Skip to main content

A prototype public docket site for the Connecticut Public Utilities Regulatory Authority

Utility Dockets and Filings

Interrogatory responses

Answers to questions 379, 380, 381, 382, 383

ResponseFiled by Connecticut Light and Power Company dba Eversource Energy11 files
Part of docket 26-05-10Open
  • Electric
Application of The Connecticut Light and Power Company d/b/a Eversource Energy to Amend its Rate Schedules

Files11

Search terms highlighted
Eversource rate increase is on 18 pages across 3 files of the text below, highlighted. Go to the first matchClear highlighting
Words on different pages
Words on different pages
Words on different pages

Text of EOE-381_Final.pdf

Extracted from the file · 2 pages · 3,490 characters

Words on different pagesRead the text of EOE-381_Final.pdf

Text of EOE-382_Final.pdf

Extracted from the file · 1 page · 2,648 characters

Words on different pagesRead the text of EOE-382_Final.pdf

Text of EOE-383_Final.pdf

Extracted from the file · 4 pages · 10,383 characters

Words on different pagesRead the text of EOE-383_Final.pdf

Text of EOE-383 Attachment 1.pdf

Extracted from the file · 125 pages · 401,903 characters

5 pages match
  1. Page 103 of 182

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 2 Page 103 of 182 Report on the Response of CL&P and UI to Storms in August and October 2011 The following chart details the peak staffing for each day of storm Irene. CE was able to secure considerable staffing to handle incoming calls. CL&P’s staffing levels peaked on the 4th day of the storm, a Tuesday.139 Throughout the storm, CE continued to monitor weather on an hourly basis. CE conducted twicedaily conference calls to review staffing, crew welfare, technology, restoration priorities, and deliver status from other CE Emergency Operations teams. Upfront messaging for inbound customer calls was also reviewed and updated twice a day. Training tips and reminders on various relevant topics were distributed as refreshers to all CE employees throughout the storm. Early in the storm, CE manually cutover to Twenty First Century Communications high-volume overflow IVRs. CE created the Exceptions Group to address any calls that could not be handled automatically by Twenty First Century Communications’ IVR (TFCC), CL&P’s high-volume overflow vendor. During a large storm, such as Irene, call volumes can quickly exceed CL&P capacity. At this point, outage calls will be forwarded to TFCC for automated handling. If TFCC can find the incoming phone number in its database, an outage ticket is automatically created and forwarded to CL&P’s outage management system. If TFCC cannot match the phone number it is recorded on an exceptions log that is forwarded every 30 minutes to CL&P for manual processing. Each exception represents a reported outage in which TFCC was unable to associate an account with the phone number. As a result, CL&P must contact the phone number associated with each exception to identify the correct CL&P account and then manually enter an outage in the outage management system. This can be a lengthy process. CE staffed the Exceptions group with 14 individuals from the C2 Systems Support group. During Irene, CL&P received 14,830 exceptions from TFCC, of which 1,270 were identified as an emergency such as wires down or tree on wire. At times, CE assigned as many as 30 people in 139 Response to CSU-002. April 16, 2012 The Liberty Consulting Group page 100
  2. Page 104 of 182

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 2 Page 104 of 182 Report on the Response of CL&P and UI to Storms in August and October 2011 12-hour shifts to work the exceptions queue until it completed all exceptions, representing a significant manual effort. It worked all exceptions within 2.5 days.140 However, had CL&P designed a different call flow for TFCC, exceptions could have been routed in real-time back to live agents for immediate handling, thereby eliminating the exceptions backlog and subsequent extensive manual effort to record outages. Of real concern though are the 1,270 emergency calls that could not be matched in real-time. Even though it gave these calls top priority for follow-up by the exceptions team, they did not handle these calls in real time. During a storm, emergency calls should be routed back immediately to CL&P’s contact center for prompt handling. CE also established director-level presence in the Emergency Operations Center (EOC). CE’s Director of Customer Experience Support was assigned to represent CE in the EOC. This position participated in conference calls, worked with Corporate Communications team members on customer messaging and outbound campaigns, and helped communicate restoration status information back to CE Communications Leads to package for contact center representatives (talking points). CE also conducted several special outreach efforts during the storm including:141 • Medical hardship customers without power were contacted and provided a referral to Red Cross for assistance (pre-recorded calling campaign) • Nursing homes were contacted regarding restoration efforts (live calling campaign) • Outreach to towns in eastern Connecticut to confirm power restoration (pre-recorded calling campaign) • Sent close to 500,000 outage updates via text messaging to CL&P customer mobile phones. A group of employees, primarily in-house attorneys, staffed the Escalated Response Team to deal with difficult calls, complaints, issues needing special attention, and customers asking to speak with supervisors or company executives. This process worked very well during storm Irene and continued in the October snowstorm. In retrospect, CE’s contact centers performed well throughout the storm and very few contact center issues were encountered: • This was the first time CE used TFCC’s overflow services. As a result, CE had no clear-cut rules or thresholds for when to start and stop TFCC overflow services, aside from all trunks busy. As a result, some customers experienced busy signals during a brief period of time at the onset of the storm. Customers had approximately 4,500 calls blocked on August 28, from 7:00 am to noon. 142 In hindsight, CE could have cutover to TFCC sooner and further minimized busy signals. 140 Response to Liberty-100. Response to CSU-001. 142 Response to CSU-002. 141 April 16, 2012 The Liberty Consulting Group page 101
  3. Page 105 of 182

