Interrogatory responses

Answers to questions 379, 380, 381, 382, 383

ResponseFiled by Connecticut Light and Power Company dba Eversource Energy11 files
Part of docket 26-05-10Open
  • Electric
Application of The Connecticut Light and Power Company d/b/a Eversource Energy to Amend its Rate Schedules

Files11

Search terms highlighted
Eversource rate increase is on 18 pages across 3 files of the text below, highlighted. Go to the first matchClear highlighting
Words on different pages
Words on different pages
Words on different pages

Text of EOE-381_Final.pdf

Extracted from the file · 2 pages · 3,490 characters

Words on different pagesRead the text of EOE-381_Final.pdf

Text of EOE-382_Final.pdf

Extracted from the file · 1 page · 2,648 characters

Words on different pagesRead the text of EOE-382_Final.pdf

Text of EOE-383_Final.pdf

Extracted from the file · 4 pages · 10,383 characters

Words on different pagesRead the text of EOE-383_Final.pdf

Text of EOE-383 Attachment 1.pdf

Extracted from the file · 125 pages · 401,903 characters

5 pages match
  1. Page 133 of 182

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 2 Page 133 of 182 Report on the Response of CL&P and UI to Storms in August and October 2011 CL&P should also formalize the process to secure and train employees to serve as Town Liaisons such that there are sufficient well-trained resources that have had enough opportunity to establish a relationship with the town they are serving. X-CL&P-4 Pursue technology enhancements that will facilitate real-time updates of restoration status information into the outage system. During large outage events, CL&P should equip its damage assessors and restoration crews (and foreign crews) with mobile data terminals, laptops, or other devices that can communicate and interact with the outage system or develop a real-time process wherein outage information is communicated from the field to a skilled EDS user in a dispatch office, operating center, or other location using cellular telephone, radio or other communications device. This will improve the likelihood that EDS trouble order data is updated in a timely manner. (Also refer to recommendations in chapter IX.) X-CL&P-5 Develop specific, measurable goals and objectives for improving the accuracy and timeliness of outage related information provided to its constituents. CL&P will undoubtedly experience additional outages in the future and should develop goals and objectives to improve the accuracy of estimated restoration times. CL&P should begin measuring and tracking the accuracy of Estimated Restoration Times (ERTs) as compared to actual restoration time, both on a day-to-day basis and during major outage events. CL&P should revise outage communication procedures to provide more emphasis on the importance of providing accurate and timely estimates to customers. Procedures should include documenting the Estimated Restoration Time originally provided to customers as well as a requirement to provide on-line an updated estimate prior to expiration of any existing estimate. It should offer an explanation to the customer if the estimate changes. During each outage, CL&P should record a complete history of Estimated Restoration Times given to each customer. Finally, CL&P should implement goals to communicate better with constituents in the aftermath of outages. It should analyze customer complaints to determine whether it is improving its accuracy in estimating restoration times. Debriefing sessions should be held with all involved employees, including crews, customer service representatives, and communications personnel. The Company should also hold meetings with city and town officials, other government agencies, and the media to review ERT accuracy after large storms. B. UI 1. Customer Contact Center Operations UI’s Client Fulfillment organization provides services to support customer inquiry, meter reading, billing, collections, and field services. UI’s Customer Care Center (CCC), located in New Haven, is supported by Aspect ACD and IVR technologies. The Aspect ACD is connected through tie lines to UI’s enterprise Cisco Call Manager telephone system. During storms, April 16, 2012 The Liberty Consulting Group page 130
  2. Page 134 of 182

