Compliance Filing, Order No. ComplianceFiled by DEEP
Compliance Order No.15
- Type of filing
- Compliance filing (Compliance Filing, Order No. Compliance)
- Date filed
- September 1, 2026
- Filed by
- DEEP
- Files
- 2
As listed on the current system: Compliance Filings, 09/01/2026 [26-08-04] Order No.Compliance Order No.15 / DEEP / Compliance Order No.15
Files
09012026_DEEP Compliance Order No 15 SCEF Year 8 Dkt. 26-08-04.pdf
PDF · 678 KB · 6 pagesText searchable
Download 09012026_DEEP Compliance Order No 15 SCEF Year 8 Dkt. 26-08-04.pdfRead the text of 09012026_DEEP Compliance Order No 15 SCEF Year 8 Dkt. 26-08-04.pdf
09012026_Attachment 1 - SCEF Year 8 DEEP Appendix B redlines Dkt. 26-08-04.pdf
PDF · 347 KB · 26 pagesText searchable
Download 09012026_Attachment 1 - SCEF Year 8 DEEP Appendix B redlines Dkt. 26-08-04.pdfRead the text of 09012026_Attachment 1 - SCEF Year 8 DEEP Appendix B redlines Dkt. 26-08-04.pdf
Text of 09012026_DEEP Compliance Order No 15 SCEF Year 8 Dkt. 26-08-04.pdf
Extracted from the file · 13,141 characters
ENERGY & TECHNOLOGY POLICY
September 1, 2026
Mr. Jeffrey R. Gaudiosi, Esq.
Executive Secretary
Public Utilities Regulatory Authority
10 Franklin Square
New Britain, CT 06051
Re: Docket No. 26-08-04, Annual Review of Statewide Shared Clean Energy Facility
Program Requirements – Year 8
Dear Mr. Gaudiosi:
The Bureau of Energy and Technology Policy (BETP) of the Department of Energy and
Environmental Protection (DEEP) hereby submits the recommended Procurement Price Cap, Bid
Preferences, and Appendix B for the eighth program year (Year 8) of the Statewide Shared Clean
Energy Facility (SCEF) program. Pursuant to Order No. 15, DEEP is required to submit its
recommended Procurement Price Cap, Bid Preferences, and changes to Appendix B to the Public
Utilities Regulatory Authority (PURA) by September 1, 2026. 1
Public Process
On June 24, 2026, DEEP issued a Notice of Public Meeting and Request for Written Comments
(Notice), which included DEEP’s draft recommendations to PURA for Year 8 of the SCEF
program. 2 DEEP held a public meeting virtually on Zoom on July 8, 2026, to present the draft
recommendations and receive feedback from stakeholders. Twenty-nine people registered for the
meeting.
DEEP accepted written comments on the draft recommendations until July 24, 2026. Three
stakeholders submitted written comments:
•
Council on Environmental Quality 3
PURA, Final Decision, Docket No. 25-08-04, Annual Review of Statewide Shared Clean Energy Facility Program
Requirements – Year 7 (Dec. 17, 2025).
2
DEEP, Notice of Public Meeting and Opportunity for Written Comments, Public Act 18-50, Section 7(a)(1)(C),
Statewide Shared Clean Energy Facility Program (Jun. 24, 2026).
3
Council on Environmental Quality, Comments, Public Act 18-50, Section (a)(1)(C), Statewide Shared Clean
Energy Facility Program (Jul. 24, 2026). Available at:
https://www.dpuc.state.ct.us/DEEPEnergy.nsf/c6c6d525f7cdd1168525797d0047c5bf/044a1924da624da685258e500
0472f62/$FILE/CommentsSCEF%20Year%208%20-%20CT%20Council%20on%20Environmental%20Quality%20(CEQ).pdf
1
•
•
Save the Sound 4
Verogy 5
Procurement Price Cap
Conn. Gen. Stat. § 16-244z(a)(5) prescribes a price cap as the highest selected bid price from the
previous SCEF procurement, unless PURA determines there are changed circumstances. 6 DEEP
historically recommended price caps that matched the highest selected bid price from the previous
year until SCEF Year 7, when DEEP recommended that PURA consider the changed
circumstances caused by the loss of the investment tax credit. 7 For the Year 8 SCEF procurement,
DEEP recommends that the price cap be the highest selected bid price from the previous SCEF
procurement, which would mean a price cap of $182.93/MWh. 8
DEEP asserts that this recommended price cap accommodates the continued circumstances
regarding the federal investment tax credit while maintaining a competitive and cost-effective
program, allowing the EDCs to maximize the capacity that can be deployed within the annual
SCEF budget. Written Comments from Save the Sound affirm that “the results of the Year 7
solicitation seem to suggest that the recommended price cap is sufficient to encourage robust
program participation.” 9 Further, this recommended price cap is higher than the electric
distribution companies’ (EDCs) proposed buy-all price cap for the Large Zero Emission category
in the Year 6 Non-Residential Renewable Energy Solutions (NRES) program, which is only
$179/MWh. 10
Save the Sound, Comments, Public Act 18-50, Section (a)(1)(C), Statewide Shared Clean Energy Facility Program
(Jul. 24, 2026). Available at:
https://www.dpuc.state.ct.us/DEEPEnergy.nsf/c6c6d525f7cdd1168525797d0047c5bf/05790d7d08dce01c85258e410
044b83e/$FILE/Save%20the%20Sound%20-%20Comments%20on%20SCEF%20Year%208%20Recommendations
%207.24.26.pdf
5
Verogy, Comments, Public Act 18-50, Section (a)(1)(C), Statewide Shared Clean Energy Facility Program (Jul.