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 2 Page 105 of 182 Report on the Response of CL&P and UI to Storms in August and October 2011 • A couple of days into the storm CE realized that the upfront messaging on TFCC’s IVR was not the same as that of the internal IVR. As a result, CE was not seeing the benefit of that message (callers hanging up after they have heard the message). CE addressed this issue following the storm and made sure that messaging was consistent during future storms, including the October snowstorm. October Snowstorm Response Beginning as early as Friday, CE began to supplement staffing for the weekend. It added ten CSRs to the Saturday schedule (afternoon) and placed 15 more on paid standby (in each center). Other pre-storm preparations included:143 • Daily pre-storm conference calls within CE leadership • Formal monitoring of the weather • All telephony systems and overflow options were tested • IT was notified to prepare to overflow calls to Twenty First Century Communications • Prepared to close for regular business on Monday, October 31, 2011 • Participated in CL&P Operations Preparations & Communication conference calls • Drafted outbound messaging in anticipation of major event • Removed global restoration message from IVR CE held a Storm Call at 1:00 pm on Saturday to evaluate storm conditions and predictions. At this time, it activated the CE Storm Plan. CE also extended the schedules for CSRs already onsite, added 10 more CSRs at each center, and called in the 15 on standby. From Saturday on, CE scheduled its employees to work extended 12-hour shifts to provide 24-hour coverage during the storm. Unlike storm Irene, CE did not decide to preposition employees in the CE Centers. It made the decision to call in “all hands” on Saturday afternoon, after it activated the Storm Plan, as the number of outages climbed and conditions worsened. Unfortunately, worsening conditions also made it challenging for employees to get to the contact center. As a result, the Windsor CE Center’s staffing levels were at their lowest during the highest volume of calls. Pre-positioning employees in the contact centers ensures that employees are not trying to get to work during or after the storm. Rather, employees are in the centers ready to respond when customers begin to lose power. Ramping up to full staffing proved to be a lengthy and somewhat onerous process. CE first initiated an Everbridge automated notification asking all CE employees to report for storm duty, followed up by blast pages. To reach everyone, the CE Storm Staffing Team ended up having to call 200 to 250 employees that had not responded to the notification, further delaying the ramp up to full staff. The Windsor Center did not reach near-peak staffing until the fourth day of the storm. Center staffing levels actually peaked on the tenth day of the storm.144 143 Response to CSU-001. Response to CSU-109. 144 April 16, 2012 The Liberty Consulting Group page 102
  4. Page 106 of 182

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 2 Page 106 of 182 Report on the Response of CL&P and UI to Storms in August and October 2011 The CE Storm Team booked a half a dozen hotel rooms ahead of the storm, for employees who did not feel comfortable driving in storm conditions. However, the hotel lost power in the storm so employees were unable to use the rooms. Cots were provided in the Center as well. CE focused more on employee welfare during this storm, recognizing what they were asking of employees. It made provisions for three meals a day to all Windsor employees, as well as snacks and refreshments. CE also distributed Meals-Ready-to-Eat to employees to take home with them, because many employees had no power at home. It conducted stretching sessions frequently during the storm, led by CL&P’s Well-Aware coordinator. On November 3, CE brought in therapists to help employees deal with the stress caused by the storm. Therapists remained on site through November 8. CE also hired two massage therapists to provide 10-minute massages to employees on November 3 and 4. Expecting a high volume of callers over the weekend, CL&P reprogrammed its IVRs to the “after-hours” mode, informing callers that CL&P was handling emergency calls only. This remained in effect until Monday, November 7. It also placed the following upfront message on the IVR to alert callers to the storm: As of 4 p.m. on Sunday, the early nor’easter has caused unprecedented damage throughout [Connecticut/Western Massachusetts/New Hampshire]. As we work to restore the majority of customers within seven days, there may be customers in hardest hit areas where outages could last longer. We are continuing damage assessments and are working with town leaders on emergency response activities. As on location assessments are completed, we will use that information as the basis for restoration projections. We are working around the clock and will have additional support from other utilities. To report an immediate emergency such as burning wires or any other situation requiring a 911 response, or to report a April 16, 2012 The Liberty Consulting Group page 103
  5. Page 107 of 182

