Skip to main content

A prototype public docket site for the Connecticut Public Utilities Regulatory Authority

Utility Dockets and Filings

Interrogatory responses

Answers to questions 379, 380, 381, 382, 383

ResponseFiled by Connecticut Light and Power Company dba Eversource Energy11 files
Part of docket 26-05-10Open
  • Electric
Application of The Connecticut Light and Power Company d/b/a Eversource Energy to Amend its Rate Schedules

Files11

Search terms highlighted
Eversource rate increase is on 18 pages across 3 files of the text below, highlighted. Go to the first matchClear highlighting
Words on different pages
Words on different pages
Words on different pages

Text of EOE-381_Final.pdf

Extracted from the file · 2 pages · 3,490 characters

Words on different pagesRead the text of EOE-381_Final.pdf

Text of EOE-382_Final.pdf

Extracted from the file · 1 page · 2,648 characters

Words on different pagesRead the text of EOE-382_Final.pdf

Text of EOE-383_Final.pdf

Extracted from the file · 4 pages · 10,383 characters

Words on different pagesRead the text of EOE-383_Final.pdf
6 pages match
  1. Page 37 of 125

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 37 of 125 Docket No. 11-09-09 Page 33 CL&P argues that its Town Liaison program was helpful during the storms, but its effectiveness was hampered by technology and information limitations. CL&P Brief, p. 23. CL&P further asserts that the AG and the OCC claim that the Town Liaison program was imprudent fails to satisfy the Authority’s three-part test: (1) there was no evidence establishing a clearly understood definition of the standard of care by which the Town Liaison program can be measured; (2) there was no evidence as to whether the Town Liaison program failed to meet any such standard of care; and, (3) the AG and the OCC failed to demonstrate a causal connection between the alleged failure of the Town Liaison program and the storm costs they seek to disallow. While CL&P acknowledges and recognizes that there is a need for improvement to its Town Liaison program, it contends that the evidence in this proceeding does not establish that the program was imprudent. CL&P Reply Brief, p. 39. CL&P claimed that training for its Town Liaison staff has been performed prior to the 2011 Storms. In the 12 months preceding Tropical Storm Irene, CL&P held 3 training sessions for its Town Liaison personnel: September 2010, February 2011 and August 2011. Tr. 4/23/12, pp. 1102 and 1103. The last training session, held on August 23, 2011, was a Town Liaison program update. Its objectives were to define and clarify the roles and responsibilities for the Town Liaison staff, to provide an opportunity to hear first-hand accounts of lessons learned, and to provide a forum to discuss best practices and utilize peers as resources for success. CL&P Response to Interrogatory AG-8, Attachment 1. CL&P also undertook other initiatives to improve storm related communications prior to Tropical Storm Irene. Some of these initiatives included adding over 100 additional employees to the Town Liaison roster to ensure coverage during major storms and providing copies of CL&P’s Emergency Plan sent to each town via certified mail along with account executives providing second copies during personal visits with their town contacts. CL&P Response to Interrogatory AG-8. CL&P also contends that contrary to the claims of the AG and the OCC, the Town Liaison program was not a wide-spread failure. CL&P Reply Brief, p. 39. In this regard, the Authority notes numerous positive comments regarding CL&P’s Town Liaison program during both storms from municipal officials in response to post storm surveys. CL&P Response to Interrogatory OCC-94. As previously stated, CL&P recognizes a need for improvement to its Town Liaison program. One of those areas of improvement that CL&P is addressing is information technology for its liaisons. Town maps have been developed for all 149 towns in CL&P’s service area showing GIS based color-coded circuits overlaying street maps and reflecting critical customers (police, fire, hospital, etc.) with both street addresses and supply circuits. Meetings between Town Liaisons and municipal contacts have been ongoing regarding the use of these new maps, as well as verifying the critical customers. Further, CL&P stated that these meetings will continue as both utility and municipal emergency programs evolve and will include periodic validation of critical customers. CL&P is also creating an additional storm position, GPS Monitor, which will enhance situational awareness of crew locations and the efficiency of restoration crews via the use of GPS locational devices. CL&P Response to Interrogatory EL-36. Along with these measures, CL&P is implementing new real-time information displays for internal and external uses that will indicate town priorities, trouble spots, internal and foreign crew locations, work package stations, and restoration projections. CL&P also will implement enhancements to its outage map that will be available to customers and municipalities. CL&P Late Filed Exhibit No. 39, pp. 21-27. Along with these improvements, CL&P is undertaking measures to improve the
  2. Page 38 of 125