24, 2026). Available at:
https://www.dpuc.state.ct.us/DEEPEnergy.nsf/c6c6d525f7cdd1168525797d0047c5bf/7ee67771749df2cd85258e500
046ce49/$FILE/Verogy%20SCEF%20Year%208%20Written%20Comments%202026.07.24_Submitted.pdf
6
Specifically, Conn. Gen. Stat. Sec. 16-244z (a)(5) states, in pertinent part, “The maximum selected purchase price
of energy and renewable energy certificates on a cents-per-kilowatt-hour basis in any given solicitation shall not
exceed such maximum selected purchase price for the same resources in the prior year's solicitation, unless the
authority makes a determination that there are changed circumstances in any given year....”
7
DEEP, Compliance Order No. 15, Docket No. 25-08-04, Annual Review of Statewide Shared Clean Energy
Facility Program Requirements – Year 7 (Sep. 2, 2025).
8
DEEP notes that United Illuminating is currently accepting bids for Year 7 Round 2. However, given the highest
selected bid price in Year 7 Round 1 was only $0.01/MWh lower than the Year 7 Price Cap, DEEP’s
recommendation will not change as a result of any Year 7 Round 2 selections.
United Illuminating, Motion No. 7, Order Nos. 9 and 10 Attachment B, Docket No. 25-08-04, Annual Review of
Statewide Shared Clean Energy Facility Program Requirements – Year 7 (Jun. 18, 2026).
9
Save the Sound, Comments, Public Act 18-50, Section (a)(1)(C), Statewide Shared Clean Energy Facility Program
(Jul. 24, 2026).
10
Eversource Energy and United Illuminating, Motion No. 3, Joint Motion for Review and Approval of Order No. 3,
Docket No. 26-08-03 Annual Non-Residential Renewable Energy Solutions Program Review – Year 6, (Jul. 20,
2026).
4
Though it is not DEEP’s recommendation at this time, PURA may want to further evaluate whether
there are changed circumstances as part of their public process and prior to the Final Decision in
this Docket as the impacts of President Trump’s Section 232 tariff on polysilicon imports to the
United States are better understood. 11 The impacts of the tariff may have varying effects on SCEF
project prices, depending on where developers source their materials. In their written comments,
submitted before the details of the tariff were finalized, Verogy approximated that the tariff could
increase “build cost” by five to seven percent. 12
Verogy further expressed concern over “unilaterally imposed” interconnection cost increases,
stating that the EDCs have required Verogy to:
(1) pave any access roads that serve a SCEF (as opposed to constructing a gravel access
road); (2) required redundant disconnect switches, poles and other equipment beyond the
minimum requirements to serve a SCEF and (3) required that otherwise serviceable
interconnection gear be relocated to an area more convenient for the EDC. These
requirements, and others, have been imposed by EDCs as a condition to execute an
[Interconnection Service Agreement], yet these requirements are not spelled out in EDC
technical interconnection standards or other material. 13
DEEP believes further investigation into these claims is warranted before relying on them as
“changed circumstances” to warrant a higher price cap but wanted to bring the concern to PURA’s
attention.
Bid Preferences
Brownfields and Landfills
DEEP recommends maintaining the 20% bid preference for projects sited on landfills and on
brownfields.
Save the Sound and the Council on Environmental Quality (CEQ) both expressed concern with
the small number of bids received in Year 7 on landfills and brownfields. CEQ suggested
increasing the cap, while Save the Sound suggests there may be other factors at play and
suggests getting further input from the solar industry. 14 15 DEEP received one written comment
The President of the United States of America, Adjusting Imports of Polysilicon and its Derivatives Into the
United States (Aug. 6, 2026). Available At: https://www.whitehouse.gov/presidential-actions/2026/08/adjustingimports-of-polysilicon-and-its-derivatives-into-the-united-states/
12
Verogy, Comments, Public Act 18-50, Section (a)(1)(C), Statewide Shared Clean Energy Facility Program (Jul.
24, 2026).
13
Verogy, Comments, Public Act 18-50, Section (a)(1)(C), Statewide Shared Clean Energy Facility Program (Jul.
24, 2026).
14
Save the Sound, Comments, Public Act 18-50, Section (a)(1)(C), Statewide Shared Clean Energy Facility
Program (Jul. 24, 2026).
15
Council on Environmental Quality, Comments, Public Act 18-50, Section (a)(1)(C), Statewide Shared Clean
Energy Facility Program (Jul. 24, 2026).
11
from the solar industry, in which Verogy states that the 20% bid preference is sufficient but that
these projects should be allowed to bid above the price cap like solar canopy projects. DEEP
does not recommend allowing brownfield and landfill projects to bid above the price cap as it
will reduce the cost effectiveness of the SCEF program.
