STATE OF CONNECTICUT
PUBLIC UTILITIES REGULATORY AUTHORITY
ANNUAL NON-RESIDENTIAL RENEWABLE ENERGY SOLUTIONS PROGRAM
REVIEW – YEAR 6
:
:
:
DOCKET NO. 26-08-03
AUGUST 20, 2026
NRES YEAR SIX WRITTEN COMMENTS
Verogy Holdings, LLC (“Verogy”) respectfully submits the following comments in response to the
Notice of Request for Written Comments from the Public Utilities Regulatory Authority (“PURA” or “The
Authority”) issued on August 5, 2026, in the subject docket intended to align the NRES program with its stated
objectives1.
1. RECOMMENDED PRICE CAPS AND BID PREFERENCES
i. Comment: Verogy asserts that since the issuance of the NRES Year 5 Final Decision
on December 17, 2025, there have been significant changes to circumstances entirely
outside of the control of NRES program participants which justify further increases to
program price caps. Namely, on August 6, 2026, the Federal Government issued a
decision regarding the “Section 232 Tariffs” and established, amongst other price
controls, a minimum import price of $0.22/Wdc for solar cells, $0.38/Wdc for solar
modules and an additional 15% ad valorem tariff (with exceptions for certain “U.S.
Treaty Partners”)2. While the Section 232 Tariffs are scheduled to go into effect
December 4, 2026, both domestic and international module vendors are now aware of
the decision and have immediately begun increasing equipment prices. While the final
impacts of the Section 232 Tariff has yet to be settled at the time of writing these
comments, Verogy has received indication from various module suppliers that these
Section 232 Tariffs will likely increase module cost by at least $0.11 - $0.13/Wdc for
imported modules and $0.10 - $0.15/W for domestically manufactured modules
(though the impact to domestic module prices is less certain at this time). Depending
1 The objectives (Program Objectives) outlined in the Year 5 NRES Final Decision include:
1.
2.
3.
4.
5.
Foster the sustained, orderly development of the state’s Class I renewable energy industry;
Deploy the full megawatt capacity allowable under statute, to the extent possible;
Ensure least-cost outcomes through the annual solicitation process;
Enable program accessibility for customers through simplified program and tariff designs; and
Encourage increased inclusivity overall, as well as program participation by customers in underserved and environmental justice
communities.
2 Adjusting Imports of Polysilicon and its Derivatives into the United States – The White House
1
on the exact design and equipment spec of a non-canopy NRES project, the Section
232 Tariffs likely imply an approximate 5 – 7.5% unavoidable increase in build cost.
Therefore, Verogy asserts that the Section 232 Tariffs alone justify a commensurate
increase of 5 – 7.5% to the various NRES Year 5 price caps.
Beyond the imposition of the Section 232 Tariffs, Verogy suggests that other factors,
either entirely or largely outside of the control of NRES Project Developers, justify
further price cap increases. These include ever-increasing and unilaterally imposed
interconnection costs with no effective way to share cost-share, a constrained supply
chain resulting from the rush to safe harbor projects by July 4, 2026, or have projects
placed in service by December 31, 2027, and economy-wide inflation resulting from
the ongoing conflict in the Middle East.
Verogy suggests that even without the budgetary program cap in place, price cap
increases would be justified for these reasons. However, should the budgetary program
cap be retained, the budgetary cap would limit ratepayer impact should price cap
increases be adopted.
2. RECOMMENDED PROGRAMMATIC CHANGES
a) Removal of Budgetary Program Cap
i. Comment: Verogy strongly asserts that the budgetary program cap imposed in NRES
Year 5 creates a barrier of entry for projects that would otherwise be eligible for the
NRES program and economically feasible under the program price caps and statutory
annual procurement limit of 100 MWac, running contrary to Program Objectives1 &
2. Additionally, Verogy believes that the budgetary program cap runs contrary to the
plain language and intent of the Program’s enabling statute and was established
without proper authorization.
Public Act 25-173 § 9 altered Conn. Gen. Stat. § 16-244z(c)(1)(B) to state:
“For procurement and tariff years commencing on and after January 1, 2025, the
authority may exceed the limits on total available megawatts…(if) the aggregate dollar
2
amount of procurements of energy and renewable energy credits over the tariff term
for all selected projects does not exceed the aggregate dollar amount of procurements
of energy and renewable energy credits over the tariff term for all projects selected in
such program during the calendar year 2024. The authority shall determine the manner
of exceeding such limits”3 (emphasis added).
