Written Comments
Filed by Office of Education, Outreach and Enforcement
- Type of filing
- Comments (Written Comments)
- Date filed
- August 26, 2026
- Filed by
- Office of Education, Outreach and Enforcement
- Files
- 1
As listed on the current system
Written Comments - 08/26/2026 [26-06-04] (Office of Education, Outreach and Enforcement)
Files1
26-06-04 EOE Written Comments FINAL.pdf
PDF · 443 KB · 7 pagesText searchable
Download 26-06-04 EOE Written Comments FINAL.pdfRead the text of 26-06-04 EOE Written Comments FINAL.pdf
,
STATE OF CONNECTICUT
PUBLIC UTILITIES REGULATORY AUTHORITY
OFFICE OF EDUCATION, OUTREACH, & ENFORCEMENT
August 26, 2026
Public Utilities Regulatory Authority
10 Franklin Square
New Britain, CT 06051
Re:
Docket No. 26-06-04 – IMPLEMENTATION OF CLEAN ENERGY
SUCCESSOR PROGRAMS
Dear Commissioners,
The Office of Education, Outreach, and Enforcement (EOE) respectfully submits
these Written Comments to the Public Utilities Regulatory Authority (Authority) in
response to the Notice of Request for Written Comments dated July 28, 2026 (Notice), 1
specifically regarding Topic 4: “current RRES [and] NRES . . . Program rules that should
be carried forward, as well as those that should be modified, in successor programs.
1.
Non-Residential Renewable Energy Solutions (NRES) Program and its
successor program
As the Authority has recognized:
Interconnection remains one of the most persistent and multifaceted
barriers to DER deployment in Connecticut. Challenges related to lengthy
timelines, high and uncertain upgrade costs, cost-allocation
methodologies, conservative utility modeling assumptions, and limited
incentives for EDCs to proactively plan and complete system upgrades all
continue to constrain project development.
Legislative Report, Feb. 27, 2026, Docket No. 25-02-14, Renewable Energy Tariff
Program Successor Study, p. 119. In EOE’s role as the Interconnection
Ombudsperson, EOE has repeatedly seen interconnection issues in disputes brought to
mediation. In light of the known interconnection barriers and EOE’s observation of the
same, EOE provides the following for consideration in addressing interconnection
issues in the clean energy non-residential successor program.
1 The Notice initially requested comments by August 12, 2026. However, in its Ruling on Motion No. 13,
the Authority extended the deadline for all parties to August 26, 2026.
10 Franklin Square, New Britain, CT 06051
An Equal Opportunity Employer
www.ct.gov/pura
Docket No. 26-06-04
a. Interconnection costs vary greatly from estimate to postinterconnection “true-up”
It is EOE’s understanding that, under the standard non-residential
interconnection agreements (IA),2 developers are required to pay for all “interconnection
costs,” which includes costs for testing, communications infrastructure, upgrade costs,
and maintenance and other costs. IA § 5.1. The same is true for “distribution
upgrades.” IA § 5.6.
While the electric distribution companies (EDCs) provide an initial cost estimate
to developers with the IA, that estimate can be of little use by the time the project
interconnects. One reason can be that a significant amount of time has passed since
the IA was presented and the state of the “grid” may be quite different than when the
estimate was provided. Sometimes, the estimate becomes inaccurate because of
changes the developer makes to the project. At other times, the EDCs may provide an
erroneous estimate that is not accurate even at the time it is provided.
Regardless of the reason the estimate is not aligned with actual costs, once the
EDCs incur the “interconnection costs,” they are billed directly to the developer, who is
required to pay them in order to interconnect. The most egregiously inaccurate
estimate EOE has seen in its role as the Interconnection Ombudsperson was an
increase of approximately 3,000%. Unfortunately, in the current NRES program, there
does not appear to be any recourse for developers, or their financial investors, as the
“interconnection costs” are a direct pass-through from the EDCs to the developer. If the
developers want to complete their project, in which they have invested substantial sums
of money, they feel they have no choice but to pay the full interconnection costs.
b. Upgrade costs regarding poles owned by third-party custodians are not
included in EDC cost estimates and may be entirely unknown (and
unknowable) by developers
Cost estimates for interconnection upgrades provided by the EDCs are limited to
the EDCs’ costs, which would include any costs associated with poles for which the
EDCs are custodians. However, many poles have a third-party custodian, and costs for
those poles are not included in the EDC estimates, nor is any information regarding the
absence of those costs. As far as EOE is aware, there is no way for a developer to be
on notice that additional pole costs could be incurred nor any way for a developer to
identify the pole custodian.