Solar Canopies
DEEP recommends maintaining the 40% bid preference for solar canopy projects. In Years 6 and
7, eight total solar canopy projects bid into the SCEF program, six of which were selected with the
40% bid preference. 16 17
Both Verogy and Save the Sound commented that the 40% bid preference is sufficient to support
some solar canopy projects as currently structured. 18 19 In order to balance the environmental
benefits of solar canopies with the ratepayer impact of the SCEF program, and given the relative
success of the 40% bid preference, DEEP does not recommend increasing the bid preference for
Year 8.
Other Bid Preference Considerations
In DEEP’s June 24, 2026 Notice, DEEP contemplated a bid preference for projects that provide
additional distribution system benefits. DEEP thanks those who submitted public comments on
this concept but does not recommend any additional bid preferences for SCEF Year 8.
Appendix B Submittal
In addition to changes to incorporate the recommendations above, DEEP proposes minimal
changes to the Year 8 Appendix B submittal, a redlined version of which is included as Attachment
1. DEEP does not consider any of these changes to place any further burden on Bidders.
Most of the changes to Appendix B simply clarify language, like specifying that when Bidders
provide the census tract number they must provide the full 11-digit number and switching Public
Act references to the Connecticut General Statute section numbers where they were codified. Of
particular note, DEEP confirmed that Appendix B submittals are due to DEEP by the due date and
time established by the EDCs in the SCEF Request for Proposals for Year 8 and that to ensure
bids are considered by DEEP as timely filed, the bid must be received by DEEP prior to the
expiration of the bid deadline.
Eversource, Order No. 11 Compliance Filing, Attachment 1, Docket No. 25-08-04, Annual Review of Statewide
Shared Clean Energy Facility Program Requirements – Year 7 (Jun. 16, 2026).
17
United Illuminating, Order No. 11 Compliance Filing, Attachment 1, Docket No. 25-08-04, Annual Review of
Statewide Shared Clean Energy Facility Program Requirements – Year 7 (Aug. 3, 2026).
18
Verogy, Comments, Public Act 18-50, Section (a)(1)(C), Statewide Shared Clean Energy Facility Program (Jul.
24, 2026).
19
Save the Sound, Comments, Public Act 18-50, Section (a)(1)(C), Statewide Shared Clean Energy Facility
Program (Jul. 24, 2026).
16
DEEP reworded question B5.7 to make it narrower and clearer for Bidders, specifically asking
about ridgelines and ridgeline setback areas within one mile of the Project Site and interconnection
route, instead of simply asking whether there were any ridgelines or ridgeline setback areas “in
proximity,” which was overly broad.
DEEP added section B7 regarding the Freedom of Information Act (FOIA) to ask Bidders to state
in their Appendix B response whether they are claiming any FOIA exemptions and to confirm they
have reviewed and understand the FOIA information in Appendix B. DEEP previously asked for
this information to be provided in the body of the Appendix B submission email sent to DEEP but
was often following up with Bidders to clarify. This section is not asking Bidders to do anything
additional to what has been required in previous SCEF years, it simply streamlines the
administrative process for both DEEP and the Bidders.
Finally, DEEP revised the Veracity of Statements Affidavit, Attachment 3 to Appendix B. The
new version of the affidavit allows DEEP to verify that the affiant is referring to the individual bid,
rather than a batch of bids from the same developer. However, it does not place any additional
burden on the bidder or ask them to attest to anything new.
Program Manual
DEEP does not propose any changes to the Year 8 Program Manual.
Thank you for your time and consideration.
Sincerely,
DEPARTMENT OF ENERGY AND
ENVIRONMENTAL PROTECTION
Bureau of Energy and Technology Policy
/s/ Victoria Hackett
Victoria Hackett
Bureau Chief, Bureau of Energy &
Technology Policy
10 Franklin Square
New Britain, CT 0605[phone removed]
[email removed]
CERTIFICATE OF SERVICE
I hereby certify that a copy of the foregoing has been furnished to the service list in compliance
with Conn. Agencies Regs. § 16-1-15.
By: /s/ Suzannah K. Nigro
Suzannah K. Nigro
Commissioner of the Superior Court
Text of 09012026_Attachment 1 - SCEF Year 8 DEEP Appendix B redlines Dkt. 26-08-04.pdf
Extracted from the file · 35,811 characters
SHARED CLEAN ENERGY FACILITY (SCEF) PROGRAM
YEAR 87
APPENDIX B: SUBMITTAL TO DEEP
INSTRUCTIONS
In addition to any complete Bid submitted to the electric distribution companies (EDCs) in
response to the Request for Proposals (RFP) for Year 87 of the Shared Clean Energy Facility
(SCEF) Program, Bidders must submit a complete Appendix B submission to the Department of
Energy and Environmental Protection (DEEP). Bidders must provide written responses to all
questions in sections B1-B67, below, and provide the necessary affidavits and forms. Bidders must
use the affidavits and forms provided as Attachments herein. Complete Appendix B submissions
must include:
I. Responses to all questions in sections B1-B76, below, with all supporting information
requested in both the main question and any question subparts. Each question must be
answered in its entirety. If supplemental material is required in the form of an appendix,
exhibit, table, map, or other documents, Bidders must provide each supplemental material
directly below the applicable question or provide a link directly to that supplemental
material. If any section or question is not applicable, this should be clearly stated with a
full explanation as to why that section or question is not applicable. Do not skip any
section or question.
