Skip to main content

A prototype public docket site for the Connecticut Public Utilities Regulatory Authority

Utility Dockets and Filings

Interrogatory responses

Answers to questions 379, 380, 381, 382, 383

ResponseFiled by Connecticut Light and Power Company dba Eversource Energy11 files
Part of docket 26-05-10Open
  • Electric
Application of The Connecticut Light and Power Company d/b/a Eversource Energy to Amend its Rate Schedules

Files11

Search terms highlighted
Eversource rate increase is on 18 pages across 3 files of the text below, highlighted. Go to the first matchClear highlighting
Words on different pages
Words on different pages
Words on different pages

Text of EOE-381_Final.pdf

Extracted from the file · 2 pages · 3,490 characters

Words on different pagesRead the text of EOE-381_Final.pdf

Text of EOE-382_Final.pdf

Extracted from the file · 1 page · 2,648 characters

Words on different pagesRead the text of EOE-382_Final.pdf

Text of EOE-383_Final.pdf

Extracted from the file · 4 pages · 10,383 characters

Words on different pagesRead the text of EOE-383_Final.pdf

Text of EOE-383 Attachment 1.pdf

Extracted from the file · 125 pages · 401,903 characters

5 pages match
  1. Page 8 of 182

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 2 Page 8 of 182 Report on the Response of CL&P and UI to Storms in August and October 2011 VI-CL&P-3 VII-CL&P-1 VII-UI-1 VIII-CL&P-1 VIII-CL&P-2 VIII-CL&P-3 VIII-UI-1 VIII-UI-2 IX-CL&P-1 IX-CL&P-2 IX-CL&P-3 IX-UI-1 IX-UI-2 X-CL&P-1 X-CL&P-2 X-CL&P-3 X-CL&P-4 X-CL&P-5 X-UI-1 April 16, 2012 Activate the division command posts in all major outage events as set forth in its emergency plan............................................................................................ 66 Develop a checklist for winter storms similar to the one it has for hurricanes and use the event classification levels to guide preparations during the alert phase................................................................................................................. 73 Amend the EPP and change UI’s practice to ensure that it opens the EOC prior to the onset of major events. ............................................................................ 75 Work with EEI and other Mutual Assistance Groups to improve the present process, and work with PURA in an attempt to avoid problems such as the one involving a governor not allowing crews to leave his state. ............................ 80 Adopt an aggressive plan to avoid the mistakes made in Irene and the October snowstorm in requesting outside help. ............................................................. 80 Follow the deployment point process as outlined in the EPP when large numbers of outside resources are incoming. .................................................... 81 Work with EEI and other Mutual Assistance Groups to improve the present process, and work with PURA in an attempt to avoid problems such as the one involving a governor not allowing crews to leave his state. ............................ 82 Join other mutual assistance groups................................................................. 83 Develop a process to use damage assessment information in a statistical manner for overall crew resource-requirement projections. ............................ 90 Improve the damage assessment processes at the district level. ...................... 90 Reinforce aggressively the need for accurate, timely damage and restoration updates from the field....................................................................................... 90 Develop a process to use damage assessment information in a statistical manner for overall crew resource-requirement projections. ............................ 93 Verify that the 2011 EPP adequately covers restoration status updates, and address the issues identified during the two storms. ........................................ 93 Create a call center staffing model to facilitate quick ramp-up and consider staging agents in nearby hotels in preparation for a large storm, especially one that makes travel to the center difficult or unsafe. ......................................... 129 Redesign the interface between the call center technologies and Twenty First Century Communications to improve communications with customers during a large outage or storm...................................................................................... 129 Enhance the Town Liaison program to create a more coordinated and consistent approach to keeping community leaders and municipal officials better informed of storm restoration status. ................................................... 129 Pursue technology enhancements that will facilitate real-time updates of restoration status information into the outage system.................................... 130 Develop specific, measurable goals and objectives for improving the accuracy and timeliness of outage related information provided to its constituents..... 130 Create a call center storm staffing process to facilitate quick ramp-up of call takers during a large outage. .......................................................................... 152 The Liberty Consulting Group page 5
  2. Page 9 of 182

