Motion No. 001
Request for NEPOOL GIS Operating Rule 3.8(d) Consent (3.6.26)
Files1
Docket No. 25-06-01 - Eligo Request for NEPOOL GIS Operating Rule 3.8(d) Consent (3.6.26).pdf
PDF · 206 KB · 5 pagesText searchable
Download Docket No. 25-06-01 - Eligo Request for NEPOOL GIS Operating Rule 3.8(d) Consent (3.6.26).pdfRead the text of Docket No. 25-06-01 - Eligo Request for NEPOOL GIS Operating Rule 3.8(d) Consent (3.6.26).pdf
NEW YORK
HANOI
LONDON
HO CHI MINH CITY
SINGAPORE
SHANGHAI
FIRM and AFFILIATE OFFICES
PHILADELPHIA
ATLANTA
CHICAGO
BALTIMORE
WASHINGTON, DC
WILMINGTON
SAN FRANCISCO
MIAMI
ALEXANDER W. JUDD
DIRECT DIAL: [phone removed]
PERSONAL FAX: [phone removed]
E-MAIL: [email removed]
SILICON VALLEY
SAN DIEGO
LOS ANGELES
BOSTON
BOCA RATON
PITTSBURGH
NORTH JERSEY
LAS VEGAS
www.duanemorris.com
HOUSTON
DALLAS
SOUTH JERSEY
LAKE TAHOE
FORT WORTH
MYANMAR
AUSTIN
ALLIANCES IN MEXICO
April 28, 2026
Jeffrey R. Gaudiosi, Esq.
Executive Secretary
Public Utilities Regulatory Authority
10 Franklin Square
New Britain, CT 06051
Re:
PURA Confirmation for NEPOOL GIS – Post-Close Transfer of Renewable
Energy Credits Pursuant to NEPOOL GIS Operating Rules 3.8(d)
Dear Mr. Gaudiosi:
Eligo Energy CT, LLC (“Eligo”) respectfully requests 1 that the Public Utilities Regulatory
Authority (the “Authority”) provide Eligo with a statement in writing, whether in response to this
letter or otherwise, that the Authority will accept Renewable Energy Credits (“RECs”) generated
in the calendar year 2024 (the “2024 RECs”) 2 towards the Connecticut’s Renewable Portfolio
Standards (“RPS”) compliance requirements for the compliance year 2025.
In particular, Eligo makes this request pursuant to the New England Power Pool (‘NEPOOL”)
Generation Information System (“GIS”) Operating Rules (“Operating Rules”), Rule 3.8(d). Eligo
has spoken to NEPOOL and the APX Administrator, in charge of managing the GIS system, and
has received approval to make a post-closing account adjustment of these 2024 RECs in order to
apply them to the 2025 compliance year. These post-closing adjustments will result in the 2024
RECs appearing in the My Settled Certificate Disposition Report issued by NEPOOL GIS and to
be submitted to the Authority by Eligo on October 15, 2026 for 2025 compliance. All accounting
and tracking will be done through NEPOOL, with the 2024 RECs reflecting a 2024 generation
Eligo originally filed this request as undocketed correspondence on March 9, 2026. On April 28, 2026, it was
requested by the Authority that Eligo re-file this request as a motion in Docket No. 25-06-01.
1
The 2024 RECs include 6,282 Class I RECs generated by solar, fuel cell, hydroelectric, and biomass facilities
properly registered through the Authority as a Class I generator, and 1,122 Class III RECs produced by Combined
Heat and Power Systems properly registered through the Authority as Class III generators. The total estimated cost
of the 2024 RECs is $280,344.30
2
D UANE M ORRIS LLP
100 PEARL STREET, 13 TH FLOOR
HARTFORD, CT 06103
PHONE: [phone removed]
FAX: +[phone removed]
Jeffrey R. Gaudiosi, Esq.
April 28, 2026
Page 2
date and 2025 settlement date. NEPOOL and the APX Administrator have requested only that the
Authority provide notification of its consent for Eligo and APX to proceed with this transfer under
Rule 3.8(d)(ii).
Rule 3.8(d) provides:
Rule 3.8 Post-Closing Account Adjustment
(d) In addition to the foregoing provisions relating to Post-Closing Account
Adjustments and notwithstanding any other provision of these Rules to the
contrary, an Account Holder that has had Certificates that are eligible for
inclusion in a Banked Certificate Subaccount under Rule 3.7 retired from
its account or Subaccount and become Unsettled Certificates at the end of
any Trading Period may, upon request to the GIS Administrator, have such
Unsettled Certificates credited back to that account or Subaccount and/or
subsequently transferred to another account or Subaccount if the following
conditions are met:
(i)
those Certificates may be credited to the Account Holder’s
account or Subaccount and/or transferred to another account or Subaccount
not later than the date for the annual compliance filing for the state RPS or
APS for which those Certificates are eligible; and
(ii)
if an Energy Regulatory Agency listed on Appendix 5.3 notifies
the GIS Administrator in writing that any such crediting and/or transfer of
Certificates eligible for its state’s RPS or APS must be approved by that
Energy Regulatory Agency, then that Energy Regulatory Agency shall have
approved the crediting and/or transfer of those Certificates.