The most troubling instance of these “hidden” interconnection costs seen by EOE
as the Interconnection Ombudsperson involved an additional $350,000+ of costs
associated with replacement of poles owned by a third-party custodian. These possible
additional costs were not shared by the EDC with the developer. Rather, the developer
received an invoice directly from the third-party pole custodian after the developer paid
2 Standard Fast Track and Study Process Generator Interconnection Agreement.
2
Docket No. 26-06-04
to the EDC multiple millions of dollars in interconnection upgrade costs to be incurred by
the EDC for the developer’s project. Once again, if developers want to complete their
projects, in which they have invested substantial sums of money, they feel compelled to
pay the full interconnection costs, no matter how unexpected or “unfair” they may seem.
In the clean energy non-residential successor program, EOE suggests that all
upgrade costs, including those of third-party pole custodians, should be included in the
estimate provided by the EDCs. The EDCs are the only parties in possession of the
information regarding both the proposed project and the pole custodian(s). Thus,
because all the pole upgrade costs are in aid of interconnection, the EDCs should be
responsible for providing an estimate for those costs, as obtained from the third-party
custodian. At the very least, the EDC should provide notice to the developer that the
pole custodian is a third-party and direct the developer to contact that third-party to
obtain an estimate.
c. Interconnection timeline delays based on lack of communication
A majority of the disputes EOE handles as the Interconnection Ombudsperson
are the result of timeline delays and the perceived lack of communication developers
receive from the EDCs throughout the interconnection process. Communication
breakdowns can occur when either party – developer or EDC – fails to provide
requested information. EOE recognizes that only developers reach out to the
Interconnection Ombudsperson when communication breaks down, which can make it
appear as if all the communication problems are the result of EDC failures. While this
cannot be presumed, the EDCs sometimes fail to timely and effectively communicate
during projects, and sometimes for months on end, for reasons that EOE has been
unable to fully understand.
The primary complaint is that developers repeatedly reach out for updates and
receive none. Failures include lack of timely: countersignatures on IAs, cost updates,
study results, updates to study schedules, revised documentation, accurate
documentation, responses to project changes, and status updates.
As the Authority develops clean energy successor programs, it should consider
ways to decrease timeline delays, including delays based on lack of EDC
communication, possibly by holding the EDCs accountable in some way for
unnecessarily causing delays, e.g. fines, inability to recover costs in rate base, etc.
d. Changes required in prior Authority decisions that should carry forward
to the clean energy non-residential successor program
EOE suggests that the proposals recommended in the 100-Day Sprint Working
Group Report3 (Sprint Report), which were adopted and accepted by the Authority in
3 100-Day Sprint Working Group Report, Dec. 20, 2024, Docket No. 17-12-03RE06, available at Docketed
Correspondence for [ 17-12-03RE06 ] Final Sprint Report.
3
Docket No. 26-06-04
Docket No. 25-01-27, should carry forward to the successor program to the extent they
remain applicable in the new program. To summarize, those proposals included
updates to (1) PowerClerk and EDC data, (2) interconnection timelines, (3) EDC
processes and procedures, and (4) timelines and cost estimates. Following its review of
the Sprint Report, the Authority made clear in its decisions in Docket No. 25-01-27
which proposals the EDCs were to implement. Interim Decision, Mar. 26, 2025, Docket
No. 25-01-27, PURA Investigation into Interconnection Process Modifications, pp. 7-11,
28-30; Final Decision, Aug. 20, 2025, Docket No. 25-01-27, PURA Investigation into
Interconnection Process Modifications, pp. 7-8, 14-17, 50-54.