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 38 of 125 Docket No. 11-09-09 Page 34 communication of restoration information to municipalities, as well as a formal training program for Town Liaisons and participation in exercises and drills. Id., pp. 18 and 19. Liberty reviewed CL&P’s Town Liaison program and its effectiveness through the two storms. Liberty noted that CL&P deployed 90 Town Liaisons to towns that had requested support and had opened its EOC after Tropical Storm Irene made landfall. According to Liberty, Town Liaisons generally met with town or emergency officials twice daily to share restoration status information and to coordinate town priorities. During the October Storm, CL&P deployed more than 100 Town Liaison staff. Liberty Report, p. 113. Liberty stated that conceptually, CL&P’s Town Liaison process is good, but it was still in development when both storms hit. While CL&P was making adjustments and improvements in between the storms, Liberty found that the program was still relatively new and untested. Liberty further noted that critical infrastructure in towns such as water treatment plants, gasoline stations and hospitals, for example, were not easily identifiable in CL&P’s outage system. This circumstance left many towns in difficult situations, such as without drinking water, and created difficulties in the prioritization of restoration efforts as well as creating public relations issues. Id., pp. 113 and 114. Liberty contends that the Town Liaison program brings inherent challenges to provide assistance and communications in a consistent fashion. As the program was a new approach for all involved, CL&P operations staff, Town Liaisons, and municipal officials, Liberty contends that it was a bold move to deploy 149 individuals, many of which had never served in this manner before. Liberty also asserts that CL&P had not established a list of critical infrastructure in each town, so there were challenges managing each town’s priorities with the Company’s restoration priorities. Id., p. 114. Liberty indicated a number of lessons learned and offered a number of recommendations regarding the Town Liaison program: CL&P had not clearly established municipalities’ restoration priorities before the storms. In the future, CL&P should meet annually with municipal officers to discuss and confirm priorities. These priorities should be flagged on CL&P’s circuit maps and in its electronic dispatch systems. CL&P should strive to communicate estimated restoration times until the critical infrastructure has been restored. Regional partnerships or associations may be necessary, as some towns do not have EOCs. Towns need timely and accurate restoration status information. CL&P has developed town-level tools that provide access to outage status information. Town Liaisons need to establish a relationship with the municipality in advance of the storm. CL&P will pre-assign Town Liaisons and designate a back-up who will meet periodically with town leaders to develop and ongoing relationship. Id., p. 114. Liberty also recommended that CL&P enhance its Town Liaison program to create a more coordinated and consistent approach to keeping community leaders and
  3. Page 39 of 125

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 39 of 125 Docket No. 11-09-09 Page 35 municipal officials better informed of storm restoration status. Further, Liberty noted that CL&P should continue to build upon the Town Liaison program with a focus on consistency as well as developing a process by which restoration priorities are revisited or updated with each town on an annual or as-needed basis. Liberty stated that CL&P should expand post-storm follow-up to capture feedback on the quality of the Town Liaison relationship and services provided. Finally, Liberty stated that CL&P should formalize the process to secure and train employees that serve as Town Liaisons so that there are sufficient, well-trained resources. Id., pp. 129 and 130. The Authority employed Liberty to conduct its own comprehensive review of the 2011 Storms. Authority review of the Liberty Report determines that none of its findings or conclusions with regard to the Town Liaison program are contradicted by the record in this proceeding. The Authority adopts the findings, conclusions and recommendations of the Liberty Report with regard to this issue. The Authority notes that the record in this proceeding indicates that there clearly were deficiencies in CL&P’s execution of its Town Liaison program. As previously discussed, the Town Liaison program was still in development when the 2011 Storms hit. Liberty Report, p. 113. Even the Witt Report indicated that CL&P’s Town Liaison program was not fully developed. In addition, the Witt Report noted that program performance varied by person, location, and severity of damage. The Authority agrees with the representation that the Town Liaison program was essentially a work in progress at the time of the two storms. As noted previously, numerous positive comments were provided regarding the Town Liaison program after both storms. However, many negative comments regarding CL&P’s communications were noted by Municipalities indicating deficiencies in the manner CL&P supported its municipal liaison program. Response to Interrogatory OCC 94. The Authority is acutely aware of the deficiencies that occurred during the both storms and the hardships that were created for the residents and officials of the towns affected. However, these deficiencies to CL&P’s Town Liaison program were not wide-spread or state-wide, given the scope and scale of the 2011 Storms. The Authority believes that with the improvements already implemented or in the process of being implemented, CL&P’s Town Liaison program should be capable of providing the bidirectional information, support, notification and communications between municipal officials and CL&P relating to electrical system restoration during emergency operations. b. Restoration Estimate Another aspect of CL&P’s communications during the storms that was identified by the AG and the OCC as being imprudent was restoration times. The AG argued that CL&P mismanaged its communications to municipalities and the public and failed to provide complete and accurate information regarding restoration times. In particular, the AG argues that CL&P stubbornly held fast to its 99% restoration goal of all of its customers by midnight, November 6, 2011, even when it was an unrealistic objective. AG Brief, pp. 22 and 23. The AG claimed that CL&P repeatedly reaffirmed the 99% goal and that many towns and members of the public depended on its restoration estimate. Also, many customers in the hardest hit areas had left their homes during the early stages of the outage and returned in anticipation of CL&P’s fulfillment of its restoration goal. Id., pp. 23-28. With its Central Division only 82% restored at midnight
  4. Page 40 of 125