In the event that any Unsettled Certificates that are to be credited to an
account or Subaccount under this Rule 3.8(d) are eligible for the RPS or
APS of more than one state, then those Certificates shall only be designated
as being eligible for any RPS or APS for which (x) they are otherwise
eligible, (y) the annual compliance filing deadline has not occurred, and (z)
either no Energy Regulatory Agency approval is required or the applicable
Energy Regulatory Agency has granted approval. Upon any crediting and/or
transfer of Certificates under this Section 3.8(d), the GIS Administrator
shall update the quarterly and annual reports produced under Rule 5.2(a) of
the Account Holder(s) to which those Certificates have been credited and/or
transferred.
It is Eligo’s understanding that the Authority had “opted-in” to subsection (ii) of Rule 3.8(d) and
has notified NEPOOL that the Authority must approve a crediting or transfer of RECs eligible for
the Connecticut RPS, although Eligo was not able to find such opt-in notification as part of the
Jeffrey R. Gaudiosi, Esq.
April 28, 2026
Page 3
public record. 3 Presently, there is nothing in Rule 3.8(d), Connecticut General States § 16-245a
or the Regulations of Connecticut State Agencies (“RCSA”) § 16-245a-1 et seq. that disallows
RECs generated from a prior year to be applied directly to a future RPS compliance year.
Under the NEPOOL GIS Operating Rules, Rule 3.8(d), the requirements for eligibility for a postclosing transfer are summarized as follows:
1. The RECs must be “Unsettled Certificates,” as defined in the NEPOOL GIS Operating
Rules;
2. The Unsettled Certificates must be credited or transferred to the account holder’s account
or subaccount prior to the date of the annual compliance filing for which they are eligible
to be applied (i.e., October 15, 2026); and
3. That the state regulatory agency, in this case the Authority, if opted-in to require separate
approval, provides approval in writing of the post-close transfer.
Unsettled Certificates represent unused RECs at the end of an applicable trading quarter, wherein
the RECs are “swept” back into the NEPOOL Residual Mix. Operating Rules, Rule 3.4(a); see
also Docket No. 13-11-18, Petition of Clearview Electric, Inc. for a Declaratory Ruling Regarding
the Applicability of Certain Statutes and Regulations to its Renewable Energy Portfolio Standards
Compliance in the Year 2010 (May 20, 2014 Authority Decision), at 7-8. In Eligo’s present
situation, all Class I and Class III RECs requested to be transferred are Unsettled Certificates, as
verified through the APX Administrator’s willingness to move such credits from the Residual Mix
to Eligo’s Connecticut account, to be used towards the 2025 RPS compliance requirements. These
RECs were swept into the residual mix following the fourth quarter of the 2024 trading period.
As it pertains to the second requirement under Rule 3.8(d), the compliance year in which Eligo
will utilize these RECs is for compliance year 2025, which is not to be filed until October 15, 2026.
Both of these two requirements are squarely met.
The last, and only remaining requirement is for Eligo to receive the Authority’s approval, in
writing, to allow the post-close transfer to occur.
Eligo is aware of the Authority precedent since July 31, 2020, where the Authority stated it would
“no longer entertain any requests for Authority approval to reallocate and use misplaced or
inadvertently transferred RECs for the 2019 RPS compliance year, and any subsequent compliance
years thereafter.” Docket No. 21-06-01, Annual Review of Connecticut’s Electric Suppliers’ and
Electric Distribution Companies’ Compliance with Connecticut’s Renewable Energy Portfolio
Standards in the Year 2020, Motion Nos. 1 and 2 Ruling (Oct. 6, 2021), at 2; Docket No. 20-0601, Annual Review of Connecticut’s Electric Suppliers’ and Electric Distribution Companies’
During discussions, the APX Administrator reviewed the relevant rules surrounding REC eligibility and agreed that
there is no indication that such a use of prior-year generated RECs cannot be used in this way, but still requested that
Eligo receive confirmation from the Authority that the Authority would accept the 2024 RECs as part of Eligo’s future
2025 RPS compliance, to be filed on October 15, 2026.
3
Jeffrey R. Gaudiosi, Esq.
April 28, 2026
Page 4
Compliance with Connecticut’s Renewable Energy Portfolio Standards in the Year 2019, Motion
No. 3 Ruling (Aug. 31, 2020); Docket No. 20-06-01, Final Decision (May 19, 2021), at 5.