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 2 Page 134 of 182 Report on the Response of CL&P and UI to Storms in August and October 2011 customers can use the IVR system to automatically report a power outage or service emergency and receive an estimated restoration time if available. UI also uses an Aspect Unified IP system for outbound dialing campaigns. UI also maintains production Aspect ACD and IVR systems at its Data Center for business continuity and disaster recover purposes.175 UI staffs its CCC to handle customer calls from 7:00 am to 7:00 pm, Monday through Friday, and from 7:00 am to 4:00 pm on Saturdays. During these business hours, call center representatives handle customer calls relating to service, billing and collections, and calls to report power interruptions. Upon calling UI’s toll-free number customers enter the Automatic Call Distributor (ACD) and hear a company greeting and outage messaging (if activated). Calls then proceed to the IVR for call classification and self-service. Callers requesting to speak with an agent are transferred to an agent queue. Emergency calls (reporting gas odor or downed wires) received at any time of the day are immediately queued to an agent group. Otherwise, all other call types will request authentication to provide self-service options or additional account information. At any point in the call flow, in the IVR or the ACD, customers can abandon their call. Calls from police and fire officials are normally routed to a dedicated phone line in the System Operations Center (SOC). During a storm, UI 911 call takers handle these calls, working under the direction of the Wire Down storm lead. Reports of downed wires and other emergencies will be entered into the Outage Management System (OMS) and prioritized for dispatch.176 Tropical Storm Irene Response The Customer Care Center storm plan is integrated into UI’s Emergency Preparedness Plan filed with PURA on December 1, 2011. The section that includes the Customer Service lead roles, job responsibilities, and position checklists is in Appendix 9, Operations. The plan designates lines of authority, provides an overview of the process, describes roles and responsibilities, and includes roles-based procedural checklists. During an emergency, the Customer Service Lead reports to the Operations Team leader and is responsible for Customer Care Center operations and readiness of a back-up call center site, should UI need it. The Customer Service Lead coordinates closely with the Operations Team Leader to determine when to expand or extend shifts. The Customer Service Lead is supported by the Customer Care Center Lead who supervises and schedules CSRs and manages call volume and customer needs. UI’s Customer Care Center organization undertook numerous measures in preparation during the week leading up to projected landfall:177 • Dedicated phone line was set up for call center employees to get updates concerning work schedules during the storm and employee’s on-call contact information was updated • The alternative business continuity call-center site in Shelton, CT was tested and made ready in the event that call center resources needed to be relocated. 175 Response to Liberty-55. Response to OCC-166. 177 Response to CSU-001 and AR-Liberty-48. 176 April 16, 2012 The Liberty Consulting Group page 131
  3. Page 135 of 182

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 2 Page 135 of 182 Report on the Response of CL&P and UI to Storms in August and October 2011 • • • • • • • • • • Additional headsets were ordered. Training resources were secured and scheduled to train non-traditional call center personnel to assist with outage calls as needed. The Facilities group was contacted to secure food, hotel rooms, and inflatable mattresses for Customer Care. Union leadership was contacted to review the storm-staffing plan. Staffing plans and schedules were shared with employees. Alternate call center site was prepared for potential use. The Customer Care Center was provided with information that included the list of municipal liaisons that were assigned to each town throughout the storm event. On August 27, 2011, an outbound message was placed to more than 4,000 UI customers coded as “medical” to advise them of the importance of having a back up plan in the event of an extended power outage. In addition, customers were advised that additional assistance would be available from Infoline at 211 or the American Red Cross. A dedicated escalation line from the Customer Care Center to the Storm Center in Shelton was established in the event the center needed assistance with an escalated issue. Communications plan was set up for updates to customers throughout the storm. All Customer Care employees were scheduled to begin work at 6:00 am on Sunday, August 28, 2011, based on the estimated storm arrival. UI scheduled a small crew to arrive at 1:00 am that morning, in the event there were outages in the early stages of the storm. Employees were gradually released later on Sunday evening as the call volume reduced, with a small crew remaining overnight.178 Starting Monday, August 29, 2011, all Customer Care employees were assigned to rotating 12hour schedules for the week to ensure 24x7 coverage throughout the storm. Training continued as needed to prepare additional resources to supplement outage call handling in the Customer Care Center.179 On August 31 and again on September 3, in cooperation with many of the towns in its territory, UI conducted additional outbound calling campaign to medical customers to provide the appropriate number to call for assistance within their respective towns.180 Customer Care employees were provided with key information and talking points daily to assist when handling customer inquiries. Some of this information included:181 • Directing customers to the Red Cross, 211, or their towns for assistance as needed • Number of crews and crew locations • Restoration time availability • Number of outages by town 178 Response to CSU-1 Response to CSU-1 180 Response to CSU-1 181 Response to CSU-1 179 April 16, 2012 The Liberty Consulting Group page 132
  4. Page 136 of 182

