Compliance Filing, Order No. 17Filed by Avangrid
Compliance with Order No. 17
- Type of filing
- Compliance filing (Compliance Filing, Order No. 17)
- Date filed
- July 31, 2026
- Filed by
- Avangrid
- Files
- 2
As listed on the current system: Compliance Filings, 07/31/2026 [26-08-03] Order No.17 / Avangrid / Compliance with Order No. 17
Files
2026-07-31 UI Compliance with Order No. 17 Cover Letter #26-08-03.pdf
PDF · 157 KB · 3 pagesText searchable
Download 2026-07-31 UI Compliance with Order No. 17 Cover Letter #26-08-03.pdfRead the text of 2026-07-31 UI Compliance with Order No. 17 Cover Letter #26-08-03.pdf
2026-07-31 UI Order 17 - Attachment 1 #26-08-03.xlsx
Excel · 28 KBText searchable
Download 2026-07-31 UI Order 17 - Attachment 1 #26-08-03.xlsxRead the text of 2026-07-31 UI Order 17 - Attachment 1 #26-08-03.xlsx
Text of 2026-07-31 UI Compliance with Order No. 17 Cover Letter #26-08-03.pdf
Extracted from the file · 4,884 characters
July 31, 2026
Mr. Jeffrey R. Gaudiosi, Esq.
Executive Secretary
Public Utilities Regulatory Authority
10 Franklin Square
New Britain, CT 06051
Re:
Docket No. 26-08-03, Annual Non-Residential Renewable Energy Solutions Program
Review Year 5, Compliance with Order No. 17 of the Final Decision in Docket No. 2508-03
Dear Mr. Gaudiosi,
Pursuant to the Public Utilities Regulatory Authority’s (“PURA” or the “Authority”) Final
Decision in Docket 25-08-03 (“Decision”) dated December 17, 2025, The United Illuminating
Company (“UI” or the “Company”) respectfully submits Order No. 17 of the Decision which
states:
No later than August 1, 2024, and annually thereafter, each EDC shall file as
compliance in the most recent annual review docket (i.e., in 2024, Docket No. 2408-04) a NRES Interconnection Report. The Report shall consist of a summary of
the state of interconnection for all approved NRES projects to date and shall
include, at a minimum, (1) the interconnection status of each NRES project; (2)
the EDC interconnection approval due date for each project per approved
interconnection guidelines; (3) the number of days from when all required
interconnection materials were submitted to the utility for each project to
interconnection approval, or to when the data was pulled for the report, if
interconnection approval has not been granted; (4) the date for which data was
pulled for the report; (5) the project attrition rate; (6) a list of the most common
reasons for interconnection delays; and (7) EDC-proposed solutions for each of
the most common reasons delaying interconnection.
1. The interconnection status of each NRES project.
Response: The interconnection status of each NRES project can be found in
Attachment 1 column C.
2. The EDC interconnection approval due date for each project per approved
interconnection guidelines.
Response: The EDC interconnection approval due date for projects per approved
interconnection guidelines is available in Attachment 1 column D. Please note that the
Interconnection Guidelines establish EDC approval timelines only for projects that
have successfully completed the interconnection review process and have been
granted Approval to Energize (ATE) status.
1
The Interconnection Guidelines do not define a due date, target completion date, or
Electric Distribution Company (EDC) approval deadline for projects that have not yet
reached the ATE milestone. Accordingly, UI's reported data is limited to projects that
have completed the interconnection review process and received an ATE, as these
are the only projects for which guideline-based approval due dates are established.
3. The number of days from when all required interconnection materials were submitted
to the utility for each project to interconnection approval, or to when the data was
pulled for the report, if interconnection approval has not been granted.
Response: Please see Attachment 1 column E.
4. The date for which data was pulled for the report.
Response: The data for this order was pulled on July 28, 2026 and contains data
from the inception of the program through July 28, 2026.
5. The project attrition rate.
Response: The project attrition rate is 6%.