However, such precedent is inapplicable to the instant request for two reasons. The first being that
since the Authority has implemented this guidance, it has not issued any decisions specific to
Unsettled Credits, nor under Operating Rule 3.8(d). The most recent example of requests pursuant
to Operating Rule 3.8(d) occurred in Docket No. 20-06-01, where the Authority approved Vistra
Corp.’s transfer of Unsettled RECs totaling 16,761 Class II RECs and 16,373 Class III RECs that
became unsettled. 4 In response to a request in Docket No. 17-06-29, the Authority similarly
approved the transfer of 7,548 RECs from Choice Energy’s Unsettled Certificates housed in the
residual mix to be moved to its Connecticut subaccount. 5 Second, Rule 3.8(d) was amended in
2014, as reflected in NEPOOL Working Group and Markets Committee materials from July 2014, 6
to solve exactly this problem: it extended the post-closing adjustment window to each state’s
annual compliance-filing deadline and adopted an opt-in state-approval option so that Unsettled
Certificates could be corrected and used for compliance. The Authority’s own practice aligned
with that practice in Docket No. 17-06-29 where it approved Choice Energy’s transfer.
Eligo understands that the Authority may have reservations in reviewing requests for approval of
REC transfers, including those requests specific to Rule 3.8(d). In the case that the Authority is
inclined to refuse written consent for the APX Administrator to go through with the discussed
transfer, Eligo would request, in the alternative, that the Authority then withdraw its notification
to NEPOOL requesting that Rule 3.8(d) requests require direct approval by the Authority, as well
as meeting the other requirements for eligibility. Eligo, NEPOOL, and the APX Administrator
have reviewed the request 7 and are able to move ahead with the transfer without any state-level
regulatory approval (absent the NEPOOL notification) pursuant to the Operating Rules and
Connecticut law, and doing so may alleviate the administrative burden that would require the
Authority to review such a request. 8 However, if the Authority simultaneously declines to consider
See Docket No. 20-06-01, Ruling to Motion No. 3 (Aug. 31, 2020).
See Docket No. 17-06-23, Annual Review of Connecticut Electric Suppliers and Electric Distribution Companies,
Final Decision (Jan. 23, 2019), at 10-11.
6
See NEPOOL, Memorandum from Paul N. Belval, NEPOOL Counsel, to NEPOOL Markets Committee, Re: Referral
to GIS Operating Rules Working Group — Reversal of Retirement or Movement of Certificates (July 1, 2014)
(NEPOOL Counsel explaining that DTE Energy Trading, Inc. had forfeited Certificates with a value of approximately
$763,000 — and estimated total losses as high as $875,000 — because the pre-amendment Rule 3.8(d) prohibited
credit-backs after the expiration of the fourth quarter Trading Period); NEPOOL, Meeting Minutes of the NEPOOL
Markets Committee Meeting (July 25, 2014) (“GIS Account Holders [were] potentially losing several million dollars
at a time due to the fourth quarter Trading Period close out clause" and that, to recover those losses, Account Holders
had been forced to "contact the state regulators and file[] petitions to allow for the utilization of the affected Certificates
to meet state RPS requirements.").
7
NEPOOL and the APX Administrator have found Eligo’s request under Rule 3.8(d) to be consistent with NEPOOL
policy and the Operating Rules, and likewise find no reason for the proposal to be found as inconsistent with
Connecticut law. Rule 3.8(d), at its core, was contemplated (and revised) for this type of proposal.
8
NEPOOL will perform the post-closing transfer upon approval and the 2024 RECs will appear in Eligo’s My Settled
Certificate Disposition Report as part of Eligo’s normal RPS compliance filing, to be filed October 15, 2026. The
2024 RECs will reflect a 2024 generation year with settlement in 2025.
4
5
Jeffrey R. Gaudiosi, Esq.
April 28, 2026
Page 5
this Rule 3.8(d) request — whether by applying the 2020 Authority policy in denying reallocation
of RECs or otherwise — the practical effect is that Rule 3.8(d) is nullified for Connecticut. Eligo
would be left with no possible pathway: the APX Administrator cannot act without the Authority’s
optional consent, and the Authority will not provide it while still requiring it.
In either situation, whether the Authority provides affirmative consent for the 2024 RECs to be
utilized for the 2025 compliance year RPS, or the Authority opts to instead rescind its NEPOOL
notification, the APX Administrator will conduct the post-closing transfer of the 2024 RECs, and
Eligo will provide the documentation in its usual RPS compliance filing October 15, 2026 for the
Authority’s review and approval.
If the Authority instead wishes for a fulsome review of this proposal and retain authorization
authority under Rule 3.8(d) through the Authority’s opt-in notification, Eligo has discussed this
matter with the Authority’s Office of Education, Outreach, and Enforcement (“EOE”), and both
Eligo and EOE are willing to enter into settlement discussions, if directed, to effectuate the signoff for the APX Administrator to conduct the transfer.
Please do not hesitate to contact me if you have any questions or require additional information.
Thank you.
Very truly yours,
Alexander W. Judd
cc:
Service List
As listed on the current system
Motion No. 001 04/28/2026 (Eligo Energy CT, LLC) - Request for NEPOOL GIS Operating Rule 3.8(d) Consent (3.6.26) [26-06-01]