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 2 Page 136 of 182 Report on the Response of CL&P and UI to Storms in August and October 2011 • Press release information UI closed for normal business starting on Sunday August 28, 2011, as it focused on storm damage assessment and restoration efforts. UI instructed Customer Care CSRs to handle only emergency calls. UI resumed normal business operations on Tuesday, September 6.182 The following upfront message was played to callers in the first 2 days of the storm183: We are aware of the many outages in our area and our restorations crews are working around the clock. The focus to this point has been to take actions to ensure public safety. Currently, we are not able to provide restoration times. We appreciate your understanding and patience during this difficult time. Please stay on the line if you are calling to report an emergency or if your call is of an urgent nature. Thank you. UI received close to 200,000 calls during Tropical Storm Irene. More than 60 percent were handled through UI’s Interactive Voice Response (IVR) system. UI’s call center representatives handled more than 65,000 calls during the storm, with an average speed of answer of 148 seconds.184However, more than 14 percent of callers abandoned over the course of the storm, with the heaviest abandoning on August 31. 185 Many customers encountered busy signals throughout the storm. More than 150,000 busy signals were delivered to callers over the course of the storm, many more than actually got through to the company on several days.186 182 Response to CSU-5. Response to OCC-157. 184 Response to CSU-4. 185 Response to CSU-4. 186 Response to CSU-2-1.xls. 183 April 16, 2012 The Liberty Consulting Group page 133
  5. Page 137 of 182

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 2 Page 137 of 182 Report on the Response of CL&P and UI to Storms in August and October 2011 From Sunday, August 29 to Monday, August 30, it was determined that accurate restoration times were not available due to the severity of the storm. UI placed a message sharing this information on its IVR system to be heard as soon as the customers called in. The intent of this message was to minimize any inconvenience to customers who were calling in for restoration times. From Tuesday, August 31 through Saturday, September 3, restoration times were available for some customers and the IVR message was updated accordingly.187 The above chart details the peak staffing for each day of Tropical Storm Irene. UI’s CCC was able to secure considerable staffing to handle incoming calls during the storm, especially coverage over the initial weekend.188 Following the storm, UI conducted a final outbound calling campaign to all customers: This is a message from The United Illuminating Company, to our valued customers. On Sunday August 28th, the State of Connecticut experienced one of the worst weather events since Hurricane Gloria in 1985. As New Englanders we demonstrated our resolve and resilience when federal, state, and local government agencies partnered with the state utilities to clear streets and restore power. On behalf of the more than eighteen hundred employees of The United Illuminating Company, The Southern Connecticut Gas Company, Connecticut Natural Gas Corporation and The Berkshire Gas Company we would like to extend our gratitude to our customers for their understanding and cooperation during the recovery period.189 In retrospect, UI’s contact center struggled throughout the storm, even with near-peak staffing in place before the storm hit. Many customer calls were blocked due limited capacity in the Customer Care Center and the lack of an overflow IVR provider. Additionally, many customers experienced long wait times to speak with a CSR. 187 Response to CSU-1 Response to CSU-002. 189 Response to OCC-147. 188 April 16, 2012 The Liberty Consulting Group page 134
  6. Page 138 of 182

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 2 Page 138 of 182 Report on the Response of CL&P and UI to Storms in August and October 2011 October Snowstorm Response UI did not have as much time to prepare for the October snowstorm. Customer Care participated in a storm planning call at noon on Friday, October 28, 2011. Starting Friday afternoon, UI began to supplement staffing for the weekend. It added 15 CSRs to the normal Saturday afternoon schedule. The Company did not place any outbound calling campaigns to medical customers prior to the October 29 snowstorm.190 On Saturday afternoon, management began the call in process for additional Customer Care resources when call volumes climbed. Management had difficulties securing enough additional CSRs. It made the decision to call in employees as the number of outages climbed and conditions worsened. Unfortunately, worsening conditions also made it challenging for employees to get to the contact center. As a result, the UI’s Customer Care Center’s staffing levels were at their lowest during the highest volume of calls. Many customers experienced busy signals. Those able to get through waited on average 15 minutes to get to an agent.191 Once the Customer Care management team had exhausted its resources, it reached outside the department to secure additional resources (union and management personnel). Management continued to call in employees on Sunday night in an effort to secure resources for Monday morning. Long wait times were experienced again on Sunday morning, with an average wait ranging from 15 to 30 minutes. Customers also received busy signals as UI’s incoming telephone trunks filled up. On Monday, UI was finally able to fully staff the Customer Care Center. Ramping up to full staffing proved to be a lengthy and onerous process. UI assigned employees to rotating 12-hour schedules for the week to ensure 24x7 coverage throughout the storm. An internal Storm Center Hotline number was also established in the EOC to assist with escalated calls.192 190 Response to OCC-147. Response to AR-Liberty-48. 192 Response to AR-Liberty-48. 191 April 16, 2012 The Liberty Consulting Group page 135
  7. Page 139 of 182