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 2 Page 9 of 182 Report on the Response of CL&P and UI to Storms in August and October 2011 X-UI-2 X-UI-3 X-UI-4 X-UI-5 XI-CL&P-1 XII-CL&P-1 XII-CL&P-2 XII-CL&P-3 XII-CL&P-4 XII-UI-1 XII-UI-2 XII-UI-3 XIII-CL&P-1 April 16, 2012 Redesign call center technology to improve communications with customers during a large outage or storm. ...................................................................... 152 Rigorously test call-handling technology, website, and Outage Management System to ensure the technologies operate to expectations and specifications. ........................................................................................................................ 153 Enhance the Municipal Liaison program to create a more consistent approach to keeping community leaders and municipal officials better informed of storm restoration status. ........................................................................................... 153 Pursue technology and process enhancements that will facilitate real-time updates of restoration status information in the outage system and enable more timely ETRs. .................................................................................................. 153 Reduce the number of support functions assigned to Area Logistics. (See also Chapter VI, Recommendation 2) ................................................................... 156 Strengthen procedures for getting regular, timely restoration status updates from crews in the field. .................................................................................. 168 Change the restoration practice in major events such as Irene and the October storm to limit the amount of time crews are moved from one circuit to another until work on the first circuit is completed. ................................................... 168 Assign crews to specific circuits in a major outage event. ............................ 168 Work with the towns, other utilities, and emergency agencies to establish specific guidelines as to the work to be done in the “Cut/Clear, Make Safe” effort with the towns. ..................................................................................... 169 Strengthen the procedures for getting regular, timely restoration status updates from crews in the field. .................................................................................. 174 Change the restoration practice in major events such as Irene to limit the amount of time crews are moved from one circuit to another until work on the first circuit is completed................................................................................. 174 Work with the towns, other utilities, and emergency agencies to establish specific guidelines as to the work to be done in the “Cut/Clear, Make Safe” effort with the towns. ..................................................................................... 175 Revise post-event process to accomplish the mutual goals of senior management involvement and timely completion, and to make the critiques of more value to the response team. ................................................................... 177 The Liberty Consulting Group page 6
  3. Page 10 of 182

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 2 Page 10 of 182 Report on the Response of CL&P and UI to Storms in August and October 2011 II. Emergency Plans A. Background “Plan your work and work your plan,” is never more applicable than with the response of a utility to a major outage event. While all utilities have experience in responding to common outages, a major outage event brings more and greater challenges in both degree and complexity. For any utility to respond appropriately, it must begin with a comprehensive, user-friendly emergency plan. A comprehensive plan addresses all aspects of the response process beginning with pre-event activities, covering all aspects of the restoration, and concluding with the postevent period. It also addresses major outage events other than those related to storms, such as floods, catastrophic facility or equipment failures, overload emergencies, and terrorist activities. In addition to being user-friendly, a plan must be readily accessible to all response employees in both print and electronic format. To provide the intended guidance, response employees must use the plan. Response employees must have a good general knowledge of all aspects of the plan and a verified working knowledge of those sections of the plan dealing specifically with their functional area. To ensure that the employees have this degree of knowledge and are comfortable using the plan, utilities must conduct regularly scheduled drills and training activities. All key responders should be drilled or receive supplemental training at least once per year. Failing to keep the plan updated can have a significant negative effect on their usefulness. Not only does the out-of-date or lacking information cause confusion and lost efficiency, but also the signal sent to the responders is that company leaders do not put a high priority on the plan. A good test of a utility’s commitment to having an outstanding response organization is the quality of its emergency plan, and the resources expended in drilling and training their responders and in updating their plan. This chapter provides a description and evaluation of the emergency plans that Connecticut Light & Power (CL&P) and United Illuminating (UI) had in effect prior to the 2011 storms. Liberty’s objective for the work included in this chapter was to assess the companies’ emergency plans, including the companies’ training and drill procedures for emergency response. The chapter addresses: 1. The adaptability of the plans to address different sizes of events, including a method to categorize events by severity level and to detail activities required for each level 2. The accessibility of the plans to all response personnel 3. The extent to which the plans are user-friendly and provide necessary information in a clear, concise format 4. The extent to which response personnel have a good working knowledge of the plans 5. The comprehensiveness of the plans, covering all phases of emergency response – prevent, restoration, and post-event 6. The extent to which the plans contain recognized utility best practices 7. The frequency, comprehensiveness, and effectiveness of drills and training exercises on the plans and emergency response activities April 16, 2012 The Liberty Consulting Group page 7
  4. Page 11 of 182