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 40 of 125 Docket No. 11-09-09 Page 36 November 6, 2011, CL&P knew or should have known before its own deadline that it would not be able to restore power to 99% of the residents. Id., pp. 28 and 29. Had CL&P given up on its unrealistic objective and provided a more honest restoration estimate, the AG argues that the Company would have taken the best approach towards protecting its corporate reputation and fostering more positive public opinion. Id., p. 30. The AG also contends that CL&P’s methodology for arriving at its 99% restoration goal was flawed, as none of its models or formulas were designed or intended to assist in generating an accurate restoration estimate in light of the scale and scope of the two storms. Id., pp. 31-33. In these regards, the AG claims that CL&P was imprudent in the development of its restoration estimates and the communication to the public and public officials of its restoration estimates. Similar to the AG, the OCC asserts that CL&P knew or should have known that its 99% restoration goal was unrealistic. Further, CL&P’s insistence to the public that it would meet this goal was misleading. OCC Brief, p. 15. The OCC also questioned the rationale behind CL&P’s development of its restoration estimate. According to the OCC, while CL&P had various models it could use to determine its restoration estimate, the actual goal was based upon a meeting between CL&P and NU officers. Id., pp. 15 and 16. The OCC took exception to CL&P not communicating until the evening of November 6, 2011, that it would be unable to meet its restoration deadline of midnight, even when the company acknowledged it was aware of this situation during the morning of November 6, 2011. Id., p. 16. Yet, according to the OCC, CL&P knew sooner than November 6, 2011, that it would be unable to meet its restoration goal. The OCC asserts that as early as November 4, 2011, CL&P was beginning to receive reliable information from internal sources that indicated the 99% restoration goal was unattainable. In addition, the OCC notes a CL&P briefing sheet from November 4, 2011, that appeared to anticipate the company’s failure to meet its deadline. Id., pp. 17 and 18. The OCC argues that CL&P was not providing its customers with the best information available regarding restoration and this information is extremely vital during extended outages such as the October Storm. Unfortunately, according to the OCC, CL&P continued to persist in its message that the 99% restoration goal by November, 6, 2011, was attainable and because of this, customers suffered. Ultimately, the OCC requests that CL&P’s actions with regard to the management of its communications to the public regarding restoration estimates be found imprudent and penalties be incurred in future proceedings. Id., pp. 19-21. CCM also took issue with CL&P’s actions in regard to the restoration estimates. The CCM did not dispute that predicting restoration estimates can be a challenging task given the scope and scale of the October Storm. However, CCM claims that CL&P’s actions were negligent by its insistence on continuing to communicate the November 6, 2011 deadline. The CCM notes that municipal officials unsuccessfully appealed to CL&P for it to offer a more realistic restoration estimate. When power was not restored at the time that CL&P committed to, residents in some towns overloaded emergency shelters or failed to relocate to safer quarters as they were misled about the likely time of restoration. The CCM argues that CL&P’s restoration estimate was either intentional or at best a negligent misrepresentation. This misrepresentation impacted upon municipalities’ costs of the outage and increased the danger and risk to public health and safety. The CCM states that the best way to ensure this situation never reoccurs is for the Authority to hold CL&P accountable for its misconduct. CCM Brief, pp. 9 and 10.
  5. Page 41 of 125