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 2 Page 107 of 182 Report on the Response of CL&P and UI to Storms in August and October 2011 power outage, please stay on the line. Please, always stay away from all downed wires and electrical equipment. For shelter information please dial Infoline at 211. Thank you for your patience."145 As with storm Irene, CL&P, Yankee Gas, and WMECO closed for normal business as NU focused on storm damage assessment and restoration efforts. This included closing the walk-in centers in Berlin and Hartford, suspending service disconnects, and instructing CSRs to handle only emergency calls. The Contact centers suspended normal business operations through 1:00 pm on Monday, November 7, 2011, and returned to full operations on Thursday, November 10. The Berlin Business Office reopened on November 7, while the Hartford Business Office did not re-open until November 14. On Monday, October 31, CL&P initiated a pre-recorded outbound dialing campaign to notify customers of damage assessment activities and to set expectations for an extended outage: Hello. This is an important message from Connecticut Light and Power. With the widespread impact of the weekend nor’easter, we are working tirelessly to ensure power outages are restored as safely and as quickly as possible. Damage assessments are ongoing and we are working closely with town leaders on emergency response activities. As on-site damage assessments are completed, the information will be used as the basis for restoration projections. We are working to restore the majority of customers within seven days, however, it may take longer for restorations in the hardest hit areas. We have more than 350 line and tree crews working, we anticipate over 600 additional crews joining us from other utilities, and we continue to request crews. If you see a downed power line, please always assume it’s live, don’t go near it, and never drive over a power line. We understand how difficult it is to be without electricity and we are working aroundthe-clock to restore your power. Please call us at [phone removed] to report an emergency situation. Thank you.146 On Saturday and Sunday, CL&P received 469,908 calls, nearly half of which were handled by Twenty First Century Communications, CE’s high-volume overflow IVR. 147 Calls averaged about 10,000 calls per hour for that 24-hour period, about five times more than handled on a dayto-day basis. By the end of the storm, the Windsor CE Center handled more than 1.1 million calls. The following chart details calls handled by day for the storm.148 145 Response to AG-111-BULK, page 4. Response to AG-111-BULK, page 4. 147 Response to CSU-019. 148 Response to Witt-043. 146 April 16, 2012 The Liberty Consulting Group page 104
  6. Page 108 of 182

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 2 Page 108 of 182 Report on the Response of CL&P and UI to Storms in August and October 2011 CL&P customers may have encountered busy signals during a brief period on the first day of the storm, Saturday, October 28, 2011, from 3:00 pm to 5:00 pm, at which point call volume jumped from 4,000 calls per hour to 30,000 calls per hour. Approximately 9,600 busy signals were recorded in two hours.149 While NU does contract with TFCC to provide high-volume overflow services, CE personnel must manually switch call routing to invoke the service. The individual charged with this responsibility during the October Snowstorm had difficulty getting to the Windsor Contact Center to change the call routing. Once on site, it successfully cutover call routing to TFCC. Throughout the storm, CE continued to monitor weather on an hourly basis. CE conducted twicedaily conference calls to review staffing, crew welfare, technology, restoration priorities, and deliver status from other CE Emergency Operations teams. CE reviewed and updated upfront messaging for inbound customer calls twice a day. As appropriate, CE distributed training tips and reminders to its employees on relevant topics during the storm. CE again established director-level presence in the Emergency Operations Center (EOC). CE’s Director of Customer Experience Support represented CE in the EOC. This position participated in conference calls, worked with Corporate Communications team members on customer messaging and outbound campaigns, and helped communicate restoration status information back to CE Communications Leads to package for contact center representatives (talking points). 149 Response to CSU-019, page 3 of 14 April 16, 2012 The Liberty Consulting Group page 105
  7. Page 109 of 182