II. Attachment 1: An affidavit attesting to the Bidder’s control of the Project Site by the Bidder
(Affidavit #1)
III. Attachment 2: An affidavit attesting to the Bidder’s control of the Project Site by the owner
of the Project Site (Affidavit #2) (required only if the Bidder is not the owner of the Project
Site)
IV. Attachment 3: An affidavit attesting the veracity of statements made to DEEP (Affidavit
#3)1
1 If there is a Subscriber Organization (as defined in the Program Manual) that is different from the Bidder and the
Subscriber Organization provides responses to specific Appendix B questions on behalf of the Bidder, this must be
specifically noted in the response to the particular question(s) AND the Subscriber Organization must also provide
V. Attachment 4: An Applicant Compliance Information form to be completed by the Bidder,
who is considered the applicant for purposes of Attachment 4.
Bidders must submit their complete Appendix B submission to DEEP at
[email removed] on or before the Bid due date and time established by the
EDCs in the SCEF RFP for Year 87. To ensure that bids are considered by DEEP as timely
filed, the bid must be received by DEEP prior to the expiration of the bid deadline. DEEP
reserves the right to seek clarifying or additional information and documents at any point in
the evaluation process at its sole discretion as described in Section 3.4 of the SCEF Program
Manual approved for Year 87 of the SCEF Program in Docket No. 265-08-04.
Further, by submitting an Appendix B response to DEEP, Bidder consents to DEEP sharing
such responses with the Department of Agriculture as necessary to assist DEEP in its
evaluation of Appendix B responses.
its own separate Attachment 3- Affidavit of Veracity of Statements in addition to one executed by the Bidder. Each
Attachment 3 Affidavit must further specify the specific portions of Appendix B that the Bidder or the Subscriber
Organization are attesting to, and all portions of Appendix B must be included and accounted for in one or the other
Affidavit.
FREEDOM OF INFORMATION ACT
All information submitted to DEEP may be subject to disclosure under the Connecticut Freedom
of Information Act (FOIA). All information submitted to DEEP will be publicly posted on its
Energy Filings page, unless a Bidder claims confidentiality over portions of information submitted
in response to Appendix B. When a Bidder submits confidential information to DEEP, the Bidder
acknowledges that the FOIA governs the public’s accessibility to that information.
If a Bidder believes portions of information submitted in response to Appendix B are exempt from
FOIA disclosure, the Bidder must submit:
One complete, redacted response to Appendix B for public posting, which must be clearly
labeled PUBLIC,
AND
One complete, unredacted response to Appendix B for DEEP’s internal review, which must
be clearly labeled CONFIDENTIAL.
The Bidder must also specifically identify which FOIA exemption may be applicable to the
specific information claimed confidential. Examples of FOIA exemptions include, but are not
limited to:
Trade secrets, § 1‐210(b)(5)(A) of the General Statutes of Connecticut (C.G.S.);
Commercial and Financial information given in confidence, not required by statute, C.G.S.
§ 1‐ 210(b)(5)(B);
Responses to any request for proposals or bid solicitation issued by a public agency or any
record or file made by a public agency in connection with the contract award process, until
such contract is executed or negotiations for the award of such contract have ended,
whichever occurs earlier provided the chief executive officer of such public agency
certifies that the public interest in the disclosure of such responses, record or file is
outweighed by the public interest in the confidentiality of such responses, record or file,
C.G.S. § 1‐210(b)(24); and
Public records exempt under federal law or state statute, C.G.S. § 1‐210(a).
In addition, Bidders must submit a detailed explanation of why the relevant FOIA
exemption is applicable to the specific information requested to be redacted. A unique
explanation is required for each response to a question in which a Bidder wishes to redact
information; a blanket justification is prohibited. Failure to provide such explanation will
lead to a disqualification of the project for failure to comply with Appendix B. DEEP will
not redact proposals submitted on behalf of Bidders. Only legitimate non‐public proprietary or
sensitive information may be considered confidential. Bidders may not submit a response to
Appendix B that is entirely redacted. If the redaction is challenged in any forum, it is the
responsibility of the Bidder to defend the confidentiality of the information.
If a Bidder is not claiming any FOIA exemptions and is not providing a redacted,
confidential version of their responses to Appendix B, please confirm in your email
submission of Appendix B that you understand your Appendix B response will be made
public when you send it to DEEP.
DEFINITIONS
“Brownfield” means a site that is either: (1) an address that is included on the Connecticut
Brownfields Inventory maintained by DEEP and an attestation that such site has not achieved
regulatory closure in the form of either a verification report from a licensed environmental
professional or from DEEP; or (2) an address with a Phase 2 Environmental Site Assessment from
a licensed environmental professional identifying that the site is contaminated with pollutants,
unless such pollutants are present solely because soil at such address has been historically
intermixed with coal ash, wood ash, coal fragments, coal slag, coal clinkers, asphalt paving
fragments, or any combination thereof. For both (1) and (2), the Bidder must demonstrate, to
DEEP’s sole satisfaction, the site is either abandoned or underutilized because of such
contamination.
“Core Forest” means unfragmented forested land of at least two hundred and fifty (250) acres
that is three hundred (300) feet or greater from the boundary between forested land and nonforested land.
