10:00 11/04/2011 03:00 11/03/2011 20:00 11/03/2011 13:00 11/03/2011 06:00 11/02/2011 23:00 11/02/2011 16:00 11/02/2011 09:00 11/02/2011 02:00 11/01/2011 18:00 11/01/2011 10:00 11/01/2011 02:00 10/31/2011 19:00 10/31/2011 11:00 10/31/2011 02:00 10/30/2011 19:00 10/30/2011 11:00 10/30/2011 04:00 10/29/2011 21:00 10/29/2011 14:00 10/29/2011 07:00 0 10/29/2011 00:00 Customers Affected 600000

Text of EOE-383 Attachment 2.pdf

Extracted from the file · 182 pages · 461,233 characters

Text of EOE-383 Attachment 3.pdf

Extracted from the file · 55 pages · 132,814 characters

Text of EOE-383 Attachment 4.pdf

Extracted from the file · 2 pages · 4,635 characters

Text of EOE-383 Attachment 5.pdf

Extracted from the file · 7 pages · 11,175 characters

As listed on the current system

Question(s) Answered 379, 380, 381, 382, 383 (Connecticut Light and Power Company dba Eversource Energy) Date Filed: 10/27/2026

This filing on the current system (opens in a new tab)