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 41 of 125 Docket No. 11-09-09 Page 37 CL&P disputes the claims from the AG and the OCC that the development of its restoration estimate was imprudent. CL&P contends that early in the recovery period of the October Storm, it developed its restoration estimate under extremely difficult circumstances as well as in response to understandable pressure from the public and public officials seeking guidance. CL&P states that it then committed the company to developing a restoration plan, securing additional resources and doing everything that was within its power in order to meet the restoration estimates. While CL&P noted that it was able to meet its estimate for 100% restoration, the fact that it did not meet the 99% goal was a reflection of the difficulties and challenges of the October Storm. CL&P Reply Brief, pp. 27 and 28. CL&P acknowledges that developing restoration estimates during the October Storm was far from a perfect procedure, but there was no support on the record to support the AG’s claim that the company had provided multiple different explanations. Throughout the proceedings, CL&P asserts that it had provided a consistent explanation for how it calculated its restoration estimates. In addition, CL&P states that it has provided a detailed step-by-step description, consistent with its Emergency Response Plan, of how the restoration estimates were derived. Id., pp. 29 and 28. CL&P also disputes the AG’s argument that the restoration estimates were derived and determined not by any formula or model, but via consultation of CL&P corporate officials. According to CL&P, the restoration estimate was a result of collaboration and multiple inputs, including projections developed pursuant to its Emergency Response Plan. CL&P claims that the record reflects that the process used to develop the restoration estimate was a process involving multiple individuals to arrive at a challenging, but still reasonable goal: 99% restoration by midnight on November 6, 2011, and 100% restoration by November 9, 2011. Id., pp. 30-33. CL&P also argues that its 100% projection (midnight of November 9, 2011), released three days after the storm on November 1, 2011, was accurate and based upon the same restoration projection process and data collection system that the company employed during Tropical Storm Irene. Further, this same process to estimate the restoration arrived at a 100% restoration on September 7, 2011, for Tropical Storm Irene, and the goal was arrived at one day earlier, on September 6, 2011. Id., p. 34. During Tropical Storm Irene, CL&P estimated that it would take three days to restore power to the last one percent of its customers, but in actuality it only took two days. Based upon this experience, CL&P estimated that it should be able to restore power to the last one percent of its customers in three days of the October Storm. This estimate prompted CL&P to estimate that it should be able to restore power to 99% of its customers at midnight, November 6, 2011, which was 3 days prior to the 100% target (November 9, 2011). This process of estimation was directly from CL&P’s Emergency Response Plan that utilized “extrapolations based on application of logic and experience.” However, CL&P explained that the last days and hours leading up to November 6, 2011 99% goal were in continual flux. CL&P was achieving improvements to the pace at which it was restoring customers and it was adding 294 additional crews to the restoration process. CL&P states that it was confident it could reach the 99% goal. However, CL&P argues that power restoration during catastrophic circumstances is by definition a fluid and uncertain process as a number of unforeseen developments during the morning of November 6, 2011, a substation fire in New Britain, cable faults in West Hartford and a number of unexpected additional outages, hampered its restoration process. In the end, CL&P was only able to restore power to 94% of its customers by midnight of November 6, 2011. Id., pp. 34-36.
  6. Page 42 of 125

