Written Exceptions
Filed by OCC
Part of
Annual Residential Renewable Energy Solutions Program Review and Rate Setting - Year 6
- Type of filing
- Exception (Written Exceptions)
- Date filed
- October 15, 2026
- Filed by
- OCC
- Files
- 1
As listed on the current system
Exception to Decision filed 10/15/2026 (OCC) [26-08-02]
Files1
26-08-02 LIL WE.pdf
PDF · 245 KB · 4 pagesText searchable
Download 26-08-02 LIL WE.pdfRead the text of 26-08-02 LIL WE.pdf
Paschaline Poku
Email:[email removed]
October 15th, 2026
Public Utilities Regulatory Authority
Ten Franklin Square
New Britain, Connecticut 06051
Re: Docket No. 26-08-02: Annual Residential Renewable Energy Solutions Program Review
and Rate Setting - Year 6.
Dear Commissioners,
The Office of Consumer Counsel (“OCC”) respectfully submits this letter in lieu of written
exceptions in response to the Public Utilities Regulatory Authority’s (“Authority”) Proposed Final
Decision (“PFD”), issued on October 1, 2026, in the above-referenced docket.
OCC takes exception on two issues: application fees and Multi-Family Affordable Housing
(“MFAH”) eligibility. Additionally, OCC also offers a brief comment on standardizing saving
assumptions for consideration in the successor program. 1
I.
APPLICATION FEES
OCC has consistently argued that application fees should cover the cost of processing
applications rather than shifting the remainder of the cost to all ratepayers. 2 In Year 4’s annual
review, OCC noted that the fee had originally been set below cost out of concern that a higher fee
would discourage participation and that this concern no longer held because the program had far
surpassed its enrollment targets. 3 In Year 5’s Review, OCC similarly acknowledged the
Authority’s upward adjustment to the fee but cautioned that a continued risk of under-collection
remained, with a shortfall borne by all ratepayers. 4 In this proceeding, OCC again urged that fees
be set to fully recover each EDC’s actual administrative costs. 5
Docket 26-06-04, Implementation of Clean Energy Successor Programs.
OCC Written Comments, Docket No. 21-08-02, August 31, 2021.
3
OCC Written Comments, Docket No. 24-08-02, August 12, 2021, p. 1-2.
4
OCC Written Exceptions, Docket No. 25-08-02, p.2
5
OCC Written Comments, Aug. 19, 2026, p.3
1
2
The record in this docket shows the same gap. Eversource collected $1,520,126.00 in
application fees over the twelve months ending June 30th 2026, and expects to incur $1,760,735 in
program costs, a shortfall of roughly $240,600. 6 The United Illuminating Company (“UI”)
collected $546,149 against estimated administrative costs of $1,001,682, a shortfall of roughly
$455,500. 7 The PFD acknowledges that the approved fees “do not fully cover all RRES Program
administrative costs” and also notes that no stakeholder argued UI’s proposed increase would be
a barrier to participation. 8 The remaining costs are recovered from all customers through the EDCs’
annual Rate Adjustment Mechanism (“RAM”) proceedings. 9 As a result, customers who do not
participate in the RRES Program continue to subsidize the cost of processing participants’
applications.
In recognizing that 2027 is the final year of the program, OCC does not ask the Authority to
revisit the fee levels approved in the PFD. However, OCC maintains its position and requests that
the Final Decision replace the statement that the EDCs “may be directed” to justify their RRES
administrative costs in the RAM proceedings with a directive that each EDC file, in its 2027 RAM
proceeding, a breakdown of the fixed and variable components of those costs. UI should also
explain why its total administrative costs did not decline with lower application volumes, a
question that PFD itself raises. 10 The Authority should also confirm that recovery of undercollected RRES administrative costs through the RAM remains subject to review for prudence and
reasonableness. The Authority should further direct that application fees in the successor
residential program being developed in Docket 26-06-04 11 be designed to fully recover
administrative costs.
OCC reserves the right to address the recovery of these costs in subsequent EDC RAM
proceedings.
II.