6. A list of the most common reasons for interconnection delays.
Response: The most common reasons for interconnection delays include:
• Incomplete or inaccurate applications
• Complex technical reviews
• Regulatory compliance burdens
• High application volumes
• Multi-team coordination challenges
• Metering configuration and provisioning delays
• System inefficiencies and resource constraints
7. EDC-proposed solutions for each of the most common reasons delaying
interconnection.
Response: UI’s solutions for the most common reasons delaying interconnection
referenced above include:
•
PowerClerk has been enhanced to add a “chess clock,” which will assign
either the EDC or customer to a task, increasing assignee
transparency and reducing incomplete or inaccurate application correction
times.
•
Integration in place of a mandatory pre-submission checklist to reduce
application errors and improve completeness during the initial application
stage.
2
•
Multiple updates and continuous process adjustments have been
implemented to include enhancements to the meter procurement,
programming, and installation timelines through internal process
streamlining in turn, expediting the time from authority
having jurisdiction (AHJ) approval to permission to operate.
The implementation of these solutions continues to assist with addressing the root
causes of delays and improve the overall efficiency of the interconnection application
process.
I hereby certify service of this filing upon all parties and intervenors of record in this proceeding.
Very truly yours,
James Nitz
Manager, Regulatory Services
UIL Holdings Corporation
As Agent for The United Illuminating Company
3
Text of 2026-07-31 UI Order 17 - Attachment 1 #26-08-03.xlsx
Extracted from the file · 14,540 characters
[Sheet: Order No. 17]
Program Year | Tariff ID | Question 1. Project Status | Question 2. Interconnection Approval to Energize Date | Question 3. Days from Interconnection Submittal to Interconnection Approval | System Design Capacity (SDC) kW AC
Year 1 | NS40181 | Energize System | 2024-06-14 00:00:00 | 595 | 75
Year 1 | NS40173 | Energize System | 2023-10-05 00:00:00 | 318 | 120
Year 2 August | NS45165 | Energize System | 2024-07-31 00:00:00 | 567 | 43.2
Year 1 | NS40185 | Energize System | 2025-09-17 00:00:00 | 880 | 100
Year 2 August | NS45163 | Energize System | 2024-07-18 00:00:00 | 442 | 17.3
Year 1 | NS40168 | Energize System | 2023-09-07 00:00:00 | 123 | 150
Year 2 February | NS43231 | Energize System | 2023-12-12 00:00:00 | 209 | 200
Year 2 February | NS43237 | Energize System | 2023-10-25 00:00:00 | 151 | 67.3
Year 1 | BS40184 | Energize System | 2024-03-13 00:00:00 | 202 | 200
Year 2 February | BS43228 | Energize System | 2023-12-11 00:00:00 | 103 | 50
Year 2 February | NS43233 | Energize System | 2023-12-25 00:00:00 | 70 | 187.5
Year 2 February | BM43641 | Energize System | 2024-12-09 00:00:00 | 413 | 720
Year 2 February | BS43234 | Energize System | 2025-02-19 00:00:00 | 332 | 100
Year 2 August | NM45685 | Energize System | 2025-02-19 00:00:00 | 320 | 700
Year 3 February | BS46900 | Energize System | 2025-10-16 00:00:00 | 557 | 80
Year 2 August | NS45179 | Energize System | 2024-12-18 00:00:00 | 247 | 75