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 42 of 125 Docket No. 11-09-09 Page 38 According to CL&P, its restoration projections were estimates, not guarantees. As previously stated, CL&P claims that it was under considerable pressure from state officials, municipalities and its customers to provide restoration estimates. On November 1, 2011, three days after the October Storm, CL&P provided its estimates, earlier than what it had wanted. CL&P Late Filed Exhibit No. 68. CL&P acknowledges that it could have declined to provide the restoration estimates or issued an estimate laden with caveats that would have caused them to be less than helpful. Id. In creating its restoration estimates for the October Storm, CL&P followed the formulas and procedures within its Emergency Response Plan (ERP). CL&P’s 100% October Storm restoration estimate proved to be accurate, as 100% of its customers were restored by midnight on November 9, 2011. CL&P states that the procedures in its ERP states that the formulas only provide a guide to determining restoration times and that company personnel developing the estimate will utilize extrapolations based upon application of logic and experience. CL&P notes that this also includes the following conditions: Historic storm restoration curves; Experience from prior storms; Knowledge of and experience with CL&P’s electric system; Knowledge of current system conditions; Expectations about how many additional crews will be available and when additional crews will be available; Knowledge and experience about the process CL&P uses to collect and input data during the storm restoration process, including the company’s knowledge that data collection is an imperfect process; and Any other factors and data deemed relevant by CL&P based on logic and experience. Id. Utilizing its knowledge and experience from Tropical Storm Irene, CL&P noted that restoration of the last one percent of customers took two days to complete instead of the projected three days. Due to the scale and scope of the October Storm, as well as issuing its restoration estimates sooner than the company had wanted, CL&P states that it reasonably estimated that it would be able to restore power to the last one percent of its customers in three days. Id. CL&P further notes that storm restoration is a dynamic process where there will be periods of time when the pace of restoration can be faster, on target or slower than estimated. During the entire restoration process, CL&P stated that it continually evaluated updated information, and due to the scale and scope of the October Storm, it was understandable that the data collection process would be imperfect. This, coupled with delays in the collection and inputting of data, would lead to understated and/or inaccurate data. Id. CL&P claims that there would have been little value to the State, municipalities or to the public had the company issued revisions to its restoration estimates on an hourly or even daily basis to reflect the normal fluctuations to the pace of the restoration process or to incorporate the company’s discovery of understated or inaccurate data. Company e-mails indicated that up until the morning of November 6, 2011, CL&P reasonably believed that it would be able to meet its 99% goal. These beliefs were based upon additional crews being
  7. Page 43 of 125

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 43 of 125 Docket No. 11-09-09 Page 39 added to the process as well as a 15% improvement to the pace of restoration on November 4, 2011 and November 5, 2011. Id. CL&P also believed that if it were able to improve the pace of restoration by an additional 20% then it was still reasonably plausible to meet the 99% goal. However, on the morning of November 6, 2011, CL&P also found it necessary to inform the State that it might not be able to meet the 99% goal. Id. By 6:00 p.m. on November 6, 2011, CL&P made an announcement that the 99% restoration goal would not be reached. Tr. 5/21/12, p. 2653. By midnight of November 6, 2011, CL&P had restored power to approximately 94% of its customers. CL&P Late Filed Exhibit No. 68. CL&P states that despite an additional 294 utility crews available on November 6, 2011, and despite its encouragement to all crews to work extended shifts, the 99% restoration estimate was not achieved for a number of reasons, including a substation fire in New Britain, cable faults in West Hartford and unexpected additional outages. Id. Various facts were collected regarding CL&P and its 99% restoration estimate. In its management audit of CL&P, Witt Associates noted that during the October Storm, the company’s Chief Operating Officer (COO) publicly released an internal restoration target and then stated a further goal that 99% of each town would be restored by a date certain without verifying that either was a realistic or appropriate statement to release to the public. Witt further noted that the CL&P COO publicly stated that the restoration target was perceived as a commitment, particularly when he affirmed it in subsequent statements. Witt Audit Report, p. 50. CL&P’s own internal report, conducted by Davies Consulting found that there was no clear understanding of who had responsibility for developing or implementing a communications strategy during storm restoration. The problem was further compounded with the statement that 99% of customers would be restored two days prior to when they ultimately were. Davies stated that external stakeholders perceived that CL&P was either intentionally misleading the public or simply did not understand the scope of damage to its own system. Davies Report, p. 56. Liberty noted that CL&P was able to develop an overall projection as to when it would restore 99% of customers as it did during Tropical Storm Irene. However, at some point, the 99% restoration estimate turned into a commitment to restore 99% of customers in each town by November 6, 2011, which Liberty claimed was a much more aggressive goal than restoring 99% of all affected customers. When CL&P failed to achieve this goal, customers and municipal officials all were frustrated and inconvenienced. Liberty Report, pp. 111 and 112. As discussed, these frustrations felt by customers and municipal officials led to contentions that CL&P was imprudent in its development of its restoration estimates and was imprudent in its failure to notify the public sooner than November 6, 2011, that the 99% restoration estimate was unobtainable. In analyzing CL&P’s development of the restoration estimate for the October storm, the Authority notes that the company consistently utilized its ERP in the development of its restoration estimates. CL&P also stated that it utilized the same methodology for developing restoration estimates during the October Storm as it did during Tropical Storm Irene. During Tropical Storm Irene, these restoration estimates were sustained when CL&P completed its 100% restoration one day ahead of schedule. Based upon its knowledge and experience from Tropical Storm Irene and its ERP, CL&P developed its restoration estimates for the October Storm.
  8. Page 44 of 125