Verogy asserts that The Authority’s interpretation of Conn. Gen. Stat. § 16244z(c)(1)(B) does not grant The Authority the ability to establish a budgetary
procurement cap in addition to the existing megawatt procurement caps that would
reduce available megawatts in the NRES program. Conn. Gen. Stat. § 16244z(c)(1)(B) specifically grants The Authority the ability to exceed existing megawatt
caps if the aggregate cost of a future procurement is less than 2024 levels, as only the
word “exceed” is used throughout this section. It is well established in Connecticut that
administrative agencies are strictly limited by their express statutory authority. Such
action to reduce the MW caps is ultra vires. The language of the statute and intent of
the legislation is clear on its face. Notwithstanding this plain language, understanding
the history and context of the Connecticut distributed generation programs makes it
even clearer that the purpose of the megawatt cap for the SCEF and NRES programs
was to replace a budgetary cap. The legacy LREC/ZREC programs contained
budgetary caps and were in use for nearly a decade, the legislature in passing the laws
to create the NRES and SCEF programs after the LREC/ZREC programs explicitly and
intentionally installed a megawatt cap and not a budgetary cap. This context makes the
unilateral installation of a budgetary cap by The Authority even more inappropriate.
The underlying rationale, explicitly called out, for taking this measure was to reduce
ratepayer costs.4 However, the most significant cost increase faced by Connecticut
ratepayers is caused by the dearth of in-state energy supply. To take the position that
3 AN ACT CONCERNING ENERGY AFFORDABILITY, ACCESS AND ACCOUNTABILITY.
4 Section IV.B.4 of the SCEF Year 7 Final Decision states:
“The Authority’s adoption of a budgetary cap falls squarely within the broad discretion granted under General Statutes § 16-244z(c)(1)(A),
which authorizes PURA to monitor the SCEF Program’s competitiveness and adjust the annual purchase amount or other procurement
parameters as necessary. The statute expressly provides this flexibility to maintain a competitive and efficient program. This approach also
aligns with the intent of General Statutes § 16-244z(c)(1)(B), which allows the selection of projects exceeding the applicable MW cap in
future years provided that total program costs do not exceed the aggregate cost of projects selected in 2024. While General Statutes § 16244z(c)(1)(B) does not expressly contemplate instances in which the total 2024 cost limit is exceeded even if the MW cap is not, the
Authority’s broad authority under § 16-244z(c)(1)(A) encompasses the ability to impose comparable cost-based constraints on overall
SCEF Program expenditures.”
3
the costs of the NRES program, or distributed generation programs entirely, are the
main driver for cost increases for ratepayers is to believe an EDC straw man for the
culprit of cost drivers and miss the forest for the trees. Ultimately, by effectively
replacing the megawatt program cap, The Authority contradicted plain statutory
language and legislative intent to increase the cost of electricity for Connecticut
ratepayers.
Beyond running counter to state statute and clean energy goals, Spring 2026 NRES
results56 clearly demonstrate that the budgetary cap is acting as a barrier to entry to
otherwise viable NRES projects. In the Year 5 Spring Auction, both Eversource and
United Illuminating fully exhausted their budgetary allocation for their “Medium”
category despite awarding only 67% and 45% of their respective capacity allocations.
This trend also held true for the Eversource SCEF Year 7 procurement as described in
Verogy’s SCEF Year 8 Written Comments submitted to DEEP7.
Verogy strongly requests that The Authority rescind the NRES budgetary program cap
entirely from NRES Year 6, as the budgetary cap hampers Program Objectives 1, 2 and
4 and was established without proper authorization or process. Additionally, all MWs
from preceding solicitations not awarded as a result of this impermissible budgetary
cap should be added to the Year 6 MW allocation.
b) Reallocation Of Unallocated Small Capacity and Budget
i. Comment: Section 5.6.3 of the NRES Year 6 Program Manual proposed by the EDCs8
states, in part:
“If either EDC has uncommitted MWs remaining in the small zero emission category
and such MWs cannot accept the next full Project or all eligible Bids in the
5 Eversource NRES Year 5 Spring Auction Results: year-5-feb-public-summary-data.xlsx
6 United Illuminating NRES Year 5 Spring Auction Results: Motion No. 016 Docket 25-08-03
7 Available at:
https://www.dpuc.state.ct.us/DEEPEnergy.nsf/c6c6d525f7cdd1168525797d0047c5bf/7ee67771749df2cd85258e500046ce49?OpenDocume
nt
8 Available at:
https://www.dpuc.state.ct.us/dockcurr.nsf/8e6fc37a54110e3e852576190052b64d/fbef8709a95dd5ce85258e440065da59/$FILE/Att%202b
%20NRES%20Year%206%20Program%20Manual%20Proposed%20Redlines.pdf
4
small zero emission category have been exhausted, any leftover MW in the small
zero emission category will solely roll over to the small zero emission category for
the following year.”