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 2 Page 11 of 182 Report on the Response of CL&P and UI to Storms in August and October 2011 8. The extent to which the plans capture and use feedback from drills, training exercises, and post-event critiques of actual storm responses to affect improvements in the plans 9. The proven effectiveness of procedures, methods, organizational structures, and processes as set forth in the plans 10. The frequency, comprehensiveness, and effectiveness of updates to the plans The chart below lists items that a comprehensive emergency plan should address. While not intended to be comprehensive, this list includes the important topics in a major outage response. In its review of the emergency plans of both CL&P and UI, Liberty used this chart to determine whether in its opinion the plans were comprehensive in content. General Information Lines of Authority Pre-Event Activities Event/Damage Prediction Classes of Emergency Internal Communications Restoration Activities Use of Outside Resources Operation Center Inventory Control Public Safety Meals/Lodging Practices Use of Other Personnel Downed Wire Process Elected Officials Employee Services Est. Restoration Time Transmission System Hazard Analysis Post-Event Activities Post-Event Critiques B. Administration/Resources Roles/Responsibilities Weather Services Activation/Mobilization Alert Notification Process Organizational Structure Damage Assessment Crew Guides Division Operation Center Material Supply Employee Safety Security Work Prioritization Cut and Clear Process Priority Services Plan Accessibility Call Center Operations Substations Transportation Ramp-Down Action Item Prioritization Planning Processes Drills/Training Monitoring/Alert Processes Documentation External Communications Personnel Support Restoration Work Force Team Leaders Local Operation Center Procurement Logistics Worker Orientation Work Order Handling Regulatory Relationships Critical Care Customers Fleet Management Tree Clearing Status Conference Calls Fueling Process Clean-Up Corrective Action CL&P 1. Form and Contents The emergency plan used by CL&P in responding to Hurricane Irene and the October snowstorm was the Emergency Response Plan, filed with the Connecticut Public Utilities Regulatory Authority (PURA) in June 2011. The plan consists of four sections as follows: Section 1 – Basic Plan – 28 pages Section 2 – District Plan – 42 pages (including 11 pages of appendices) Section 3 – Division Plan – 22 pages Section 4 – Emergency Response Organizations – 45 pages April 16, 2012 The Liberty Consulting Group page 8
  5. Page 12 of 182

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 2 Page 12 of 182 Report on the Response of CL&P and UI to Storms in August and October 2011 In addition to these four sections, the CL&P plan has three pages of definitions and a four-page summary of changes to the previous plan. While not on file with PURA, CL&P used a 414-page Index of Operating procedures (known as EPOPS), which covers 25 separate response functions, to provide response guidance. CL&P requires each district storm room to keep these combined plan documents, which total 558 pages. 1 Contained in one large binder, these plans are physically unwieldy. Section 1 – Basic Plan The basic plan has six subsections – Introduction, Authority and Policies, Concepts of Operation, Preparedness Activities, Response Activities, and Post Incident Activities.2 Subsection 1 – Introduction As stated in the opening line, the objective of the CL&P Emergency Response Plan (ERP) is to provide “a systematic and organized approach to prepare for, and respond to, power outages caused by severe weather, flooding, civil disturbance, or other major disruptions of the Distribution System.” This subsection established the operational structure, defined as Incident Command Center (ICS), for CL&P’s emergency response. The plan is applicable to CL&P and Northeast Utilities (NU) corporate staffs in all moderate through major power outages.3 This subsection is, and by definition should be, general in nature. Subsection 2 – Authority and Policies This subsection covers the delegation by the president of CL&P of “authority for performance and direction of actions of this plan.” For CL&P, it delegates this authority to the Manager – Emergency Management and the CL&P Emergency Management Group (EMG). For NU, it names the Manager – System Restoration and Emergency Preparedness, and the Northeast Utilities Emergency Operations Group (NU EOG).4 There is no specific wording in this section to underscore top management’s full support and involvement in major outage restoration. This subsection discusses policies dealing with safety, environmental concerns, and communications. As would be expected, the treatment of these topics is primarily generalized and conceptual in nature. The wording makes the ICS Communication Policy seem more proactive than the Safety and Environmental Policies. There is no mention of advanced training and specific actions such as daily safety briefings.5 Under Public Safety and Restoration Priority, the document makes the following statement: “Public safety requires immediate efforts for making safe downed, energized wires, and clearance of downed wires, poles, trees, and limbs on major transportation arteries that 1 CL&P Emergency Response Plan, Section 2 – District Plan, page 33; Interview No. 27, 1/4/2012 CL&P Emergency Response Plan, Section 1 – Basic Plan, page 2 3 CL&P Emergency Response Plan, Section 1 – Basic Plan, page 3 4 CL&P Emergency Response Plan, Section 1 – Basic Plan, page 5 5 CL&P Emergency Response Plan, Section 2.2 – 2.5 – Basic Plan, pages 5-7 2 April 16, 2012 The Liberty Consulting Group page 9
  6. Page 13 of 182

