Skip to main content

A prototype public docket site for the Connecticut Public Utilities Regulatory Authority

Utility Dockets and Filings

Interrogatory responses

Answers to questions 379, 380, 381, 382, 383

ResponseFiled by Connecticut Light and Power Company dba Eversource Energy11 files
Part of docket 26-05-10Open
  • Electric
Application of The Connecticut Light and Power Company d/b/a Eversource Energy to Amend its Rate Schedules

Files11

Search terms highlighted
Eversource rate increase is on 18 pages across 3 files of the text below, highlighted. Go to the first matchClear highlighting
Words on different pages
Words on different pages
Words on different pages

Text of EOE-381_Final.pdf

Extracted from the file · 2 pages · 3,490 characters

Words on different pagesRead the text of EOE-381_Final.pdf

Text of EOE-382_Final.pdf

Extracted from the file · 1 page · 2,648 characters

Words on different pagesRead the text of EOE-382_Final.pdf

Text of EOE-383_Final.pdf

Extracted from the file · 4 pages · 10,383 characters

Words on different pagesRead the text of EOE-383_Final.pdf

Text of EOE-383 Attachment 1.pdf

Extracted from the file · 125 pages · 401,903 characters

5 pages match
  1. Page 173 of 182

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 2 Page 173 of 182 Report on the Response of CL&P and UI to Storms in August and October 2011 Toolworkers per 1,000 Customers Out At Peak The number of linemen working on UI property in response to Irene was significantly lower than the others measured. UI experienced the same problem that CL&P did in getting outside help in the early stages of the storm, but the low lineman staffing was a hindrance to a timely restoration. 2. UI Lineman staffing The chart below 255 depicts the UI lineman staffing over the past five years. The number of linemen has increased by 9 percent in this time period. 255 UI response to audit request OCC – 163 April 16, 2012 The Liberty Consulting Group page 170
  2. Page 174 of 182

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 2 Page 174 of 182 Report on the Response of CL&P and UI to Storms in August and October 2011 UI Lineman Staffing 2007 – 2011 Liberty analyzed the UI lineman staffing on the basis of total customers served, comparing UI to both CL&P and a composite of others. UI has a very compact service area with high customer density, which explains the disparity. April 16, 2012 The Liberty Consulting Group page 171
  3. Page 175 of 182

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 2 Page 175 of 182 Report on the Response of CL&P and UI to Storms in August and October 2011 Utilities determine line worker staffing based on normal revenue and maintenance workload, routine storm response requirements, and other factors such as productivity and process improvements. In a major outage event, a successful response depends on a number of factors such as a good plan, the recruitment and early deployment of adequate numbers of outside workers, and good processes to manage this workforce. The UI lineman staffing level was not a factor in their response to Irene and the October storm. 2. Restoration Practices The UI service area had three geographic areas – West, Central, East – for the Irene response. Each area contained five to six towns. The purpose in doing this was for control – UI kept its crews separate from other types of crews. UI does not mix its crews with contractors. UI crews were in one area, “internal contractors” (those who work on UI property on a full-time basis) were in another area, and Mutual Assistance crews from other utilities and “external contractors” worked in the third area. Crews worked directly out of EOC. Crew leaders would work with crews and report in at the EOC.256 UI assigned dispatchers at the SOC to work with certain groups of crews that had been assigned specific towns or circuits. Dispatchers had separate work areas so that they would not conflict with each other. UI operators handled switching at the System Operating Center (SOC), and did this when repair crews were on site and could take clearance. It did not do switching during the night in preparation for the crews the next day. UI restoration priorities were: 1) municipal priorities – downed wires, road clearing; 2) backbone feeders, and 3) side taps, based on largest number of customers. In those cases where it assigned a circuit, they picked up everything but services, and then moved to work orders with the most customers. UI followed the philosophy of assigning orders based on numbers of customers as opposed to assigning crews to circuits. On a few occasions, it assigned a crew to a circuit, but that was the exception.257 UI used local electricians to pick up services or coil them and tack them to the pole. This is a best practice that more utilities should follow. UI also engaged contractors to go into the flooded area. The UI process for restoration status updates was manual. A crew called in when it completed orders and UI updated the outage management system (OMS) at the work center. UI expedited this call-in process by assigning dispatchers to work with a specific work area. UI served meals at local restaurants at pre-determined times. If a crew was still out working, UI made accommodations on a case- by-case basis. There were three staging sites, and trucks were tied up there and refueled at night. UI transported workers to their lodging. The longest trip was eight to eleven miles. Breakfast was served at one staging site; other workers got breakfast at the restaurants at their lodging.258 256 UI Interview #11, February 8, 2012, and UI Interview #15, January 10, 2012 UI Interview #13, February 9, 2012 258 UI Interview #7, January 20, 2012 257 April 16, 2012 The Liberty Consulting Group page 172
  4. Page 176 of 182