Notwithstanding the previous comment, Verogy suggests that any unallocated Small
category budgetary or capacity allocation at the conclusion of the Year 6 Fall
procurement be reallocated to the next most cost-efficient unawarded project(s) that
can be awarded at full as-bid capacity until the entire Small program budget / capacity
allocation is granted to eligible projects. The Small category has the highest price cap
of the NRES program, so re-allocating budget or capacity from this category to either
the Medium or Large category would be assigning program resources to a more costeffective project while simultaneously enabling additional NRES Tariff awards to
eligible projects. For these reasons, Veorgy asserts that allowing Small category
budgetary or capacity allocation to be re-allocated to larger, more cost-efficient
projects would achieve Program Objectives 1, 2 and 3.
c) SAM Customer Host Site Control
i. Comment: Section 4.4.4 of the NRES Year 6 Program Manual proposed by the EDCs9
states, in part:
“For Projects where the SAM Customer Host is not the Owner of the Project Site, the
Owner of the Project Site must attest that the SAM Customer Host: 1) has control of
the Project Site or an unconditional right to obtain site control, 2) has authorized the
Bidder, if different than the Customer Host, to submit a NRES BidBid for the Project
Site, and 3) is authorized to participate in the NRES Program for the entire 20-year
Tariff Term should the Bid be selected.”
Verogy asserts that the requirement for a SAM Customer Host to have direct control,
if not outright ownership, of a Project Site frustrates the intent of Public Act No. 23102 Section 25 subsection (g) and places undue burden on property owners, SAM
9
Available at:
https://www.dpuc.state.ct.us/dockcurr.nsf/8e6fc37a54110e3e852576190052b64d/fbef8709a95dd5ce85258e440065da59/$FIL
E/Att%202b%20NRES%20Year%206%20Program%20Manual%20Proposed%20Redlines.pdf
5
customers, and project developers seeking to allocate benefits to SAM customers from
an NRES project sited on a parcel not owned by the SAM customer. Verogy believes
that the intent of Public Act No. 23-102 Section 25 subsection (g) was to allow greater
flexibility for siting SAM projects by removing the SAM site ownership requirement
present in NRES Years 1 and 2 and in a broader scope removing SAM site control
requirements altogether to enable optimal siting of projects that would deliver the
greatest volume of program benefits to SAM customers. Notably, Public Act No. 23102 Section 25 subsection (g) does not use the language “ownership” or “owned” but
the more general term “customer’s own premises”. Rather than maximizing program
flexibility, the EDCs imposed unnecessary site control requirements between the SAM
customer and Owner of the Project Site that adds complexity to the Program and bid
submission process.
Removing these site control requirements between the SAM Customer Host and the
Owner of the Project Site would directly accomplish Program Objectives 1, 2 and 3.
3. RECOMMENDED APPLICATION FEE
i. Comment: Verogy asserts that the non-refundable NRES Bid Fee should remain at its
current level of $450 and that the EDC recommended bid fee of $70010 is unduly
punitive to NRES program participants, especially small customers or developers. The
EDC recommended non-refundable bid fee of $700 represents a 55% increase in a
single year, far outpacing any real-world cost of labor increases, and would likely
depress participation in the Small category, which has already seen a marked reduction
in participation levels compared to previous years. Increasing the Bid Fee by 55% in a
single year runs contrary to Program Objectives 1 and 5.
Notably, as more time elapses since the beginning of the NRES program the EDCs
may experience a sort of windfall from forfeited Performance Assurance deposits of
early NRES Tariffs. Verogy suggests that if needed, these forfeited Performance
10
26-08-03 Joint Order No 19:
https://www.dpuc.state.ct.us/dockcurr.nsf/8e6fc37a54110e3e852576190052b64d/29bd86e4f90540e085258e440057974b/$FI
LE/26-08-03%20Order%2019.pdf
6
Assurance deposits could be used to offset program administration costs rather than
dramatically increasing non-refundable Bid Fees.
4. BUDGET ALLOCATION
i. Comment: Verogy supports the re-balancing of NRES program budget to align with
the 80% / 20% MW split between Eversource and United Illuminating. Verogy
suggests that re-balancing the budget to align with the well-known MW split would
simplify program design and help to achieve Program Objective 4.
Verogy thanks PURA for the opportunity to provide written comments for consideration in NRES Year 6
development.
Respectfully submitted,
Verogy Holdings, LLC d/b/a Verogy
124 LaSalle Road, 2nd Floor
West Hartford, CT 06107