Interrogatory responses
Answers to questions 1 thru 4
Filed by CL&P dba Eversource Energy4 files
Part of docket 26-08-03Files4
CL&P dba Eversource Energy
Docket 26-08-03
Set PURA-01
Date Issued September 21, 2026
CAE-001
Page 1 of 2
Date Filed: October 05, 2026
Witness:
Rice, Brian J
Request from: Public Utilities Regulatory Authority
Question:
Motion No. 12, June 5, 2026, Docket No. 25-08-03, Ex. B1; Motion No. 16, July 1, 2026, Docket
No. 25-08-03, Ex. B. Describe the methodology used to calculate expected annual production for
each project bid, including the capacity factor and any other assumptions used. Justify the
methodology and explain whether it continues to provide a reasonable estimate of actual annual
production.
Response:
The EDCs use a standardized methodology to calculate expected annual production for NRES
Projects. For solar Projects, the EDCs use a 15% capacity factor as the standard assumption, unless
a Bidder provides documentation supporting a different capacity factor based on project-specific
characteristics. The standard calculation is: Installed Capacity (kW AC) × 8,760 hours/year × 15%
capacity factor.
The NRES Program Manual provides for the use of this standardized capacity factor and allows
the EDCs to consider an alternative capacity factor where project-specific characteristics, such as
panel orientation or shading, are supported by appropriate documentation. The EDCs use this
standardized methodology to provide a consistent and administratively efficient approach for
estimating expected annual production across NRES Projects. Estimated annual production is also
used in determining project compensation in budget-based solicitations.
To evaluate whether the 15% capacity factor continues to provide a reasonable estimate of actual
annual production, Eversource reviewed 80 NRES projects with complete 2025 production data.
For each project actual 2025 production was compared with estimated annual production based on
the 15% capacity factor. The average percentage difference across the 80 Projects was
approximately 2%, indicating that, on an aggregate basis, the 15% methodology did not result in
a material systematic over or under estimation of production.
The EDCs also calculated the average absolute percentage difference, which was approximately
19%. This measure reflects the magnitude of the difference between estimated and actual
production without regard to whether the estimate was higher or lower than actual production. The
difference between the two measures reflects the fact that project-specific over and underestimates
offset one another when calculating the average percentage difference.
The EDCs believe that these results support continued use of the 15% capacity factor as a
standardized program-administration methodology, while recognizing that actual production can
CL&P dba Eversource Energy
Docket 26-08-03
Set PURA-01
Date Issued September 21, 2026
CAE-001
Page 2 of 2
vary from the estimate for individual Projects. The EDCs will continue to consider project-specific
documentation supporting an alternative capacity factor where appropriate.
As listed on the current system