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 2 Page 139 of 182 Report on the Response of CL&P and UI to Storms in August and October 2011 UI’s Customer Care Center did not reach peak staffing until the 3rd day of the storm. The following upfront message played to alert callers to the storm and possible long wait times during the first two days of the storm193: We are aware of the many outages in the area due to the storm, and are currently experiencing longer than normal wait times to speak to a representative. We appreciate your understanding and patience during this time. Please stay on the line if you are calling to report an emergency or if your call is of an urgent nature. Thank you. As with storm Irene, UI closed for normal business on Monday as it focused on storm damage assessment and restoration efforts. This included suspending service disconnects and instructing CSRs to handle only emergency calls. The Contact centers returned to full operations on Wednesday, November 2. On Saturday and Sunday, UI had received 38,000 customer calls. By the end of the storm, UI’s Customer Care Center CSRs handled nearly 20,000 calls, with an average speed of answer of 216 seconds. An additional 35,000 calls self-served in UI’s IVR.194 However, more than 14 percent of callers abandoned over the course of the storm, with the heaviest abandoning on Saturday, the first day of the storm.195 In addition, many UI customers encountered busy signals throughout the October snowstorm. Callers received more than 150,000 busy signals over the course of the storm, many more than actually got through to the company on the first two days of the storm, as depicted by the line on the following chart.196 193 Response to OCC-157. Response to CSU-20. 195 Response to CSU-19-1.xls. 196 Response to CSU-2-1.xls. 194 April 16, 2012 The Liberty Consulting Group page 136
  8. Page 140 of 182

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 2 Page 140 of 182 Report on the Response of CL&P and UI to Storms in August and October 2011 Call answering performance, as defined by wait time, also suffered during the first two days of the storm197 Shortly following storm Irene, UI contracted with a third party to survey residential customers regarding their experiences with UI during the storm. More than 86 percent surveyed “strongly agreed” or “somewhat agreed” that UI worked very hard to restore power as soon as possible following the storm. Seventy-five percent were either “very satisfied” or “somewhat satisfied” with UI’s handling of customers during the storm. Of those not satisfied, 39 percent indicated they would have liked power back sooner, 23 percent expressed difficulties communicating with the company, and 11 percent sited a lack of restoration estimates. Only half of respondents 197 Response to CSU-20. April 16, 2012 The Liberty Consulting Group page 137
  9. Page 141 of 182

