Interrogatories
To Earthlight Technologies, LLC; GoodLeap; Ion Solar Pros, LLC; Savkat, Inc.; Sunrun, Inc.; Sunrun, Inc.; Tesla, Inc.; Trinity Solar, Inc., questions 14 thru 20
Files1
26-08-02 Interrogatories Set 1.pdf
PDF · 188 KB · 9 pagesText searchable
Download 26-08-02 Interrogatories Set 1.pdfRead the text of 26-08-02 Interrogatories Set 1.pdf
STATE OF CONNECTICUT
PUBLIC UTILITIES REGULATORY AUTHORITY
May 11, 2026
In reply, please refer to:
Docket No. 26-08-02
Re: Docket No. 26-08-02 – Annual Residential Renewable Energy Solutions Program
Review and Rate Setting – Year 6
Enclosed are interrogatories numbered CAE-1 through CAE-4, directed to The
United Illuminating Company (UI); CAE-5 and CAE-6, directed to The Connecticut Light
and Power Company d/b/a Eversource Energy (Eversource); CAE-7 through CAE-11,
directed individually to Eversource and UI (collectively, the electric distribution companies
or EDCs); CAE-12, directed individually to UI, Eversource, and the Office of Consumer
Counsel; CAE-13, directed to the Office of Education, Outreach, and Enforcement (EOE);
CAE-14 through CAE-20, directed individually to Earthlight Technologies, GoodLeap,
Ion Solar Pros, SAVKAT, SunRun, Tesla, and Trinity Solar; and CAE-21 directed to Tesla.
The responses to these questions have been deemed necessary by the Public
Utilities Regulatory Authority (Authority) in connection with the above-referenced docket
and will become a part of the record in this proceeding. Please note that persons
responsible for responses must be available for cross-examination during a hearing, if
held, and must attest to the truth and accuracy of their responses.
Please submit the responses to the Authority’s Executive Secretary no later than
May 28, 2026, at 4:00 p.m. The Authority encourages the submission of responses as
soon as they are available rather than delaying until all answers are completed. Please
list each question and answer on the same sheet of paper using a separate sheet
for each interrogatory number, and sequentially number the pages of each
response (e.g., p. 1 of 5, etc.). At the top of each page, clearly identify the Docket
Number, the interrogatory number (including the prefix), the name of the company
and the person responsible for the response, and the date of submission.
Similarly, each Late Filed Exhibit that may be submitted after hearing in this
docket shall be sequentially numbered and identified with the Docket Number, Late
Filed Exhibit Number, page number, the name of the company and the person
responsible for the exhibit, and the date of submission.
If a response to any of the requested information has already been filed in response
to another Parties’ interrogatory(ies) in this proceeding, please reference the interrogatory
which provides the information. It is the respondent’s responsibility to ensure that any
such information is on file with the Executive Secretary of the Authority.
ELECTRONIC SUBMISSION OF FILINGS
IMPORTANT NOTE: The Authority has indefinitely suspended the paper
copy filing requirement. Anyone filing material with the Authority should file only
an electronic copy through the PURA Web Filing System. Please refer to the
Electronic Filing webpage for more information, including on confidential
materials: Make An Electronic Filing
CONFIDENTIAL DOCUMENTS
No confidential material may be filed publicly through the web filing system.
Confidential material can be filed electronically by emailing the material to
[email removed] with a subject line labeled in all capital letters “CONFIDENTIAL
MATERIAL - NOT FOR PUBLIC DISCLOSURE.” Each page of any electronic
confidential information shall also contain a header “CONFIDENTIAL – NOT FOR
PUBLIC DISCLOSURE.” The motion for a protective order shall be filed electronically.
The Authority operates with the strong presumption that all documents filed with it
are public records subject to the right of public inspection and copying in accordance with
the Connecticut Freedom of Information Act, Conn. Gen. Stat. §1-200 et. seq. In those
exceptional circumstances where a participant believes that information it intends to file
is confidential under law, it may file a Motion for a Protective Order requesting an
exemption from public disclosure. The Motion must provide specific legal arguments with
reference to state or federal law describing with supporting facts why the information
should be kept confidential. A certified affidavit supplied by a competent witness in
support of the Motion must be appended to the Motion. The Authority will rule on the
Motion forthwith, and it will give further direction as necessary.
The current service list for this docket is available on the Authority's website
located at http://www.dpuc.state.ct.us/DPUCPublicList.NSF.
By the Direction of the Authority,
PUBLIC UTILITIES REGULATORY AUTHORITY
Jeffrey R. Gaudiosi, Esq.
Executive Secretary
Enclosure
cc:
Service List
Docket No. 26-08-02
Annual Residential Renewable Energy Solutions Program Review and Rate Setting –
Year 6
Interrogatories CAE-1 through CAE-4 are directed to The United Illuminating
Company (UI).
CAE-1
UI Interrog. Resp. CAE-30, Docket No. 25-08-02; UI Compliance, March 17,
Docket No. 25-08-02, Att. 1. In its response to CAE-30, UI stated that the
reported number of projects receiving adders are a subset of the number
reported that are eligible for adders. However, in the data reported for 2025,
the number of projects receiving the low-income adders is higher than the
number of projects eligible for the low-income adder. Explain and provide
corrected data if necessary.
CAE-2
Office of Education, Outreach, and Enforcement (EOE) Corresp., March 31,
2026, CCWG Report FINAL (CCWG Report), p. 10. Discuss which part(s)
of the RRES program manual or other documents would conflict with the
standardized methodology for calculating a customer's annual electricity
usage set forth in Proposal 3 of the CCWG Report.
