Compliance with Order No. 11
Filed by Avangrid
Part of
Annual Residential Renewable Energy Solutions Program Review and Rate Setting - Year 6
- Type of filing
- Compliance filing (Compliance Filing, Order No. 11)
- Date filed
- May 1, 2026
- Filed by
- Avangrid
- Files
- 2
As listed on the current system
Compliance Filings, 05/01/2026 [26-08-02] Order No.11 / Avangrid / Compliance with Order No. 11
Files2
2026-05-01 UI Order 11 Cover Letter #26-08-02.pdf
PDF · 34 KB · 2 pagesText searchable
Download 2026-05-01 UI Order 11 Cover Letter #26-08-02.pdfRead the text of 2026-05-01 UI Order 11 Cover Letter #26-08-02.pdf
2026-05-01 UI Order 11 Attachment 1 #26-08-02.xlsx
Excel · 43 KBText searchable
Download 2026-05-01 UI Order 11 Attachment 1 #26-08-02.xlsxRead the text of 2026-05-01 UI Order 11 Attachment 1 #26-08-02.xlsx
May 1, 2026
Mr. Jeffrey R. Gaudiosi, Esq.
Executive Secretary
Public Utilities Regulatory Authority
10 Franklin Square
New Britain, CT 06051
Re:
Docket No. 26-08-02, Annual Residential Renewable Energy Solutions Program Review
– Year 5, Compliance with Order No. 11
Dear Mr. Gaudiosi,
Pursuant to the Public Utilities Regulatory Authority’s (“PURA” or the “Authority”) Final
Decision in Docket 22-08-02 (the “Year 2 Decision”) dated November 2, 2022, The United
Illuminating Company (“UI” or the “Company”) hereby submits this compliance filing. The
Year 2 Decision is updated, in part, by the Final Decision in Docket No. 25-08-02 (the
“Decision”) dated December 17, 2025,
Order No. 11 of the Decision states:
Reference Year 2 Decision, Order No. 12, p. 35: On a [quarterly basis beginning on
January 1, 2024] through [the duration of the RRES Program], the EDCs shall
provide updates to Docket No. 21-08-02 Response to Interrogatory CAE-8.
Specifically, the Authority adapts the ruling in Docket No. 21-08-02 to Motion No.
26 dated March 22, 2022, which directed the EDCs to submit as a compliance filing
an update to Interrogatory CAE-8 on or before the 15th of every month through
January 1, 2023 (i.e., the final filing would have been made on December 15, 2022),
to instead direct the compliance filings to continue monthly through January 1, 2024.
Such filings shall be made in [the annual review proceeding (i.e., in 2024, Docket
No. 24-08-02)] and should also include tariff type and incentive adder status
information. [Last, beginning by July 1, 2024, the quarterly filings shall include: (1)
the total number of low-income customers and customers located in Distressed
Municipalities, and associated project capacity, which do not receive either adder,
in addition to the existing breakouts for customers enrolled in the low-income and
Distressed Municipality adders; (2) the number and associated project capacity of
customers who reside in environmental justice census block groups, broken out by
customers that qualify for the low-income and Distressed Municipality adders and
those that do not; and (3) the number and associated project capacity of RRES
customers who qualify for the Federal Justice 40 disadvantaged communities
definition.]
180 Marsh Hill Road, Orange, CT 06477
www.uinet.com
An equal opportunity employer
In compliance with the above, UI submits Attachment 1, which contains data specific to
interconnection applications that have applied to participate in the Residential Renewable
Energy Solutions (RRES) program, as originally provided in response to CAE-008, updated
from January 2026 through March 2026.
I hereby certify service of this filing upon all parties or intervenors of record in this proceeding.
Sincerely,
James Nitz
Manager, Regulatory Services
UIL Holdings Corporation
As Agent for The United Illuminating Company
180 Marsh Hill Road, Orange, CT 06477
www.uinet.com
An equal opportunity employer