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 2 Page 141 of 182 Report on the Response of CL&P and UI to Storms in August and October 2011 reported being “very aware” or “somewhat aware” of restoration priorities for UI when an outage occurs.198 UI’s Customer Care Center has several opportunities to improve operations so that it is better prepared to handle customer calls in future large outage events. Liberty discusses these opportunities in the Recommendations section at the end of this section. 2. Corporate Communications In the days leading up to storm Irene, UI held internal meetings with its storm team and within communications specifically to begin planning communications strategies based on the storm track and its potential impact on UI’s service territory. Once it was clear that customers would be affected, UI immediately began implementing its communications strategy. Prior to and during Irene, UI proactively reached out to the media and public with customerfocused communications, such as news releases, public service announcements, and social media posts. At the same time, the Customer Care Center organization initiated several automated prerecorded calling campaigns to notify customers of pre-storm preparations, safety, and medical guidance. UI also provided half-day safety presentations at the New Haven Regional Fire Training Academy during the week before the storm, to refresh first responder safety around downed wires and other electrical equipment.199 During the storm, the Company held joint press conferences with CL&P and participated in Governor Malloy’s press briefings. UI’s media hotline was open and company representatives provided media interviews as requested. UI issued 14 news releases prior to and during Irene and responded to 106 media inquiries, including 32 interviews on the first day of the storm.200The following table lists the news releases prior to and during the storm:201 Date August 25 August 26 August 28 August 28 August 29 August 29 August 30 Title As Hurricane Irene Approaches, UIL Holdings Corporation Helps Customers Prepare Storm Checklist & Preparation Tips UIL Holdings Corporation Urges Customers to Put Safety First as Hurricane Restoration Efforts Get Under Way UIL Holdings Corporation Continues Restoration Efforts UIL Holdings Corporation Expects Significant Progress with Post‐Hurricane Restoration Efforts Monday UIL Holdings Corporation Post‐Hurricane Restoration Update The United Illuminating Company Reports More Progress; Estimated Restoration Times Discussed 198 Response to AR-Liberty-31-1. uinet.com website, August 25, 2011 Press Release. 200 Response to CSU-8. 201 uinet.com website. 199 April 16, 2012 The Liberty Consulting Group page 138
  10. Page 142 of 182

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 2 Page 142 of 182 Report on the Response of CL&P and UI to Storms in August and October 2011 August 31 September 2 September 2 September 2 September 3 September 5 September 4 UI Hopeful Outages Can Be Reduced to 10,000 during the Weekend The United Illuminating Company Announces $50,000 in Relief Grants UI Expects to Restore Virtually All Remaining Outages this Weekend Outage Numbers Continue to Drop as CL&P and UI Push Restoration Efforts UI’s Restoration Efforts Nearing Completion Major Restoration Complete for UI An Open Letter to Our Customers On September 20, UI issued a press release to announce results of a residential post-storm survey. Nearly three-quarters of survey respondents reported hearing or seeing media reports or information about the progress of storm restoration, including the number of customers without power, however only 38 percent reported the media impacts had a “positive impact” while another 34 percent indicated the media reports had “no impact, but perception remained good.” When asked how respondents preferred to be contacted by UI during a storm, nearly 60 percent indicated by phone. Radio and TV were the next preferred channels, followed by text messaging and emails.202 Since the March 2010 storm, UI took steps to strengthen its customer and media communications:203 • UI hired a new Director of Corporate Communications in June 2010. • New processes were put in place to manage media relations • Additional communications strategies were developed to communicate to customers and the public. • UI delivered more targeting storm preparation and safety information messaging to customers through its monthly billing inserts. UI’s storm communications plan is integrated into the UI Emergency Preparedness Plan. Several subsections of the EPP address emergency communications, communications preparedness, and public communications. Specific elements and processes of the communications plan are referenced in Appendix 4, Liaison and Appendix 3, Public Information. The plan includes lines of authority, roles and responsibilities, procedural checklists, matrices to guide incident-level communications and recommended staffing levels for each storm duty role based on the severity of the storm. Sample communications log forms are also included as well as recommended equipment, tools, and supporting systems, scaled to the storm severity. Additionally, UI embeds more than a dozen communications professionals in the UI Storm Center during a large storm, including:204 • Two Liaison Team Leaders: responsible for all communications activities and coordination with public agencies and the media. • Six Municipal Liaison Team Coordinators: responsible for coordinating communication among the municipal liaisons. 202 Response to AR-Liberty-2. Response to AG-12. 204 Response to AG-149. 203 April 16, 2012 The Liberty Consulting Group page 139

Text of EOE-383 Attachment 3.pdf

Extracted from the file · 55 pages · 132,814 characters

Text of EOE-383 Attachment 4.pdf

Extracted from the file · 2 pages · 4,635 characters

Text of EOE-383 Attachment 5.pdf

Extracted from the file · 7 pages · 11,175 characters

As listed on the current system

Question(s) Answered 379, 380, 381, 382, 383 (Connecticut Light and Power Company dba Eversource Energy) Date Filed: 10/27/2026