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 2 Page 176 of 182 Report on the Response of CL&P and UI to Storms in August and October 2011 UI’s practice and experience in the “Cut/Clear, Make Safe” process was the same as at CL&P. They furnished a tree crew and a line crew to a town upon request. UI told crews to go and work with towns and do what they could. UI says wires were down all over, and created an issue of public safety. UI assigned two crews to each town (1 line, 1 tree crew). New Haven had three crews. UI has not analyzed the effect on restoration time. 259 3. Restoration Performance The line graph below compares the restoration rate during Irene for UI, CL&P, and a composite of nine utilities that responded to recent hurricanes. The UI restoration rate was slower than the other two. The issues covered above are the primary reason for this slower rate. 4. 1. Conclusions UI did not bring in enough line workers in its Irene response, and this extended the restoration time, but the UI normal line worker staffing is not a concern. (See recommendations in Chapter VIII) The number of linemen working on UI property in response to Irene was significantly lower than the others measured. UI experienced the same problem that CL&P did in getting outside help in the early stages of the storm, but the low lineman staffing was not a hindrance to a timely 259 UI Interview #6, January 9, 2012 April 16, 2012 The Liberty Consulting Group page 173
  5. Page 177 of 182

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 2 Page 177 of 182 Report on the Response of CL&P and UI to Storms in August and October 2011 restoration. UI’s service area is compact and has high customer density, thus requiring fewer linemen on a per customer basis. 2. UI did a good job in field restoration, but there are a number of improvement opportunities. (See Recommendations 1 - 3) UI assigned dispatchers at the SOC to work with certain groups of crews that had responsibility for specific towns or circuits. Dispatchers had separate work areas so that they would not conflict with each other. UI used local electricians to pick up services or coil them and tack them to the pole. UI also engaged contractors to go into the flooded area. There were three staging sites, and trucks were tied up there and refueled at night. UI used daily reports that crews turned in at the end of the workday, but had difficulty in getting status updates during the day. This affected the situational awareness of the response leadership on an ongoing basis during the day. The majority of districts moved crews around, assigning orders based upon number of customers affected. In major events such as Irene and the October snowstorm, assigning work in this method can cause inefficiencies and delay the restoration. UI management did not have proper control over the “Cut/Clear, Make Safe” work done with the towns. UI followed the philosophy of assigning orders based on numbers of customers as opposed to assigning crews to circuits. On a few occasions, UI assigned a crew to a circuit, but that was the exception. UI’s practice and experience in the “Cut/Clear, Make Safe” process was the same as at CL&P. They furnished a tree crew and a line crew to a town upon request, but there was little management control over what the crews did and how long they stayed on that assignment. 3. The UI restoration rate during Irene was slower than it should have been. (See recommendations in Chapter VIII and Recommendations 1-3 below.) The UI rate was slower than that of CL&P, and considerably slower than other utilities that have responded to recent hurricanes. The primary reason is failure to bring in enough outside workers and to appropriately manage the “Cut/Clear, Make Safe” process. 4. XII-UI-1 Recommendations Strengthen the procedures for getting regular, timely restoration status updates from crews in the field. UI should remind all crews at regular intervals to send in status reports. UI may need crew aides to handle the reporting duties, and mobile data terminals should be in vehicles assigned to work with each crew. XII-UI-2 Change the restoration practice in major events such as Irene to limit the amount of time crews are moved from one circuit to another until work on the first circuit is completed. UI had no choice but to move crews around until additional help arrived, but assigning crews to a specific circuit in major outage events is a utility best practice. April 16, 2012 The Liberty Consulting Group page 174
  6. Page 178 of 182