EOE notes that, in its role as a facilitator in the Interconnection Working Group
(IXWG), EOE has heard developers complain of several proposals that developers
believe the EDCs have not implemented fully and/or correctly. Without commenting on
the accuracy of the complaints, EOE provides the following examples from developer
members of the IXWG:
1. Failure to implement or implement with full functionality the “chess clock” in
Power Clerk (Sprint Report Proposal #5; Final Decision, Aug. 20, 2025,
Docket No. 25-01-27, Order No. 10).
2. Failure to resolve communications issues through an effective single point of
contact (POC), even though a POC has been provided for each project
(Sprint Report Proposals # 15, 17, 19; Interim Decision, Mar. 26, 2025,
Docket No. 25-01-27, Order No. 1).
3. Failure to fully implement solutions regarding the processes for installing and
paying for incentive meters (Sprint Report Proposal # 33; Final Decision, Aug.
20, 2025, Docket No. 25-01-27, Order No. 13).
4. Failure to timely and continually update hosting capacity maps.
To the extent any proposals ordered to be implemented in Docket No. 25-01-27
have not been fully or accurately implemented, EOE recommends that the Authority
hold the EDCs accountable and carry forward such requirements – fully implemented –
in the successor program.
Lastly, EOE recommends that any clean energy successor program includes
flexible interconnection, bidirectional EV charging interconnection, and coordination with
the successor energy storage program such that consumers can benefit from all
programs in order to further the state’s clean energy goals. See, e.g., IXWG Meeting
Summary, Feb. 10, 2026 (discussing flexible interconnection, bidirectional EV charging,
and energy storage projects), available at CT IXWG 7/10/26 Meeting Summary; 4 IXWG
Meeting Summary, Mar. 10, 2026 (discussing flexible interconnection and bidirectional
4 All IXWG meeting summaries are available on the Authority’s website at Interconnection Technical
Working Group and Interconnection Policy Working Group. Note that the two groups (technical and
policy) meet together and summaries for all meetings are posted on both webpages.
4
Docket No. 26-06-04
EV charging), available at CT IXWG 3/10/26 Meeting Summary; IXWG Meeting
Summary, Apr. 7, 2026 (discussing EDC straw proposal for interconnecting bidirectional
EVs), available at CT IXWG 4/7/26 Meeting Summary; IXWG Bidirectional EV
Interconnection Subgroup Meeting Summary, May 1, 2026, available at CT IXWG
5/1/26 BEV Subgroup Meeting Summary.
2.
Residential Renewable Energy Solutions (RRES) Program and its
successor program
EOE supports the Authority’s recommendations for the clean energy residential
successor program, including “(1) comprehensive upfront licensing requirements for
solar contractors, retailers, and installers; and (2) ongoing contractor compliance and
auditing to ensure that companies are adhering to program rules, CUTPA, and any
other applicable regulations.” Legislative Report, Feb. 27, 2026, Docket No. 25-02-14,
Renewable Energy Tariff Program Successor Study, p. 56.
EOE brings to the Authority’s attention that, since the Authority’s implementation
of the RRES contractor compliance obligations in the annual dockets (No. 2X-0802RE01) (Contractor Compliance Dockets), some solar companies have removed their
sales and marketing departments from within their solar companies so that the sales
and marketing company and the installation company are two separate legal entities.
This results in the solar installation company, over which the Authority has jurisdiction
through the RRES application process, having no marketing or training materials to file
in the Contractor Compliance Dockets and thus circumvent the protections provided to
customers in those dockets. In addition, after receiving strikes in the annual Contractor
Compliance Dockets, which prohibit a company from submitting RRES applications,
EOE has been made aware of one company who is apparently filing its applications
through a separate entity that did not receive a strike, also circumventing the protections
provided to customers in the Contractor Compliance Dockets. While the recent Public
Act 26-16 will hopefully remedy some of these problems and hold solar sales and
marketing companies accountable, EOE nonetheless wants to make the Authority
aware of these issues as it contemplates the clean energy residential successor
program.