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 2 Page 109 of 182 Report on the Response of CL&P and UI to Storms in August and October 2011 It also conducted several special outreach efforts during the storm including:150 • Medical hardship customers without power were contacted and provided a referral to Red Cross for assistance (pre-recorded calling campaign) • Nursing homes were contacted regarding restoration efforts (live calling campaign) • Outreach to towns in eastern Connecticut to confirm power restoration (pre-recorded calling campaign) • Sent nearly 500,000 outage updates via text messaging to CL&P customers’ mobile phones. During the October storm, CL&P received many more exception calls from TFCC that had to be addressed manually—52,370 exceptions, of which it identified 8,610 as an emergency, such as wires down or tree on wire. CE staffed the Exceptions group with 14 individuals from the C2 Systems Support group but also brought in other resources, due to the high volumes. At times, it assigned as many as 30 people in 12-hour shifts to work the exceptions queue until it completed all exceptions, representing a significant manual effort. It worked all exceptions within four to five days.151 The Escalated Response Team also handled more than 6,300 escalated calls from customers during the storm as customers became frustrated with the slow restoration times and missed commitments. By the sixth or seventh day of the storm, escalated calls represented 1 to 2 percent of daily call volume. CE used in-house attorneys and other employees skilled in dealing with difficult situations to handle supervisor and executive requests. The Escalated Response Team worked 12-hour shifts, 150 151 Response to CSU-001. Response to Liberty-100. April 16, 2012 The Liberty Consulting Group page 106
  8. Page 110 of 182

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 2 Page 110 of 182 Report on the Response of CL&P and UI to Storms in August and October 2011 staffing as many as 30 employees during the peak of the storm. The team handled escalated calls live and through callbacks, usually within an hour. CE’s Director in the Storm Room was also key in getting information from the field to the Escalation Team, especially town-level information, such as the daily plan. This information was key in handling these calls. In summary, CE’s Windsor Contact Center experienced few issues during the October Snowstorm: • CE was not able to staff the center as quickly as necessary at the beginning of the storm due to quickly changing conditions and a delayed decision of when to issue the “all hands on deck.” • A few thousand customer calls were blocked due to the delay in manually cutting over to TFCC, but only during a very brief period. • TFCC could not handle many outage calls automatically, resulting in more than 50,000 exceptions that CE worked manually, many of which (8,600) were emergency calls. Significant manpower was required to resolve exceptions over the course of five days. While CE’s contact centers performed extremely well in both storms, CL&P does have several opportunities to improve its telecommunications to handle better customer calls in future large outage events. Liberty discusses these opportunities in the recommendations section at the end of this section. 2. Corporate Communications To set expectations ahead of storm Irene, CL&P Corporate Communications proactively reached out to the media with customer-focused communications, such as news releases, public service announcements, and social media posts. At the same time, the Customer Experience organization initiated more than 1 million automated pre-recorded calls to inform customers about pre-storm preparations, safety, and medical guidance. To expand its social media presence, CL&P launched a Facebook page the Friday before the storm made landfall in Connecticut. Adding a Facebook page was a logical extension; CL&P had been using Twitter and YouTube since the year prior for a variety of topics. Facebook proved quite popular, people visited CL&P’s page more than 40,000 times and it attracted more than 8,000 “likes” before the end of the storm. Facebook became a place for customers to vent, however, it afforded CL&P opportunities to participate in the conversation and respond individually offline when necessary. More than 200 status updates were “tweeted” during the storm and NU Twitter followers grew substantially, from 2,000 to more than 6,300. CL&P added 11 widely viewed YouTube videos. April 16, 2012 The Liberty Consulting Group page 107
  9. Page 111 of 182