“Environmental Justice Community” means the same as C.G.S. 22a-20a: “(A) a United States
census block group, as determined in accordance with the most recent United States census, for
which thirty per cent or more of the population consists of low income persons who are not
institutionalized and have an income below two hundred per cent of the federal poverty level, or
(B) a distressed municipality, as defined in subsection (b) of section 32-9p.” DEEP maintains a
publicly accessible map of Environmental Justice Communities.
“Generation Footprint” means the land area occupied by the generation unit(s). For solar
projects the “Generation Footprint” shall mean the land area occupied by the solar panels and the
associated inter-row spacing.
“Hybrid Project” shall mean Projects that include those which are split between rooftops and
ground-mounted systems, including carports and solar canopies.
“Prime Farmland” shall have the same meaning as in 7 CFR 657, as amended.
“Landfill” means any property that is listed on the Closed Landfills list, though this list is not intended to
be exhaustive or an acknowledgement of ideal properties for renewable energy development. Only the
closed, capped portion of the property is considered a “Landfill” for bid preference purposes.
“Project Site” means the Generation Footprint and any other acreage where activity and
discharges occur that are associated with construction of the generation unit(s) and any associated
structures, including, but not limited to, perimeter fencing, or where preparation for construction,
including, but not limited to, clearing, grubbing, pile driving, soil disturbance, soil compaction by
construction equipment, staging and stockpiling, cleaning and washout, grading, excavation, and
dewatering occurs.
“Solar Canopy” “Solar Canopies” or “Solar Carport” means a solar generation Project where
the alternating current (AC) Nameplate Capacity of a Project used for generating power is installed
above a permeable and/or nonpermeable existing or new parking/driving area, pedestrian
walkway, courtyard, canal, or other utilized surface that requires shade, which is installed in a
manner that maintains the function of the area beneath the structure and continues to be used or
available for use for such purposes for the term of Program participation.
APPENDIX B QUESTIONS
B1. PROJECT OVERVIEW
B1.1. Provide an overview of the proposed project, including but not limited to:
i.
Resource type
ii.
Project size in kW (AC)
iii.
Project size in kW (DC)
iv.
Location of Project Site, specifically:
a. Municipality
b. Eleven digit cCensus tract number
c. Approximate street address, including the zip code
v.
State whether the proposed project is located in an Environmental Justice
Community
vi.
State whether the proposed project site is located, in whole or in part, on Prime
Farmland
vii.
Estimated average annual output (kWh/year)
viii.
Bid price ($/kWh)
B1.2. Identify whether the proposal is claiming a qualitative bid preference, and if so,
which qualitative bid preference. If claiming a qualitative bid preference, provide
documentation and evidence supporting your claim for the qualitative bid preference.
B1.3 Confirm the bid complies with Conn. Gen. Stat, Sec. 16-244z (a)(2)Public Act 25173’s requirement that the SCEF projects “emits no pollutants.”
B2. FINANCIAL EXPERIENCE
B2.1. Provide the following cost estimates for developing and operating the project for the
duration of the program term:
i.
Estimated equipment costs;
ii.
Estimated labor and other installation costs;
iii.
Estimated land and/or Project Site development costs. If the Project Site is
located on a brownfield, landfill, or the Generation Footprint is on a canopy,
provide an estimated premium paid, broken out from the estimated standard
development costs, for purchasing and/or developing on the landfill,
brownfield, or canopy, including but not limited to compliance costs;
iv.
Estimated interconnection costs;
v.
Estimated financing costs;
vi.
Estimated permitting costs;
vii.
Estimated operations and maintenance costs for the duration of the commercial
operation of the facility;
viii.
Estimated cost of any decommissioning, including but not limited to a
decommissioning bond, if required by Conn. Gen. Stat. Sec. 16-50kPublic Act
23-163 or other legislation; and
ix.
Other estimated expenses associated with development and operation of the
project not otherwise reflected above, including an explanation of such other
costs.
B3. PROJECT SITE
B3.1. Provide a single site plan with the following all on one map:
i.
Scale
ii.
North arrow
iii.
Parcel(s) boundary
iv.
Legend
v.
Generation footprint overlay
vi.
Road names
vii.
Anticipated interconnection route
viii.
USGS Topo map with project site outline
ix.
Acreage of the generation footprint
x.
Show watercourse and wetlands delineation, or if they have not been field
delineated, show wetland hydric soils layer from Natural Resources
Conservation Service GIS data or local GIS data for general locations.
xi.
Identify any Prime Farmland soils.
B3.2. To demonstrate the requisite proof of site control for the Project Site, complete
Affidavit #1 (Attachment 1), and, as applicable, Affidavit #2 (Attachment 2).
B3.3. For projects under 1 MW, attest that the Project Site and interconnection route are or
will be, through a variance or other permit process, acceptable uses for the zone(s) in which
they are located.
B4. PROJECT THRESHOLD REQUIREMENTS
The information requested is organized according to the classification of the Project Site or
resource type. If any section or question is not applicable, this should be clearly stated with a full
explanation as to why it is not applicable.
B4.1. Brownfield Development
i.
Attest to at least one of the following and provide any requested information:
a. That the Project Site’s address is included on the Connecticut
Brownfields Inventory maintained by DEEP and the address of the
Project Site has not achieved regulatory closure (i.e., it has not received
a verification report from a licensed environmental professional or from
DEEP); OR
b. That the Project Site’s address has a Phase 2 Environmental Site
Assessment from a licensed environmental professional identifying that
the site is contaminated with pollutants, unless such pollutants are
present solely because soil at such address has been historically
intermixed with coal ash, wood ash, coal fragments, coal slag, coal
clinkers, asphalt paving fragments, or any combination thereof.
ii.