Year 3 February | NS46940 | Energize System | 2024-12-23 00:00:00 | 213 | 86.4
Year 2 February | BM43646 | Energize System | 2026-05-13 00:00:00 | 718 | 400
Year 2 February | BS43226 | Energize System | 2026-07-23 00:00:00 | 785 | 200
Year 2 February | BM43645 | Energize System | 2026-05-08 00:00:00 | 706 | 250
Year 1 | BS40180 | Energize System | 2025-02-18 00:00:00 | 236 | 50
Year 3 February | BS46902 | Energize System | 2025-11-20 00:00:00 | 508 | 67.3
Year 1 | NM40407 | Energize System | 2025-08-07 00:00:00 | 389 | 420
Year 2 August | BS45175 | Energize System | 2026-04-14 00:00:00 | 620 | 50
Year 2 August | NS45167 | Energize System | 2025-09-11 00:00:00 | 405 | 200
Year 2 August | NS45164 | Energize System | 2026-01-19 00:00:00 | 486 | 27.3
Year 3 February | BS47002 | Energize System | 2025-06-04 00:00:00 | 248 | 100
Year 2 August | NS45169 | Energize System | 2025-12-23 00:00:00 | 447 | 200
Year 2 August | NS45166 | Energize System | 2026-01-29 00:00:00 | 472 | 193
Year 2 August | BM45744 | Energize System | 2026-07-09 00:00:00 | 621 | 750
Year 3 February | BS47001 | Energize System | 2025-09-17 00:00:00 | 325 | 120
Year 2 August | BS45171 | Energize System | 2025-11-13 00:00:00 | 368 | 200
Year 1 | NM40286 | Energize System | 2025-12-24 00:00:00 | 409 | 433
Year 3 February | BS47003 | Energize System | 2025-11-13 00:00:00 | 365 | 120
Year 3 February | NE47246 | Energize System | 2025-03-05 00:00:00 | 101 | 460
Year 2 February | BS43221 | Energize System | 2025-08-21 00:00:00 | 236 | 200
Year 2 February | BS43222 | Energize System | 2025-08-21 00:00:00 | 236 | 200
Year 3 February | NS46886 | Energize System | 2025-07-24 00:00:00 | 201 | 67.3
Year 2 August | BS45174 | Energize System | 2026-05-20 00:00:00 | 499 | 200
Year 2 August | NL45716 | Energize System | 2026-06-26 00:00:00 | 525 | 960
Year 2 August | NS45173 | Energize System | 2025-07-24 00:00:00 | 177 | 75
Year 1 | NS40192 | Energize System | 2025-12-22 00:00:00 | 326 | 43.2
Year 3 February | NM47218 | Pending Approval To Energize | 2026-06-24 00:00:00 | 476 | 210
Year 3 August | BS48658 | Energize System | 2026-01-15 00:00:00 | 313 | 140
Year 3 August | NS48678 | Energize System | 2025-12-18 00:00:00 | 196 | 50
Year 4 Feb | NS50766 | Energize System | 2026-05-22 00:00:00 | 344 | 160
Year 3 August | NM49115 | Energize System | 2026-04-20 00:00:00 | 301 | 225
Year 4 February | NE51053 | Energize System | 2025-09-29 00:00:00 | 96 | 460
Year 3 August | NS48710 | Energize System | 2026-01-02 00:00:00 | 161 | 196
Year 3 August | NS48711 | Energize System | 2026-02-11 00:00:00 | 189 | 175
Year 4 Feb | NS50925 | Energize System | 2025-12-18 00:00:00 | 116 | 80
Year 3 August | BS48614 | Energize System | 2026-04-08 00:00:00 | 214 | 17.3
Year 2 August | BM45723 | Energize System | 2026-06-03 00:00:00 | 268 | 348
Year 3 August | BS48589 | Energize System | 2025-09-18 00:00:00 | 9 | 150
Year 4 Feb | BS50697 | Energize System | 2026-02-12 00:00:00 | 150 | 100
Year 4 Feb | BS50685 | Energize System | 2026-06-09 00:00:00 | 258 | 100
Year 4 Aug | BS52575 | Energize System | 2026-06-26 00:00:00 | 231 | 125
Year 3 August | NS48702 | Energize System | 2026-04-29 00:00:00 | 99 | 32
Year 3 February | BE47262 | Construction in Process | 2125
Year 1 | BM40343 | Construction in Process | 600