MFAH ELIGIBILITY
The PFD declines to change the rules on MFAH eligibility, despite OCC’s stated concerns
that there is risk of overcompensation that may benefit developers over the low-income customers
that the program is seeking to benefit. 12
OCC does not request modification to the MFAH eligibility criteria for the final program
year, given that the program is concluding and the resulting 2027 ratepayer impact is expected to
be minimal. However, OCC requests that the Final Decision direct the EDCs to track and report
for 2027 MFAH applications the number, size, and compensation of projects interconnected at a
separate service point from the existing building load. Additionally, the Final Decision should
request that the EDCs report how many MFAH projects compensated at RRES rates could
otherwise have qualified for the Non-Residential Energy Solutions (“NRES”) Program, along with
data on each project’s size and total compensation. Including such data would show the scope of
Proposed Final Decision, Docket No. 26-08-02, p.9-10
Id. p. 10
8
Id.
9
Id. p.11
10
Id. p.10-11
11
Implementation of Clean Energy Successor Programs
12
PFD, p.30-31, see also OCC Written Comments, Aug. 19, 2026, p.4
6
7
the issue before successor program rules are set and allow the parties to assess how often this
eligibility gap has been used.
OCC has also consistently maintained that the benefits of solar must reach tenants and
support solar access for low-income residents. 13 Accordingly, OCC does not seek any
modifications that foreclose participation by such residents. The Implementation of Clean Energy
Successor Program review should also examine whether large MFAH projects are in fact
delivering these required benefits to low-income tenants. To support this review, OCC further
requests that the EDCs’ annual tenant-benefit compliance filing under Standing Order No. 10 be
provided at the project level breakdown for MFAH projects size for projects interconnected at a
separate service point. 14 For each project, the filing should identify the total tariff value paid, the
dollar amount distributed to tenants, the number of tenant households served, the average annual
benefit per household, and the distribution method. This information will allow the Authority to
assess in Docket No. 26-06-04 whether large MFAH projects deliver meaningful benefits to lowincome tenants that they would not receive if the projects were compensated under NRES.
The Authority should continue to evaluate and address these issues in Docket No. 26-0604 to ensure that the successor program’s MFAH eligibility criteria strikes the right balance
between solar access for low-income customers and cost-containment.
III.
STANDARDIZING SAVING ASSUMPTIONS IN THE SUCCESSOR PROGRAM.
OCC remains concerned that a customer can receive two solar proposals with very different
savings estimates because the contractors used different assumptions, an issue that was similarly
raised throughout the Contractor Compliance Working Group (“CCWG”) process and in OCC’s
comments on the CCWG Report. 15 Additionally, OCC also opposed allowing contractors to depart
from the Authority’s escalation and degradation rates for the same reason. 16
While OCC supports the PFD’s decision to evaluate contractor compliance requirements
for the successor residential program in Docket No. 26-06-04, 17OCC urges the Authority to make
uniform savings assumptions, including the starting utility rate, escalation rate, and degradation
rate a priority in that proceeding, so that customers can compare offers on equal terms.
***
OCC appreciates the opportunity to submit these Written Exceptions and respectfully
requests that the Final Decision direct the EDCs to justify their RRES administrative costs in the
2027 RAM proceedings, require reporting on separately interconnected MFAH projects and carry
that issue into Docket No. 26-06-04, and prioritize uniform savings assumptions in the successor
program.
OCC Written Comments, Aug. 12, 2024, Docket No. 24-08-02, p. 1, see also OCC Written Comments, Aug. 19,
2026, p. 4
14
Proposed Final Decision, p.36
15
OCC cautioned that disclosure of differing methodologies does not let customers meaningfully compare offers;
see OCC Written Comments, May 28, 2026, p. 4.
13
16
17
Id. p.4
PFD, p.15
Respectfully submitted,
STATE OF CONNECTICUT OFFICE
OF CONSUMER COUNSEL
CLAIRE E. COLEMAN
CONSUMER COUNSEL
By: /s/ Paschaline Poku
Paschaline Poku
Staff Attorney
John Viglione
Associate Economist
Anu Kumaria
Research Analyst
CERTIFICATE OF SERVICE
I do hereby certify that on this day the foregoing document was filed with the Public
Utilities Regulatory Authority, and copies thereof were served upon each person designated on the
official service list in this proceeding in accordance with R.C.S.A. § 16-1-15.
Dated at New Britain, Connecticut this 15th day of October 2026.
/s/Paschaline Poku
Commissioner of the Superior Court