Demonstrate, to DEEP’s sole satisfaction, the site is either abandoned or
underutilized because of such contamination.
iii.
Indicate whether 100% of the Generation Footprint is on the Brownfield.
iv.
If the project is not wholly located on the Brownfield, indicate the percentage
of the project’s Generation Footprint that is located on the Brownfield and
therefore eligible for the Brownfield bid preference.
B4.2. Landfill Development
Indicate how much of the Generation Footprint is located on a Landfill. For a project built
on a Landfill to qualify for the bid preference, the Generation Footprint must be wholly
located on the Landfill. However, if the size of the Landfill cannot accommodate the entire
Generation Footprint, then the project can still be eligible to receive the qualitative
preference, provided at least 75% of the total Generation Footprint is within the Landfill
and the Landfill land that is legally and technically available for development is utilized.
B4.3. Sand and Gravel Pits Development
i. Indicate the percentage of the total Project Site that is on the sand and gravel
pit.
B4.34. For a project located on Prime Farmland, attest that the Bidder understands that
projects shall be required to follow any rules developed by the Connecticut Department of
Agriculture and/or the Connecticut Siting Council for clean energy projects sited on Prime
Farmland as a condition of receiving payment, as stated on these webpages:
Department
of
Agriculture
resources
are
available
via
this
website:
https://portal.ct.gov/doag/adarc/programs/solar-and-farming-overview/shared-clean-energyfacility
Connecticut Siting Council resources available via this website: https://portal.ct.gov/csc
B4.45. Solar Canopy Development
i.
Indicate whether 100% of the Generation Footprint is included on the Solar
Canopy.
ii.
If the Project is a Hybrid Solar Canopy Project, indicate the percentage of the
project’s capacity (kW AC) that is located on the Solar Canopy and therefore
eligible for the Solar Canopy Bid Preference.
B5. PERMIT ACQUISITION
B5.1. Bidder acknowledges that the project may require permits including but not limited
to the Connecticut Siting Council, Department of Energy and Environmental Protection’s
General or Individual Permit for the Discharge of Stormwater and Dewatering Wastewaters
from Construction Activities (Stormwater General Permit), and environmental surveys and
reports required to support the applications. Local Building and Electrical permits may be
required. Solar arrays on a closed Landfill may require a post-closure use change approval
and a disruption authorization through the Solid Waste Permitting Program in the Waste
Engineering and Enforcement Division of DEEP. Please use this link: Permit Information
for Solar Projects, or reach out to the Client Concierge Services team at
[email removed] with any questions or to schedule a pre-application meeting.
B5.2. Identify any existing, preliminary, or pending claims or litigation, or matters before
any federal agency or any state legislature or regulatory agency that might affect the
feasibility of the proposed project or the ability to obtain or retain the required permits for
the proposed project.
B5.3. Bidder acknowledges that it is familiar with the Siting Council’s process and decision
timeframe. Bidder further acknowledges that it has reviewed DEEP’s Stormwater General
Permit and understands the requirements contained therein and the timeframe for approval.
B5.4. Bidder understands that wetland buffers of 100 feet are preferable to the Connecticut
Siting Council and for the Stormwater General Permit. If unable to provide this buffer,
bidder understands that the DEEP and/ or the Connecticut Siting Council may ask for
additional information as to the chosen layout of the project and how other alternatives
were addressed and dismissed.
B5.5. For a project sited on Prime Farmland, the Bidder acknowledges that Conn. Gen.
Stat. Sec. 16-50kPublic Act 23-163 requires a decommissioning bond as part of the
Connecticut Siting Council process.
B5.6. Confirm that the Project Site is not sited on Core Forest, in whole or in part, as
defined in this procurement.
B5.7. Indicate on a map any ridgelines or ridgeline setback areas as defined in Conn. Gen.
Stat. Sec. 8-1aa that occur within 1 mile of the Project Site and/or the interconnection route.
If no ridgeline or ridgeline setback area occurs within 1 mile of the project site and/or
interconnection route, please indicate this in your response.Indicate the proximity of the
Project Site and interconnection route to ridgelines and ridgeline setback areas as defined
in C.G.S. § 8-1aa. If this is not applicable to the location of the project, please state the
reason.
B5.8. Include a summary of environmental compliance history for the Bidder, including
any general and limited partners, officers, directors, managers, members, shareholders, and
subsidiaries, using the “Applicant Compliance Information form,” included herein as
Attachment 4.
B5.9. Bidder confirms that they have checked or will check prior to commencing
construction for conservation, recreation, or open space restrictions that would prohibit
development on the Project Site.
B6. COMMUNITY IMPACT AND ENGAGEMENT
B6.1. Provide documentation of community outreach and engagement regarding the Bid
conducted to date. A passing response must include documentation from at least two of the
following categories:
i.
Copies of any agreements with local community organizations and other
constituencies (including but not limited to Neighborhood Revitalization
Zones, environmental non-profits, social services non-profits, or other
organizations that serve the local community) that may be impacted by the
proposed project;
ii.
Emails, letters, and/or other communications with or directed to local municipal
officials;
iii.