EOE also notes for the Authority’s consideration that the EDCs may not have
fully implemented the Authority’s directions regarding the use of meter socket adaptors
(MSAs) as required by the Authority. Final Decision, Order No. 32, Nov. 1, 2023,
Docket No. 23-08-08, Annual Residential Renewable Energy Solutions Program Review
– Year 3 (requiring compliance filings in Dockets No. 23-08-02 and 23-08-05); Final
Decision, Orders No. 26 and 27, Oct. 16, 2025, Docket No. 24-08-02, Annual RRES
Program Review – Year 4. In its role as a facilitator in the IXWG, EOE has heard
developers comment that the EDCs’ meter diagrams and implementation of the MSA
program essentially prohibit the use of any MSAs. Without commenting on the
accuracy of the complaints, EOE provides the following information for the Authority’s
consideration in assessing the implementation of the use of MSAs.
5
Docket No. 26-06-04
The EDCs filed their compliance documents in accordance with the applicable
orders regarding MSA implementation; however, MSAs were routinely being rejected in
April 2025. See Final Decision, Dec. 17, 2025, Docket No. 25-08-02, Annual RRES
Program Review – Year 5, Order No. 21 and p. 26 (referring to Tesla’s comments that
UI’s metering requirements effectively contravene the use of MSAs); Correspondence
from ConnectDER and Tesla, Apr. 17, 2025, Docket No. 24-08-02, Annual RRES
Program Review – Year 4 (summarizing reasons for delays); see also IXWG MSA
Subgroup Meeting Summary, Jan. 14, 2025, available at CT IXWG 1/14/25 MSA
Subgroup Meeting Summary; IXWG MSA Subgroup Meeting Summary, Feb. 6, 2025,
available at CT IXWG 2/6/25 MSA Subgroup Meeting Summary. In light of the
difficulties in receiving approval from the EDCs to utilize MSAs in residential clean
energy projects, and the limited capacity in which they are currently being allowed, EOE
recommends that the use of MSAs be more fully implemented in the clean energy
residential successor program to enable customers to save substantial costs associated
with other methods of interconnection and wiring.
EOE thanks the Authority for its thoughtful and thorough consideration of EOE’s
prior recommendations regarding the RRES program requirements. See EOE Written
Comments, May 9, 2025, Docket No. 25-02-14, Renewable Energy Tariff Program
Successor Study;5 EOE Written Comments, Dec. 12, 2025, Docket No. 25-02-14,
Renewable Energy Tariff Program Successor Study;6 EOE’s Brief, Oct. 22, 2025,
Docket No. 25-08-02, Annual RRES Program Review – Year 5; 7 and Contractor
Compliance Working Group (CCWG) Report submitted by EOE on behalf of the CCWG,
Docket No. 25-08-02, Annual RRES Program Review – Year 5, and Docket No. 26-0802, Annual RRES Program Review – Year 6.8 EOE wishes to thank the Authority for its
adoption of many of EOE’s prior recommendations in the current RRES program and
recommends that these same improvements carry forward into the clean energy
residential successor programs.
Lastly, EOE thanks the Authority for the opportunity to comment on these issues.
Sincerely,
PUBLIC UTILITIES REGULATORY AUTHORITY
Office of Education, Outreach, and Enforcement
5 Available at 25-02-14 EOE Written Comments.
6 Available at 25-02-14 EOE Written Comments 4.
7 Available at EOE Brief for 25-08-02 filed 10/22/2025.
8 EOE Correspondence with CCWG Final Report, March 31, 2026, Docket No. 26-08-02, available at
Docketed Correspondence for 26-08-02 - CCWG Final Report (also filed in Dkt No. 25-08-02).
6
CERTIFICATE OF SERVICE
I hereby certify that on this day the foregoing document was filed with the Public Utilities
Regulatory Authority, and copies thereof were served upon each person designated on
the official service list in this proceeding in accordance with R.C.S.A. § 16-1-15.
Sincerely,
Jamie Spannhake
By: /s/
Jamie Spannhake
Staff Attorney
PUBLIC UTILITIES REGULATORY AUTHORITY
Office of Education, Outreach and Enforcement