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 2 Page 178 of 182 Report on the Response of CL&P and UI to Storms in August and October 2011 XII-UI-3 Work with the towns, other utilities, and emergency agencies to establish specific guidelines as to the work to be done in the “Cut/Clear, Make Safe” effort with the towns. There must be a clear understanding and agreement as to what the utility will do in this area. UI must train managers in this procedure, and top management must follow this during major outage restorations to ensure that all are following the guidelines and controlling the work. April 16, 2012 The Liberty Consulting Group page 175
  7. Page 179 of 182

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 2 Page 179 of 182 Report on the Response of CL&P and UI to Storms in August and October 2011 XIII. Post-storm Activities There are three primary three post-event activities, ramp-down, clean-up, and post-event critiques. Ramp-down includes releasing outside crews, de-activating storm command centers, and moving back into the normal routine. Clean-up is performing patrols, tree trimming, and line repairs as required to restore facilities to a reliable state. Post-event critiques include the lessonslearned process, and follow-up on the issues identified in this process. A. CL&P 1. Ramp-down CL&P’s ERP contains a good ramp-down procedure;260 CL&P followed it in both storms. As CL&P accomplished restoration in one area, it assigned resources to areas that still required additional assistance. Continued recovery and restoration activities result in a gradual demobilization of personnel and equipment. When recovery efforts reduced power outages across the CL&P system to manageable levels, the following actions occurred: • The NU System Commander and the Area Commander determined that a System/Area Emergency no longer exists. • Released Mutual Aid crews • Released contract crews • Released NU affiliated crews • Released support personnel • Dissolved System/Area/Division/District Command When recovery efforts are complete, the following actions occurred: • The District/Division/Area Commanders determine that a District, Divisional, or Area Emergency no longer exists. • Re-centralized dispatch functions to the SOC • Released line crews to their normal work locations • Dissolved Incident Command 2. Clean-up CL&P performed a thorough post-storm analysis for Irene and the October storm. This included contracting the assessment of approximately 17,000 miles of its overhead electric distribution system. This assessment involved a visual inspection from ground level of wires and poles, and the identification of vegetation management issues such as hazard trees. About 30 survey teams performed this work. Work continued to correct all items on a priority basis.261 260 261 CL&P ERP, Section 1, 5.6, pages 25 and 26 CL&P response to EL-12 April 16, 2012 The Liberty Consulting Group page 176
  8. Page 180 of 182

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 2 Page 180 of 182 Report on the Response of CL&P and UI to Storms in August and October 2011 3. Post-event critiques The CL&P ERP states that the company will conduct post-storm critiques at the district, division, and company levels and include a cross section of all departments involved in the restoration. After Irene, CL&P embarked on an enthusiastic effort to conduct thorough critiques and to meet with all of the 149 towns it serves through regional meetings. The CL&P Vice-President, Customer Operations, conducted in-person critiques in 21 different locations. As a result, CL&P did not complete the critiques within the thirty-day target set in the plan, and were just wrapping up the Irene critiques when the October snowstorm hit. The division managers conducted the critiques in 28 locations following the October storm. The critiques identified organizational strengths, opportunities for improvement, and captured lessons learned. Following the completion of the critiques, CL&P developed a list of action items to strengthen the CL&P Emergency Plan.262 Liberty heard some criticism of the critique process. One comment in particular seemed to sum up the concerns that were expressed: “Need to provide an open, honest forum on post-event critique “all the way to the ground floor.”263 4. 1. Conclusions – CL&P Post-storm Activities CL&P has a good plan for the post-storm activities, and performed well in all three of these areas. There is an opportunity for improvement in the postevent critiques. (See Recommendation 1) CL&P’s ERP contains a good ramp-down procedure; CL&P followed it in both storms. CL&P performed a thorough post-storm analysis for Irene and the October storm. After Irene, CL&P embarked on an enthusiastic effort to conduct thorough critiques and to meet with all of the 149 towns it serves through regional meetings. The CL&P Vice-President, Customer Operations, conducted in-person critiques in 21 different locations. The division managers conducted the critiques in 28 locations following the October storm. While the involvement of a senior officer in all post-Irene critiques is commendable, CL&P should review this decision and revise the procedure in future events to avoid the lengthy delay in completing the critiques. In addition, CL&P should aggressively seek input from response team leaders to improve the critique process. 5. Recommendations – CL&P Post-storm Activities XIII-CL&P-1 Revise post-event process to accomplish the mutual goals of senior management involvement and timely completion, and to make the critiques of more value to the response team. 262 263 CL&P interview #1, December 15, 2011, and response to Liberty audit request # 032 CL&P interview #37, January 6, 2012 April 16, 2012 The Liberty Consulting Group page 177
  9. Page 181 of 182

