STATE OF CONNECTICUT
PUBLIC UTILITIES REGULATORY AUTHORITY
TEN FRANKLIN SQUARE
NEW BRITAIN, CT 06051
DOCKET NO. 26-07-03 APPLICATION OF THE CONNECTICUT LIGHT AND
POWER COMPANY D/B/A EVERSOURCE ENERGY
(CL&P) FOR QUALIFICATION OF NON-RESIDENTIAL
RENEWABLE ENERGY SOLUTIONS (NRES) FACILITIES
AS CLASS I RENEWABLE ENERGY SOURCES – Q2 2026
August 12, 2026
By the following Commissioners:
Thomas H. Wiehl
David Arconti, Jr.
Janice A. Beecher
Holly H. Cheeseman
Everett Smith, III
DECISION
DECISION
I.
INTRODUCTION
A.
SUMMARY
In this Decision, the Public Utilities Regulatory Authority determines that the 20
Non-Residential Renewable Energy Solutions solar generation facilities located in
Connecticut qualify as Class I renewable energy sources.
B.
BACKGROUND OF THE PROCEEDING
By application received July 8, 2026 (Application) and spreadsheet labeled ES
NRES Q226 Worksheet Solar (Spreadsheet), The Connecticut Light and Power Company
d/b/a Eversource Energy (Company) requested that the Public Utilities Regulatory
Authority (Authority) determine that the 20 Non-Residential Renewable Energy Solutions
(NRES) facilities listed on the Spreadsheet (NRES Facilities) and located in Connecticut
qualify as Class I renewable energy sources.
C.
CONDUCT OF THE PROCEEDING
There is no statutory requirement for a hearing, no person requested a hearing,
and none was held.
D.
PARTICIPANTS
The Authority recognized the following as Participants to this proceeding: The
Connecticut Light and Power Company d/b/a Eversource Energy, 107 Selden Street,
Berlin, CT 06037; the Office of Consumer Counsel, Ten Franklin Square, New Britain, CT
06051; and the Commissioner of the Department of Energy and Environmental
Protection, 79 Elm Street, Hartford, CT 06106.
II.
STANDARD REVIEW
Pursuant to § 16-1(a)(20) of the General Statutes (Conn. Gen. Stat.), “Class I
renewable energy source” includes energy derived from solar power.
III.
AUTHORITY ANALYSIS
As provided in the Application and the Spreadsheet, the NRES Facilities generate
electricity using solar power and each began commercial operation on its corresponding
commercial operation date listed on the Spreadsheet.
The NRES Facilities have a total nameplate capacity of 3.298 MW. The NRES
Facilities’ aggregate New England Power Pool Generation Information System
Identification Number (NEPOOL GIS ID No) is NON261452. The NRES Facilities are
behind-the-meter generation facilities located in Connecticut and shall be subject to audits
by the Authority.
Docket
IV.
No.
26-07-03
Page 2
CONCLUSION
The Authority reviewed all information in the record and finds that pursuant to
Conn. Gen. Stat. § 16-1(a)(20), the NRES Facilities qualify as Class I renewable energy
sources, effective the later of April 1, 2026, or each NRES Facilities’ corresponding
commercial operation date listed on the Spreadsheet. The Authority assigns the NRES
Facilities Connecticut Renewable Portfolio Standard Registration No. CT260703.
The Authority’s determination in this docket is based on the information submitted
by the Company. The Authority may reverse its ruling or revoke the Company’s
registration if any material information provided proves to be false or misleading. The
Company is reminded that it is obligated to notify the Authority within 10 days of any
changes to any of the information it has provided. The Authority’s determination in this
docket applies only to the 20 NRES Facilities listed on Spreadsheet.
DOCKET NO. 26-07-03 APPLICATION OF THE CONNECTICUT LIGHT AND
POWER COMPANY D/B/A EVERSOURCE ENERGY
(CL&P) FOR QUALIFICATION OF NON-RESIDENTIAL
RENEWABLE ENERGY SOLUTIONS (NRES) FACILITIES
AS CLASS I RENEWABLE ENERGY SOURCES – Q2 2026
This Decision is adopted by the following Commissioners:
Thomas H. Wiehl
Holly H. Cheeseman
David Arconti, Jr.
Janice A. Beecher
Everett Smith, III
CERTIFICATE OF SERVICE
The foregoing is a true and correct copy of the Decision issued by the Public
Utilities Regulatory Authority, State of Connecticut, and was forwarded by Certified Mail
to all parties of record in this proceeding on the date indicated.
Jeffrey R. Gaudiosi, Esq.
Executive Secretary
Public Utilities Regulatory Authority
August 12, 2026
Date
As listed on the current system
Final Decision, 08/12/2026 [26-07-03]