Emails, letters, and/or other communications with or directed to municipality
residents and/or community organizations (including but not limited to
Neighborhood Revitalization Zones, environmental non-profits, social services
non-profits, or other organizations that serve the local community);
iv.
Time, date, and materials from any in-person or virtual meeting held with local
officials, property owners, abutters, community organizations, and/or other
town residents to educate them about the proposed project; and/or
v.
Other documentation or narrative description that substantiates outreach efforts
to-date with the host community (including property owners, abutters,
Neighborhood Revitalization Zones, environmental non-profits, social services
non-profits, or other organizations that serve the local community and/or other
town residents).
B6.2. The Bidder acknowledges the requirements of Conn. Gen. Stat. Sec. 31-53d Public
Act 21-43 f for projects two MWs or greater.
i.
Describe how the Bidder will take appropriate actions to ensure a workforce
development program is established if the Bid is selected.
ii.
If the project is equal to five MWs, describe how the Bidder will take all
reasonable actions to ensure that a community benefits agreement is entered
into with appropriate community organizations representing the residents of the
community in which the project will be located. Include the names of
community organizations the Bidder has already identified, any communication
with the community organizations regarding the Bid to-date, and any draft
community benefits agreement that exists.
B6.3. Describe how the Bidder is addressing and advancing issues of Diversity, Equity,
and Inclusion (DEI) with its mission, professional development, staffing, and/or
Connecticut based recruiting efforts. If the Bidder has a social impact statement, submit a
copy with this Appendix B response.
B7. FREEDOM OF INFORMATION ACT
B7.1. Is the Bidder claiming FOIA exemptions in this Appendix B response?
B7.2. The Bidder confirms they have reviewed and understand the information in
Appendix B related to FOIA exemptions and, if exemptions are being claimed, that the
Appendix B requirements have been met.
Attachment 1
Affidavit #1: Bidder’s Affidavit of Site Control under the SCEF Program Manual of the Shared
Clean Energy Facility Program
NOTE: Affidavit #1 must be completed and submitted by all Bidders. If the Bidder and Owner of
the Project Site are the same individual or entity, only Affidavit #1 is required. If the Bidder and
the Owner of the Project Site are not the same individual or entity, the Bidder must also submit
Affidavit #2, as completed by the Owner of the Project Site.
For the purposes of this affidavit, “Bidder” is defined as the individual or business submitting a proposal
(“Bid”) to be considered for selection in the annual Shared Clean Energy Facility (“SCEF”) Program
solicitation and “Owner of the Project Site” is defined as the legal owner of the SCEF Project Site.
As a duly authorized representative of the Bidder of the SCEF project, I hereby attest that the Bidder has
control of the Project Site, or an unconditional right, granted by the Owner of the Project Site, to acquire
such control to use the site for the SCEF in the SCEF Bid, and any rights-of-way needed for
interconnection, and is authorized to submit the Bid to locate the SCEF on the Owner of the Project Site’s
property. Site control and property rights include all leases, easements, or development rights necessary
to develop and/or operate the SCEF project, including any necessary leases from an applicable government
authority.
The Bidder understands that if it is later determined that the Bidder does not have control of the Project
Site, or an unconditional right, granted by the Owner of the Project Site, to acquire such control prior to
the bid deadline set forth by the relevant Request for Proposal, the Bidder, and the SCEF project, may be
removed from the SCEF Program and forfeit eligibility for future participation pursuant to Section 10 of
the SCEF Program Manual.
The Bidder represents that it understands the requirements for site control as outlined in the SCEF Program
Manual.
As a duly authorized representative of the Bidder, I have reviewed the statements and certifications
provided above and certify that such statements and certifications as applicable to the SCEF Bid are true
and accurate to the best of my knowledge.
The Bidder, or its representative, shall fill out and sign the following:
NOTE: Electronic signatures are not acceptable. The Bidder’s signature, or that of its
representative, is required to be witnessed by a Notary Public and documented as such.2
Please indicate the appropriate site control agreement selection with a checkmark or “x” in
the box to the left:
Signed option agreement to lease or purchase the Property.
Executed lease agreement for the Property.
Executed agreement to purchase the Property.
License or other agreement granting exclusive right to use the Property for purposes of
constructing and operating the distributed generation facility.
N/A - Property Owner will own and operate the distributed generation facility
Project Name:
Address of Pproject Ssite:
Bidder: ____________________________________________________
(Exact legal name of the Bidder, as defined above)
Signature of the Bidder
(or its Representative): ____________________________________________________
Print or Type Name of Bidder
(or its Representative):
authorized)
____________________________________________________
(duly
Title: _____________________________________________________
Date Signed: _______________________________________________
2
Please see Section 3 of the March 30, 2020 CT Executive Order 7Q regarding Remote Notarizations here:
https://portal.ct.gov/-/media/Office-of-the-Governor/Executive-Orders/Lamont-Executive-Orders/Executive-OrderNo-7Q.pdf.
The Notary Public shall fill out and sign the following:
Subscribed and sworn before me, this _____ day of _________________________ 20_____
Notary Public: ________________________________________
Date Commission Eexpires: __________________________________
Printed name of Notary Public: ______________________________
Attachment 2
Affidavit #2: Owner of the Project Site’s Affidavit of Site Control under the SCEF Program
Manual of the Shared Clean Energy Facility Program
NOTE: The completion and submission of Affidavit #2 is only required if the Bidder and Owner of
the Project Site are not the same individual or entity.