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 2 Page 181 of 182 Report on the Response of CL&P and UI to Storms in August and October 2011 B. UI 1. Ramp-down In Irene and the October snowstorm, UI followed the new post-event process contained in the December 1, 2011, EPP. Even though the plan was not completed or filed with PURA at the time of these two storms, it had reviewed and approved a number of the processes that it put into effect. This covered the process to transition from the Incident Management structure to normal operations, and the criteria for resuming normal operations. UI followed the EPP guidelines on releasing outside resources. 2. Clean-up After UI restored all of the areas affected by the storms to pre-storm operating conditions, it embarked on the clean-up phase. This included system wide inspection and remediation of the overhead distribution system. As storm restoration efforts were winding down, UI assigned resources to patrolling circuits in areas where no outages occurred to assess tree conditions that could lead to an outage and to identify damages to the overhead electric distribution system. UI has addressed this work on a priority basis.264 3. Post-event critiques UI also followed the 2011 EPP in performing post-event critiques. Each of the Incident Management organizations was responsible for conducting a post-incident performance review of its area of responsibility. UI made assignments to ensure follow-up. The Restoration Manager was responsible for ensuring that personnel completed these post-event critiques and that UI updated the EPP as appropriate. UI held post-storm critique meetings with representatives from all departments involved in the restoration process after both storms. All electric system operations managers along with supporting functional managers involved in the storm restoration participated in the critiques. UI held additional meetings with union participants representing each function involved with the restoration. UI prioritized the issues identified and are following up to complete them.265 4. 1. Conclusions – UI Post-storm Activities UI had a good plan for post-storm activities, and performed well in all three areas. In Irene and the October snowstorm, UI followed the new post-event process as contained in the December 1, 2011 EPP. This included the transition from the Incident Management structure to normal operations, and the criteria for resuming normal operations. UI followed the EPP guidelines on releasing outside resources. After restoring all of the areas affected in the storms to pre-storm operating conditions, UI embarked on the clean-up phase. This included system-wide 264 265 UI response to audit request EL-012 UI response to EL-10 April 16, 2012 The Liberty Consulting Group page 178
  10. Page 182 of 182

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 2 Page 182 of 182 Report on the Response of CL&P and UI to Storms in August and October 2011 inspection and remediation of the overhead distribution system. UI held post-storm critique meetings with representatives from all departments involved in the restoration process after both storms. UI prioritized the issues identified and are following up to complete them. 5. Recommendations – UI Post-storm Activities None April 16, 2012 The Liberty Consulting Group page 179

Text of EOE-383 Attachment 3.pdf

Extracted from the file · 55 pages · 132,814 characters

Text of EOE-383 Attachment 4.pdf

Extracted from the file · 2 pages · 4,635 characters

Text of EOE-383 Attachment 5.pdf

Extracted from the file · 7 pages · 11,175 characters

As listed on the current system

Question(s) Answered 379, 380, 381, 382, 383 (Connecticut Light and Power Company dba Eversource Energy) Date Filed: 10/27/2026

This filing on the current system (opens in a new tab)