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 44 of 125 Docket No. 11-09-09 Page 40 However, as noted in the Liberty Report, at some point, CL&P’s 99% restoration estimate turned into a commitment to restore 99% of customers in each town by midnight, November 6, 2011. As of 6:00 a.m. on November 7, 2011, over a dozen towns had greater than 10% out of service, and in some cases higher than 30% out of service. CL&P Response to Interrogatory AG-101. CL&P claims that its estimates are not a guarantee, but CL&P continued up until the morning of November 6, 2011, to release press statements that the company was focused on the 99% restoration by midnight. Response to AG-120. Further, even though the restoration work that would have been necessary on Sunday November 6, 2011, to reach the 99% goal was going to be a considerable undertaking, the company maintained that its 99% goal was attainable. However, a number of unanticipated last minute incidents such as a substation fire, cable faults and unexpected additional outages undermined CL&P’s restoration efforts. Ultimately, CL&P informed the public six hours prior to its own selfimposed deadline that the company would not be able to maintain its estimate. Was there a better time than 6 p.m. on November 6, 2011, to inform the public that the 99% restoration estimate was not attainable or would it have been more realistic for CL&P to pull back from its midnight, November 6, 2011, estimate while maintaining its overall 100% restoration estimate? CL&P stated that it provided the estimates for the October Storm under considerable difficulty and in response to pressure from the public and public officials. However, customers and public officials relied upon CL&P to provide the most accurate restoration estimates that the company could produce. CL&P itself characterized the 99% restoration estimate as a “stretch goal.” Tr. 5/21/12, pp. 2750 and 2756. Customers and public officials relied upon CL&P’s expertise regarding restoration estimates and when the company was unable to meet its commitment, it caused considerable inconvenience and hardship to customers, businesses and municipalities. For these reasons, the Authority finds that CL&P actions were deficient and inadequate in the development and communication of restoration times to customers and public officials. 4. Emergency Planning and Organization CL&P implements ICS organization principles to structure its organization during emergencies. ICS is a set of personnel, policies, procedures, facilities, and equipment, integrated into a common organizational structure designed to improve emergency response operations of all types and complexities. ICS is a subcomponent of the National Incident Management System (NIMS), as released by the U.S. Department of Homeland Security in 2004. CL&P states that its implementation of ICS and its ERP provided a good framework for managing the restoration, but there was some confusion during the 2011 Storms as to responsibilities, and questions as to “scalability.”15 CL&P notes that conclusions of the Liberty Report support that the company’s implementation of ICS provide an effective framework for an effective response, and that the Classification of Service Outage Events in CL&P’s emergency plans provides helpful guidance in determining the amount of required resources. CL&P notes that it plans to improve on 15 Scalability refers to the expansion of an organization as the size and scope of an emergency event increase.
  9. Page 45 of 125

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 45 of 125 Docket No. 11-09-09 Page 41 identified concerns with ICS scalability. Finally, CL&P requests that the Authority determine that the company has until December 31, 2012, to submit a compliance filing providing an update on the status of its review of consultant recommendations. CL&P Brief, pp. 25 and 26, 32. CL&P asserts that it recognizes a demonstrated need for improvement in its emergency operations. CL&P cites the following as improvements in its emergency preparedness and response procedures: The company has instituted an internal reorganization that included creating a new position of Senior Vice President of Emergency Preparedness, charged with improving preparedness and emergency response; CL&P has implemented a “Powered Up” program aimed at guiding its progress to achieve “best in industry” performance in six focus areas: preparedness, scalability, coordination, communications, situational awareness and infrastructure hardening; The company has conducted outreach to municipalities to better understand their concerns; The company has fully cooperated with all consultants and post-storm investigations; CL&P has enhanced its coordination and cooperation with DEMHS; The company has increased storm preparedness and response training; CL&P has substantially increased its regular tree maintenance and enhanced tree trimming in 2012; The company plans to file a revised ERP by July 1, 2012, with the Authority that will reflect many improvements, including enhanced scalability; CL&P will file a system resiliency program with the PURA by July 3, 2012, which will include proposals for additional tree trimming and certain distribution equipment upgrades; and The Company has initiated technology improvements to enhance its restoration and response. Id., pp. 26-29. Liberty found that ERPs are generally useful and provide adequate direction to guide major storm response as well as clear definition of responsibilities and management expectations. Liberty also concluded that the event classifications are in keeping with standard utility practice, and that it calls for engagement of all available resources for events that result in outages to 20,000 customers or more. However, Liberty determined that CL&P’s ERP required certain improvements to make the plan
  10. Page 46 of 125