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 2 Page 13 of 182 Report on the Response of CL&P and UI to Storms in August and October 2011 provide access for emergency services (emphasis added).”6 Liberty discusses CL&P’s practice of working with towns on road clearing in a following section of this report. Subsection 3 – Concepts of Operation The opening statement of this subsection is “Normal District work groups handle most power outages.” It goes on to say CL&P activates the response organization first at the local level to “handle events of moderate and medium severity.” 7 It does not address the situation of a large storm with advance notice (e.g., hurricane) in which “top down” activation is more likely. The language in the two segments dealing with Management and Process Summary – Sections 3.2 and 3.3 – is general and conceptual in nature, but serves the purpose of this part of the overall plan. Subsection 4 – Preparedness Activities This subsection sets forth the “elements [that] are set in place prior to an actual emergency.” The list is not all-inclusive, but contains the following elements: personnel, notification systems, contact lists, equipment, staging areas, contract crews, mutual-aid utility crews, weather forecasting, and media kits. 8 4.1 – CL&P EMG (Emergency Management Group) The description of the role of Area Command in 4.1.3 is troubling because CL&P worded the ERP in such a way as to exclude proactive activation of the Area Command prior to the onset of storms such as Hurricane Irene and the October snowstorm. Specifically, the plan uses the following language, “An Area Command is activated when there are numerous outages in more than one division, or when outside resources are required.”9 The segment 4.1.5 – Augmenting Personnel and Support Functions – is a very important part of any successful emergency response effort. CL&P does a good job of clearly setting forth the responsibilities of employees and different functional groups in providing this support. One extremely significant statement: “Personnel are drawn from normal CL&P and NU work groups to augment division or district staff and fill functions in the ICS organizations. It is the expectation of executive management that every CL&P and NU system employee will participate in his or her assigned storm role when called upon.”10 To set forth clear expectations regarding support efforts is very important, and CL&P has done so. Sections 4.2 through 4.6 These sections cover (4.2) State, Municipal, and Community Coordination, (4.3) Emergency Restoration Equipment, (4.4) Outside Services, (4.5) Emergency Response Alerts, and (4.6) Training and Drills. The wording in these segments is helpful and adequate for the intended 6 CL&P Emergency Response Plan, Section 2.2.1 – Basic Plan, page 5 CL&P Emergency Response Plan, Section 3.1– Basic Plan, page 8 8 CL&P Emergency Response Plan, Section1, 4. Preparedness Activities - Basic Plan –, page 10 9 CL&P Emergency Response Plan, Section 1, 4.1.3 – Basic Plan, page 12 10 CL&P Emergency Response Plan, Section 1, 4.1.5 – Basic Plan, page 13 7 April 16, 2012 The Liberty Consulting Group page 10
  7. Page 14 of 182