Year 3 February | BS46988 | Contingent Approval to Interconnect | 200
Year 3 August | BS48605 | Contingent Approval to Interconnect | 200
Year 4 Aug | BS52749 | Contingent Approval to Interconnect | 100
Year 1 | BS40174 | Contingent Approval to Interconnect | 192.5
Year 3 February | BS46904 | Contingent Approval to Interconnect | 112.5
Year 3 August | BS48680 | Contingent Approval to Interconnect | 150
Year 4 Feb | BS50708 | Contingent Approval to Interconnect | 200
Year 4 Feb | BS50713 | Contingent Approval to Interconnect | 200
Year 4 Feb | BS50728 | Contingent Approval to Interconnect | 75
Year 4 Feb | BS50773 | Contingent Approval to Interconnect | 200
Year 4 Feb | BS50789 | Contingent Approval to Interconnect | 34.6
Year 3 August | NM48869 | Contingent Approval to Interconnect | 300
Year 4 Feb | NM51067 | Contingent Approval to Interconnect | 240
Year 3 February | NS46913 | Contingent Approval to Interconnect | 75
Year 3 August | NS48651 | Contingent Approval to Interconnect | 100
Year 4 Feb | NS50762 | Contingent Approval to Interconnect | 33.3
Year 5 February | NS54456 | Contingent Approval to Interconnect | 50
Year 3 August | BM49130 | Facility Study Started | 966
Year 4 Feb | BM51019 | Impact Study Started | 966
Year 2 August | BM45696 | Interconnection Agreement Sent - Customer Action Required | 840
Year 4 February | BL51064 | Interconnection Validation | 3000
Year 4 Feb | BS50714 | Interconnection Validation | 200
Year 4 Feb | BS50742 | Interconnection Validation | 100
Year 5 February | BS54632 | Interconnection Validation | 60
Year 5 February | BS54636 | Interconnection Validation | 100
Year 4 Feb | BS50775 | NRES - Bid Selected | 106
Year 4 Feb | NS50659 | NRES - Bid Selected | 30
Year 3 August | BL49128 | NRES - PURA Approved | 1000
Year 1 | BM40275 | NRES- Bid Evaluation | 600
Year 2 February | BM43664 | NRES - PURA Approved | 250
Year 2 August | BM45726 | NRES - PURA Approved | 350
Year 2 August | BM45728 | NRES - PURA Approved | 562.5
Year 2 August | BM45731 | NRES - PURA Approved | 300
Year 2 August | BM45734 | NRES - PURA Approved | 580
Year 3 February | BM47265 | NRES - PURA Approved | 669.6
Year 3 August | BM49125 | NRES - PURA Approved | 700
Year 3 August | BM49127 | NRES - PURA Approved | 330
Year 3 August | BM49129 | NRES - PURA Approved | 206
Year 4 Feb | BM51062 | NRES - PURA Approved | 999
Year 4 Aug | BM53121 | NRES - PURA Approved | 216
Year 4 Aug | BM53137 | NRES - PURA Approved | 456
Year 4 Aug | BM53138 | NRES - PURA Approved | 556
Year 5 February | BM54627 | NRES - PURA Approved | 600
Year 5 February | BM54646 | NRES - PURA Approved | 400
Year 5 February | BM54647 | NRES - PURA Approved | 999
Year 1 | BS40269 | NRES - Bid Evaluation | 199.8
Year 2 February | BS43220 | NRES - PURA Approved | 50
Year 2 February | BS43223 | NRES - PURA Approved | 200
Year 2 February | BS43224 | NRES - PURA Approved | 200
Year 2 February | BS43225 | NRES - PURA Approved | 150
Year 2 February | BS43230 | NRES - PURA Approved | 200
Year 2 February | BS43236 | NRES - PURA Approved | 200
Year 2 February | BS43240 | NRES - PURA Approved | 200
Year 2 February | BS43241 | NRES - PURA Approved | 75
Year 2 August | BS45170 | NRES - PURA Approved | 200
Year 2 August | BS45178 | NRES - PURA Approved | 100