CAE-3
Motion No. 26, Docket No. 25-08-02, p. 7. Provide data for a representative
sample of RRES projects to demonstrate whether UI’s recommended
method for calculating proxy solar generation using AC inverter nameplate
capacity accurately reflects generation as measured at the production
meter. If estimated and actual production differ significantly, explain the
potential factors that contribute to the difference.
CAE-4
Motion No. 26, Docket No. 25-08-02, pp. 9-10. Provide a cost and timeline
estimate for billing system updates to enable automated calculation and
tracking for non-bypassable charges and incentive adders, if UI’s proposal
for using proxy production data for RRES customers with DC-coupled solar
and storage systems were approved by the Authority. Additionally, provide
an estimate of the costs UI would incur to administer the proxy method
through an auditable external calculation and periodic bill adjustment or
true-up process. In the response, describe the methodology used to
develop these estimates, including: (i) key assumptions; (ii) identification of
system components and workflows affected; and (iii) labor, software, and
integration cost drivers.
Interrogatories CAE-5 and CAE-6 are directed to The Connecticut Light and
Power Company d/b/a Eversource Energy (Eversource).
CAE-5
Motion No. 26, Docket No. 25-08-02, p. 4. UI identifies 160 RRES projects
with Permission to Operate (PTO), or 1.8% percent of the current RRES
projects with PTO, that are potentially affected by issues related to DCcoupled solar and storage devices utilizing a shared inverter. Provide the
number of impacted RRES projects in Eversource service territory.
CAE-6
Motion No. 26, Docket No. 25-08-02, pp. 9-10. Provide a cost and timeline
estimate for billing system updates to enable automated calculation and
tracking for non-bypassable charges and incentive adders, if UI’s proposal
for using proxy production data for RRES customers with DC-coupled solar
and storage systems were approved by the Authority. In the response,
describe the methodology used to develop these estimates, including: (i)
key assumptions; (ii) identification of system components and workflows
affected; and (iii) labor, software, and integration cost drivers.
Interrogatories CAE-7 through CAE-11 are directed individually to Eversource and
UI (collectively, the electric distribution companies or EDCs).
CAE-7
What percentage of RRES customers receiving adders have adder
payments directed to a third-party beneficiary? Provide the percentage
separately for the low-income and distressed municipality adder.
CAE-8
CCWG Report, p. 59. Which of the CCWG’s proposed changes to the
customer disclosure forms would require changes in PowerClerk? Discuss
the feasibility of adding standardized rates in the PowerClerk RRES
application, with the option for users to override the default standardized
rate when allowed to do so. If PowerClerk changes are required, provide
an estimated cost and timeline for implementation.
CAE-9
Motion No. 26, Docket No. 25-08-02. Describe the company’s current
practice for applying non-bypassable charges, applying income-eligible and
distressed municipality adders, and certifying REC eligibility for RRES
Program customers with DC-coupled solar and storage systems utilizing a
shared inverter.
CAE-10
Motion No. 26, Docket No. 25-08-02, pp. 10. Provide an estimate of the
annual lost EDC revenue if the RECs associated with DC-coupled solar and
storage systems are no longer sold into the market.
CAE-11
Describe the NEPOOL GIS requirements for verifying Class I REC eligibility.
Interrogatory CAE-12 is directed individually to UI, Eversource, and the Office of
Consumer Counsel (OCC).
CAE-12
CCWG Report, pp. 21-22. Explain why adders and storage incentives
should not be included in net savings calculations presented to customers.
Interrogatory CAE-13 is directed to the Office of Education, Outreach, and
Enforcement (EOE).
CAE-13
CCWG Report, pp. 47-48. For each of the two recommended allowable
methodologies for determining the starting utility rate that require a written
explanation (customer-specific and software methodology), provide an
example of how the methodology and parameters should be explained to
customers.
Interrogatories CAE-14 through CAE-20 are directed individually to Earthlight
Technologies, GoodLeap, Ion Solar, Ion Solar Pros, SAVKAT, SunRun, Tesla, and
Trinity Solar.
CAE-14
CCWG Report, p. 7. In what cases would residential solar contractors not
provide multi-year net saving estimates to customers?
CAE-15
CCWG Report, pp. 14, 24. In what cases would contractors provide
customers with multi-year savings estimates for terms less than 20 years?
CAE-16
For RRES projects paired with storage, do contractors include the value of
ESS incentives in the net savings estimates provided to customers?
CAE-17
CCWG Report, p. 31. Discuss the prevalence of customers opting to cancel
contracts within the three-day rescission period. Provide the percentage of
contracts that are rescinded within the three-day period, if available.
CAE-18
CCWG Report, p. 46. Discuss the method(s) contractors currently use to
determine the starting utility rate. If software platforms are used, do they
account for customer-specific rates such as low-income discount rates or
third-party supply rates?
CAE-19
CCWG Report, pp. 31, 48. Clarify whether EOE’s recommendation of
presenting completed customer disclosure forms “immediately prior to and
contemporaneously with the solar contract” would require that the customer
disclosure form be generated outside PowerClerk and uploaded to
PowerClerk after signing. If so, comment on the likelihood of introducing
transcription errors when the information from the customer disclosure form
is entered into PowerClerk.
CAE-20
In other states in which solar contractors operate that have similar customer
disclosure requirements, at what point in the sales and contracting process
are contractors required to provide completed customer disclosure forms to
customers?
Interrogatory CAE-21 is directed to Tesla.
CAE-21
CCWG Report, p. 29. Provide more precise language for Proposal 19 that
would allow Tesla to support the proposal.
As listed on the current system
Interrogs from CAE to Earthlight Technologies, LLC;GoodLeap;Ion Solar Pros, LLC;Savkat, Inc.;Sunrun, Inc.;Sunrun, Inc.;Tesla, Inc.;Trinity Solar, Inc. 14 thru 20-Issued 05/11/2026 [26-08-02]