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 2 Page 14 of 182 Report on the Response of CL&P and UI to Storms in August and October 2011 purpose, which is general and conceptual in nature. The Basic Plan appropriately addresses these topics. Overall, the ERP treatment of Preparedness Activities found in Subsection 4 provides good guidance as well as clearly stated responsibilities and management expectations. The Emergency Plan Operating Procedures (EPOP), which Liberty covers in a following section of this report, provides specific details of these activities. Subsection 5 – Response Activities This subsection covers six separate response elements. 5.1 – Command System Initiation This element sets forth the ICS initiation process, providing that senior management, Area command leaders, and Division or District heads may initiate ICS. In its application of the ICS structure, CL&P appears to put the largest responsibility on the lowest unit – the district. 5.2 – Emergency Classifications In the chart below, 11 the CL&P ERP establishes five levels of emergency that help determine the amount of required resources. Classification of Service Outage Events Level Expected Number & Type of Crews Required 1 to 25 CL&P Crews (Note 1) Expected Duration Level I < 10,000 Level II < 20,000 26 to 75 CL&P Crews (Note 1) 12 to 24 Hours < 40,000 76 to 100 CL&P, NU System Crews, & Mutual Aid Crews (Note 1) 24 to 48 Hours < 80,000 101 to 175 District, NU System, & Mutual Aid Crews (Note 2) 48 to 72 Hours Level III Level IV 11 Expected Number of Customers Likely to be Affected < 12 hours ICS Activation Managed by the SOC and District personnel Managed by the SOC, District and Division Command Managed by the District Incident Commander, Division Command, and Area Command Managed by the District Incident Commander, Division Command, Area Command, and System Command CL&P Emergency Response Plan, Section1, 5.2 – Basic Plan, page 22 (selected data – formatting) April 16, 2012 The Liberty Consulting Group page 11
  8. Page 15 of 182

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 2 Page 15 of 182 Report on the Response of CL&P and UI to Storms in August and October 2011 Managed by the District Incident Commander, Level V >100,000 > 72 Hours Division Command, Area Command, and System Command Notes: 1. Corporate Personnel pre-positioning is unlikely except for extenuating circumstances. 2. Corporate Personnel pre-positioning is optional but more likely. 3. Corporate Personnel pre-positioning is expected. over 175 District, NU System and Mutual Aid Crews (Note 3) There is an error in this chart concerning the number of customers out at each level. As shown above, there is no classification level listed for events affecting 80,000 to 100,000 customers. The event classifications as shown above are in keeping with standard utility practice. Beginning with Level III, CL&P activates Area command and brings in outside resources, including crews from other NU companies. At Level IV, CL&P activates System command, and at Level V, prepositions corporate personnel. (At Level IV, pre-positioning of corporate personnel is optional.) As stated above, the primary purpose of CL&P’s event classification is to make an early determination of required resources, based on the best information available at the time. Based on this chart, it is clear that the CL&P ERP calls for the full engagement of all resources available for all events at Level III and above. 5.3 – Escalation of Emergency Response This segment covers the “bottom up” escalation, which the ICS structure stresses. This segment covers each level—District, Division, Area, and System—along with action steps taken at each level upon activation. Escalation is the topic here, and it is adequately covered. Sections 5.4, 5.5, and 5.6 These segments address (5.4) Contractor Support and Mutual Aid, (5.5) Work Schedule, and (5.6) Demobilization from Emergency. They address the subject in a succinct manner, providing good guidance. Included are assigned responsibilities for procurement of outside resources, the emergency working hours (16 hours on and 8 hours off, maximizing daylight), and the priority order in the release of outside crews. Subsection 6 – Post Incident Activities This subsection addresses three specific areas, Equipment and Vehicle Restoration, Post-Storm Critique, and Administrative Updates and Procedure Revisions. It covers these three topics well and assigns responsibility for such things as critiques and updating of contact lists. There is one topic not covered that is normally considered an essential post incident activity. The topic left out goes by a number of names, but is essentially clean-up. This includes things like making repairs and replacements of temporary fixes to the distribution system and clearing partial tree work. This process involves thorough inspections of both line facilities and tree exposure. April 16, 2012 The Liberty Consulting Group page 12
  9. Page 16 of 182