Year 3 February | BS46921 | NRES - PURA Approved | 200
Year 3 February | BS46922 | NRES - PURA Approved | 100
Year 3 February | BS47013 | NRES - PURA Approved | 150
Year 3 February | BS47015 | NRES - PURA Approved | 120
Year 3 February | BS47021 | NRES - PURA Approved | 199.99
Year 3 February | BS47022 | NRES - PURA Approved | 199.99
Year 3 August | BS48674 | NRES - PURA Approved | 200
Year 3 August | BS48685 | NRES - PURA Approved | 200
Year 3 August | BS48714 | NRES - PURA Approved | 200
Year 3 August | BS48730 | NRES - PURA Approved | 200
Year 3 August | BS48739 | NRES - PURA Approved | 60
Year 3 August | BS48740 | NRES - PURA Approved | 40
Year 4 Feb | BS50672 | NRES - PURA Approved | 150
Year 4 Feb | BS50757 | NRES - PURA Approved | 80
Year 4 Feb | BS50768 | NRES - PURA Approved | 100
Year 4 Aug | BS52654 | NRES - PURA Approved | 200
Year 4 Aug | BS52727 | NRES - PURA Approved | 100
Year 4 Aug | BS52733 | NRES - PURA Approved | 32.5
Year 4 Aug | BS52759 | NRES - PURA Approved | 100
Year 4 Aug | BS52761 | NRES - PURA Approved | 200
Year 4 Aug | BS52765 | NRES - PURA Approved | 120
Year 5 February | BS54393 | NRES - PURA Approved | 75
Year 5 February | BS54420 | NRES - PURA Approved | 200
Year 5 February | BS54422 | NRES - PURA Approved | 100
Year 5 February | BS54423 | NRES - PURA Approved | 200
Year 5 February | BS54424 | NRES - PURA Approved | 200
Year 5 February | BS54452 | NRES - PURA Approved | 200
Year 5 February | BS54455 | NRES - PURA Approved | 50
Year 5 February | BS54468 | NRES - PURA Approved | 100
Year 5 February | BS54591 | NRES - PURA Approved | 200
Year 5 February | BS54609 | NRES - PURA Approved | 200
Year 4 August | NE53113 | NRES - PURA Approved | 460
Year 4 August | NE53142 | NRES - PURA Approved | 2925
Year 1 | NM40290 | NRES - Bid Evaluation | 240
Year 2 February | NM43662 | NRES - PURA Approved | 448
Year 2 February | NM43665 | NRES - PURA Approved | 260
Year 2 August | NM45703 | NRES - PURA Approved | 300
Year 4 Feb | NM51063 | NRES - PURA Approved | 760
Year 5 February | NM54648 | NRES - PURA Approved | 720
Year 2 February | NS43227 | NRES - PURA Approved | 175
Year 2 February | NS43253 | NRES - PURA Approved | 165
Year 2 August | NS45168 | NRES - PURA Approved | 200
Year 3 February | NS46883 | NRES - PURA Approved | 25
Year 3 February | NS46912 | NRES - PURA Approved | 200
Year 3 February | NS47025 | NRES - PURA Approved | 18.43
Year 3 August | NS48583 | NRES - PURA Approved | 66.8
Year 3 August | NS48690 | NRES - PURA Approved | 50
Year 4 Feb | NS50649 | NRES - PURA Approved | 20
Year 4 Feb | NS50650 | NRES - PURA Approved | 34.6
Year 4 Feb | NS50734 | NRES - PURA Approved | 16.15
Year 4 Feb | NS50780 | NRES - PURA Approved | 100
Year 4 Feb | NS51068 | NRES - PURA Approved | 25.2
Year 4 Aug | NS53136 | NRES - PURA Approved | 33.3
Year 5 February | NS54464 | NRES - PURA Approved | 50
Year 5 February | NS54565 | NRES - PURA Approved | 18
Year 5 February | NS54639 | NRES - PURA Approved | 200
Year 3 February | BS46952 | Pending Electrical Inspector Release | 50
Year 3 February | BS46963 | Pending Electrical Inspector Release | 200
Year 4 Feb | BS50641 | Pending Electrical Inspector Release | 80
Year 4 Aug | BS52565 | Pending Electrical Inspector Release | 37.63