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 2 Page 111 of 182 Report on the Response of CL&P and UI to Storms in August and October 2011 In total, CL&P’s Corporate Communications issued 13 news releases prior to and during storm Irene. The following table summarizes the information released by Corporate Communications regarding the number of customers without power:152 Date August 25 August 26 August 27 August 28 August 28 August 29 August 30 September 2 September 3 September 4 September 4 September 5 September 6 Title As Hurricane Irene Strengthens, CL&P is Getting Ready — Are You? You Just Bought a Home Generator. Now What? CL&P Opens Emergency Operations Center CL&P Scheduling Crews for Around the Clock Restoration CL&P Deploys All Available Crews to Begin the Restoration Effort CL&P Restores Power to Over 288,000 Customers in 24 Hours CL&P Continues to Make Significant Progress in Restoring Power CL&P Alert to Homeowners CL&P Announces Customer Relief Efforts and $1 mil Storm Recovery Donation Restoration Continues Through Holiday Weekend 99 Percent of CL&P Customers Have Power CL&P Expects to Complete Restoration by Tuesday Nearly All CL&P Customers Affected by Irene Have Power CL&P’s Corporate Communications issued a post-storm news release on September 11, 2011, “CL&P Senior Executive to Lead Post-Storm Municipal Interface Initiative.” CL&P has well-established relations with the media and often welcomes media crews into the Emergency Operations Center (EOC) during storms to film segments. This practice continued through both storms. During storm Irene, CL&P introduced Skype (Internet Video-conferencing) to enable NBC affiliates to conduct EOC-based interviews remotely. This gave the media a chance to “humanize” the story without having to send a reporter. It expanded this practice during the snowstorm. CL&P also actively encouraged media participation in twice-daily press conferences, on-location coverage, and one-on-one’s with executives. To gather material for media and public dissemination, Corporate Communications embedded a communications lead in the EOC. CL&P has established a communications room located just outside the EOC with a view of the EOC. This room is equipped with flat-screen TVs to let the communications liaison monitor news reports, weather, and keep an eye on the EOC. Communications coordinator also participated in the EOC conference calls. Communications conference calls were scheduled following the EOC calls to relay information to the Communications team leads and others. Communications also worked closely with the Customer Experience Director embedded in the EOC to craft upfront IVR messaging and outbound calling campaigns. Additionally, Corporation Communications personnel were also instrumental in packaging EOC information updates into “talking points” for the Contact Center employees. 152 c-lp.com website. April 16, 2012 The Liberty Consulting Group page 108
  10. Page 112 of 182

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 2 Page 112 of 182 Report on the Response of CL&P and UI to Storms in August and October 2011 Both Corporate Communications and CE Communications Coordinator also worked closely with the Town Liaison Coordinator to tap into town-level storm status, conditions, and needs. During a storm, each Town Liaison is charged to work closely with town emergency officials and local operations to create daily town plans and priorities. This information would then be incorporated into CSR talking points and other internal communications. The CL&P Emergency Response Plan includes a chapter dedicated to Communications. More detailed emergency communications procedures are documented in the Emergency Response Plan’s Index of Operating Procedures (M3-EP-1001).153 In addition, Corporate Communications maintains an EOC Media Book and other storm procedures and checklists for major storm communications activities.154 As defined in the ERP, Corporate Communications assigns a Communications Manager to the EOC to develop strategies for communication and media relations activities. The Media Liaison reports to the Communications Manager and is responsible for coordinating the activities of Corporate Communications personnel engaged in media contacts and media relations, social networking and employee communications. While CL&P issued press releases on a daily basis, the releases did not communicate restoration estimates until five days into the storm (September 4), at a point when 98 percent of customers had already been restored. This placed pressure on other communications channels, such as the contact center, website, and social media to provide more detailed estimates. The following table summarizes the message presented in each release, as well as the projected restoration times. August 25 August 26 August 27 August 28 August 28 August 29 August 30 September 2 September 3 September 4 September 4 September 5 September 6 Message in News Release Anticipated Restoration Date Preparedness Pre-storm Safety Pre-storm Crews on standby Pre-storm 650,000 out, storm in-progress No estimate No estimate 622,000 out, crews deployed 515,300 out No estimate 354,000 out No estimate Alert: Customer-owned equipment damage No estimate Storm fund donation No estimate 98% Have power; 27,000 out 99% by midnight Mon 99% Have power; 11,600 out 100% by midnight Wed 2,300 out 100% by Tuesday 100 out No estimate After storm Irene, Corporate Communications updated storm communications materials, including media contacts. 153 154 Response to Liberty-064. Response to Witt-021. April 16, 2012 The Liberty Consulting Group page 109

Text of EOE-383 Attachment 3.pdf

Extracted from the file · 55 pages · 132,814 characters

Text of EOE-383 Attachment 4.pdf

Extracted from the file · 2 pages · 4,635 characters

Text of EOE-383 Attachment 5.pdf

Extracted from the file · 7 pages · 11,175 characters

As listed on the current system

Question(s) Answered 379, 380, 381, 382, 383 (Connecticut Light and Power Company dba Eversource Energy) Date Filed: 10/27/2026

This filing on the current system (opens in a new tab)