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 2 Page 16 of 182 Report on the Response of CL&P and UI to Storms in August and October 2011 Section 2 – District Plan The district plan is a 42-page document divided into five subsections plus an 11-page Appendix. The five subsections are Introduction, Concepts of Operation, Instructions, Demobilization and Recentralization, and Post Storm Activities. Subsection 1 - Introduction Consisting of just one page, this first subsection addresses the objective, applicability, and organization of the District Plan. It treats these topics adequately. Subsection 2 – Concepts of Operation This subsection addresses three topics: • 2.1 General – Use of ICS at the District level • 2.2 Management – Duties of the District Commander • 2.3 Process Summary – Key points are Activation of ICS; Action Steps (pre-event, during event, and post-event); Priority of recruiting/releasing outside crews; System Operations Center (SOC) handles OMS and all dispatching. Subsection 3 - Instructions 3.1 Preparedness Activities The segments on Pre-storm Checklist and Annual Preparedness Activities (3.1.1 and 3.1.2 respectively) provide a good overview on these topics with references to more detail in sections of Emergency Plan Operations Procedures (EPOP). Segment 3.1.3 – Emergency Drills and Tabletop Exercises – places the primary load on the district. It indicates that CL&P EMG (with help from NU) normally conducts simulated storm drills annually. 12 The Division Director can decide fewer district drills are needed, and the Director, System Operations can decide fewer simulated drills are needed based on storm response experience during that period. The converse is also true, and CL&P may hold more frequent drills when there are new processes or software that requires more training. The concept of pushing the responsibility down to the lowest level of the organization is contrary to the usual practice in utilities. As written, the CL&P plan does not place an adequate stress on training and drills. 3.2 Conference Calls This segment sets forth the concept of and reason for conference calls, the responsibility for initiation of calls, and the key elements of the calls. There is no specification as to how many or at what time of day personnel should make the calls. 12 CL&P Emergency Response Plan, Section 2, District Plan, 3.1.3 page 12 April 16, 2012 The Liberty Consulting Group page 13
  10. Page 17 of 182

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 2 Page 17 of 182 Report on the Response of CL&P and UI to Storms in August and October 2011 3.3 District Decentralization “District Decentralization is defined as the transfer of certain SOC functions out to District locations during emergency events. The decision to decentralize is a collaborative process initiated by System SOC Management, Area Command, Division Command, and District Command.” 13 These are the opening sentences in this subsection. Expressed differently, it is moving the duties of switching and dispatching crews from the System Operations Center (SOC), where they normally reside, down to the district level. This is due to the large amount of damage and repair crews in the impacted area. It sets forth the duties of the four separate functional groups mentioned – SOC and Area/Division/District Command – as related to this decentralization process. The plan allows for the decentralization down to the district level even when the Area and Division Commands are not activated (although they participate in a conference call with the SOC and District Command.) When an outage event has occurred or anticipated in which CL&P considers district decentralization, the Area and Division Commands should be activated. Therefore, the plan covering district decentralization should confirm Area and Division Command activation. There should not be any need to qualify the instructions to cover “when the Area Command is activated,” and “when the Division command is activated.” 3.4 Activation and Staffing of the District Incident Command Post14 The second paragraph of this segment deals with the district organization in “an elevated event.” The wording is weak, leaving some important considerations left to the district to decide. For instance, “it is advisable for the District Commander to utilize the Section Chiefs…,” or “The District Commander needs to maintain a manageable span of control and delegate responsibilities as the situation warrants.” To provide effective guidance, the ERP should provide specific triggers to implement certain organizational structures. 3.5 Transfer of Command and 3.6 Scheduling and Utilization of Required Resources The wording in these two segments cover the process for the Incident Manager to effect transfer to the next shift Incident Manager, and the sequence of actions to begin the response and gain situational awareness. The wording effectively covers the subject matter. 3.7 Required Resources A more apt name for this segment is “restoration process requirements.” It covers the assessment and deployment of line and tree crews, the analysis process, “wires down” support, damage assessment patrols, food and lodging for workers, safety, field services (stores, transportation, and facilities), environmental management, municipal and large customer liaisons, and corporate communications. The wording is primarily general and conceptual in nature, but used in 13 14 CL&P Emergency Response Plan, Section 2, District Plan, 3.3 page 14 CL&P ERP, Section 2, District Plan, 3.4, page 15 April 16, 2012 The Liberty Consulting Group page 14

Text of EOE-383 Attachment 3.pdf

Extracted from the file · 55 pages · 132,814 characters

Text of EOE-383 Attachment 4.pdf

Extracted from the file · 2 pages · 4,635 characters

Text of EOE-383 Attachment 5.pdf

Extracted from the file · 7 pages · 11,175 characters

As listed on the current system

Question(s) Answered 379, 380, 381, 382, 383 (Connecticut Light and Power Company dba Eversource Energy) Date Filed: 10/27/2026

This filing on the current system (opens in a new tab)