Year 4 Aug | BS52566 | Pending Electrical Inspector Release | 11.52
Year 4 Aug | BS52632 | Pending Electrical Inspector Release | 200
Year 3 February | NM47217 | Pending Electrical Inspector Release | 480
Year 4 Feb | NS50663 | Pending Electrical Inspector Release | 7.6
Year 4 Aug | NS52757 | Pending Electrical Inspector Release | 50
Year 4 Feb | BM51020 | Pending Facility Study | 966
Year 4 Feb | BM51066 | Pending Facility Study | 480
Year 4 Feb | BS50705 | Pending Meter Installation | 22.8
Year 4 Feb | BS50686 | Pending Witness Test | 200
Year 5 February | BL54611 | Study In Process | 4999
Year 4 Feb | BM50765 | Technical Re-Review | 269
Year 5 February | BS54437 | Technical Re-Review | 200
Year 5 February | BM54614 | Technical Review | 960
Year 5 February | BM54616 | Technical Review | 960
Year 5 February | BM54620 | Technical Review | 480
Year 5 February | BM54621 | Technical Review | 300
Year 5 February | BM54622 | Technical Review | 500
Year 5 February | BM54625 | Technical Review | 600
Year 5 February | BS54615 | Technical Review | 120
Year 5 February | BS54623 | Technical Review | 100
Year 5 February | BS54624 | Technical Review | 150
Year 5 February | BS54626 | Technical Review | 120
Year 5 February | BS54628 | Technical Review | 150
Year 5 February | BS54629 | Technical Review | 300
Year 5 February | BM54634 | Technical Review | 360
Year 5 February | BS54466 | Technical Review | 200
Year 5 February | BS54467 | Technical Review | 200
Year 2 August | BM45730 | Technical Review Feedback– Customer Action Required | 670
Year 3 February | BM47259 | Technical Review Feedback– Customer Action Required | 999
Year 3 August | BS48720 | Technical Review Feedback– Customer Action Required | 99.9
Year 4 Feb | BS50739 | Technical Review Feedback– Customer Action Required | 200
Year 4 Feb | BS50767 | Technical Review Feedback– Customer Action Required | 200
Year 5 February | BS54441 | Technical Review Feedback– Customer Action Required | 200
Year 5 February | BS54451 | Technical Review Feedback– Customer Action Required | 200
Year 2 August | BM45733 | Validation On Hold | Corrections Required | 360
Year 3 February | BS47020 | Validation On Hold | Corrections Required | 100
Year 3 August | BS48722 | Validation On Hold | Corrections Required | 200
Year 4 Aug | BS52723 | Validation On Hold | Corrections Required | 200
Year 4 Aug | BS52724 | Validation On Hold | Corrections Required | 200
Year 4 Aug | BS52725 | Validation On Hold | Corrections Required | 50
Year 4 Aug | BS52726 | Validation On Hold | Corrections Required | 200
Year 4 Feb | NS50781 | Validation On Hold | Corrections Required | 75
Year 5 February | BS54436 | Validation On Hold | Corrections Required | 199.8
Year 2 February | BL43623 | Withdrawn | 960
Year 2 February | BL43625 | Withdrawn | 840
Year 2 August | BL45740 | Withdrawn | 990
Year 2 February | BM43624 | Withdrawn | 500
Year 2 February | BM43650 | Withdrawn | 996
Year 1 | BS40175 | Withdrawn | 60
Year 2 February | BS43229 | Withdrawn | 200
Year 3 February | BS46994 | Withdrawn | 200
Year 3 February | BS47018 | Withdrawn | 200
Year 4 Feb | BS50688 | Withdrawn | 100
Year 4 Feb | BS50689 | Withdrawn | 200
Year 1 | NM40285 | Withdrawn | 390
Year 2 August | NS45177 | Withdrawn | 50
Year 3 August | NS48725 | Withdrawn | 200