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 46 of 125 Docket No. 11-09-09 Page 42 more usable and to further clarify and refine roles and responsibilities. pp. 11-22. Liberty Report, The AG states that CL&P’s existing ERP presents a number of concerns. First, it did not adequately anticipate the scale of the 2011 Storms, since it defined the most severe event as one that plans for an outage of greater than 100,000 customers, whereas the October Storm resulted in outages of more than 800,000 customers. Second, CL&P’s plan was reactive, since it precludes activation of Area Command prior to the actual onset of storms. Finally, that CL&P’s ERP did not adequately stress training and drills. AG Brief, pp. 9 and 10. The AG furthermore states that CL&P’s failure to drill or exercise its ERP and evaluate results was imprudent. The AG notes that CL&P did not drill or exercise its ERP for at least five years prior to the 2011 Storms and that there is no evidence that the company ever drilled for storms as large as the 2011 Storms. The AG further asserts that this lack of training and preparation was apparent during the response to the October Storm. Id., pp. 11 and 12. The OCC agrees with most of the Liberty Report recommendations regarding ERP improvements, with the exception that CL&P should have more outage classification levels in its plans. The OCC also asserts that the ERP should be amended to place a higher priority on “cut, clear and make safe” activities and road clearance work (CCMS Work), leaving restoration of power to large numbers of customers until later in the restoration process. Additionally, the OCC recommends that the ERP have detailed plans for allocating resources to pole replacement activities. Furthermore, the OCC states that the 2011 Storms highlight a need for better transmission emergency planning and “infrastructure updating,” and requests that the Authority adopt a number of findings and orders to improve transmission system level outage restoration practices and material condition. OCC Brief, pp. 36-49. The CCM states that the CL&P ERP should be revised to make CCMS Work a higher priority in the restoration process.16 The CCM documents a number of instances in which access to individuals with health issues was impeded by downed wires on public roads. The CCM further states that downed wires and trees impede egress of residents from their homes to obtain necessary supplies. The CCM asserts that CL&P is unwilling to make opening all public roads a top safety priority, and that the status quo situation is unacceptable. CCM Brief, pp. 1-5. Additionally, the CCM states that CL&P’s ERP does not include a comprehensive list of critical care facilities. Further, the CCM states that leaving restoration priorities to the company’s judgment “does not work,” and cites instances of facilities such as water treatment plants and prisons coming dangerously close to exhausting fuel supplies. The CCM cites an example in Tolland where total road clearing efforts, presumably by CL&P did not take place for four to five days. Id., pp. 4-8. The towns of Newtown, Redding, Ridgefield and Wilton (collectively, the Four Towns) assert that CL&P should assign at least one line crew to each town for road 16 These activities involve EDC lineworker personnel assisting road clearing personnel in clearing fallen wires from public ways.

Text of EOE-383 Attachment 2.pdf

Extracted from the file · 182 pages · 461,233 characters

Text of EOE-383 Attachment 3.pdf

Extracted from the file · 55 pages · 132,814 characters

Text of EOE-383 Attachment 4.pdf

Extracted from the file · 2 pages · 4,635 characters

Text of EOE-383 Attachment 5.pdf

Extracted from the file · 7 pages · 11,175 characters

As listed on the current system

Question(s) Answered 379, 380, 381, 382, 383 (Connecticut Light and Power Company dba Eversource Energy) Date Filed: 10/27/2026

This filing on the current system (opens in a new tab)