For the purposes of this affidavit, “Bidder” is defined as the individual or business submitting a proposal
(“Bid”) to be considered for selection in the annual Shared Clean Energy Facility (“SCEF”) Program
solicitation and “Owner of the Project Site” is defined as the legal owner of the SCEF Project Site.
As a duly authorized representative of the Owner of the Project Site, I hereby attest that the Bidder has
control of the Project Site, and any rights-of-way needed for interconnection, or an unconditional right,
granted by the Owner of the Project Site, to acquire such control. Site control and property rights include
all leases, easements, or development rights necessary to develop and/or operate the SCEF project,
including any necessary leases from an applicable government authority.
The Owner of the Project Site understands that if it is later determined that the Bidder does not have
control of the Project Site, or an unconditional right, granted by the Owner of the Project Site, to acquire
such control prior to the bid deadline set forth by the relevant Request for Proposal, the Bidder, and the
SCEF project, may be removed from the SCEF Program and forfeit eligibility for future participation
pursuant to Section 10 of the SCEF Program Manual.
The Owner of the Project Site represents that it understands the requirements for site control as outlined
in the SCEF Program Manual.
The Owner of the Project Site further attests that the Bidder is authorized by the Owner of the Project Site
to submit the Bid to locate a SCEF project on the Owner of the Project Site’s property.
As a duly authorized representative of the Owner of the Project Site, I have reviewed the statements and
certifications provided above and certify that such statements and certifications as applicable to the Bid
are true and accurate to the best of my knowledge.
The Owner of the Project Site, or its representative, shall fill out and sign the following:
NOTE: Electronic signatures are not acceptable. The Owner of the Project Site’s signature, or that
of its representative, is required to be witnessed by a Notary Public and documented as such.3
Please indicate the appropriate site control agreement selection with a checkmark or “x” in
the box to the left:
Signed option agreement to lease or purchase the Property.
Executed lease agreement for the Property.
Executed agreement to purchase the Property.
License or other agreement granting exclusive right to use the Property for purposes of
constructing and operating the distributed generation facility.
N/A - Property Owner will own and operate the distributed generation facility
Project Name:
Address of Pproject Ssite:____________________________________________________
Owner of the Project Site: ____________________________________________________
(Exact legal name of Owner of the Project Site, as defined above)
Signature of Owner of Project Site
(or its Representative): ____________________________________________________
Print or Type Name of Owner of Project Site
(or its Representative):
authorized)
____________________________________________________
(duly
Title: _____________________________________________________
Date Signed: _______________________________________________
3
Please see Section 3 of the March 30, 2020 CT Executive Order 7Q regarding Remote Notarizations here:
https://portal.ct.gov/-/media/Office-of-the-Governor/Executive-Orders/Lamont-Executive-Orders/Executive-OrderNo-7Q.pdf.
The Notary Public shall fill out and sign the following:
Subscribed and sworn before me, this _____ day of _________________________ 20_____
Notary Public: ________________________________________
Date Commission E expires: __________________________________
Printed name of Notary Public:__________________________
Attachment 3
Affidavit: “Veracity of Statements”
NOTE: Original Attachment 3 must be completed and submitted by all Bidders for each bid.4
Project Name:_____________________________
Address of Project Site:____________________________________
Bidder: ____________________________________________________
I, ___________________, the Affiant, being duly sworn/affirmed according to law, deposes and says
that:
I am the bidder for the above- named project, or a duly authorized representative of the Bidder for the
above-named project, and as such am authorized to and do make this affidavit on behalf of the Bidder.
I attest and certify under penalty of false statement, that all statements and responses submitted in response
to Appendix B of the SCEF Program Manual for this project, as filed concurrently with a project bid filing
in response to a Request for Proposals issued by Eversource or United Illuminating, whichever is
applicable, are true, accurate, and complete and that if any substantial changes occur regarding the
information provided in the submission the Bidder will amend said submission while the project bid filing
is pending, within ten days of any such change.
I attest that the facts as set forth are true and correct to the best of my knowledge, information, and belief
and I expect said Bidder to be able to prove the same at any hearing hereof.
4 For the purposes of this affidavit, “Bidder” is defined as the individual or business submitting a
proposal (“Bid”) to be considered for selection in the annual Shared Clean Energy Facility (“SCEF”)
Program solicitation.
Signature of the Affiant: ____________________________________________________
Print or Type Name of Affiant: ____________________________________________________
Affiant’s Title and Relationship to Bidder: _________________________________________________
Date Signed: _______________________________________________
The Notary Public shall fill out and sign the following:
Subscribed and sworn before me, this _____ day of _________________________ 20_____
Notary Public: ________________________________________
Date Commission Expires: __________________________________
Printed Name of Notary Public: ___________________________________
Attachment 3
AFFIDAVIT: “VERACITY OF STATEMENTS”
That
, Affiant, being duly sworn/affirmed according to law, deposes and says that:
He/she is the
(Office of Affiant) of
(Name of Applicant);
That he/she is authorized to and does make this affidavit for said Applicant;
That
, the Applicant herein, certifies under penalty of false statement that all statements submitted in
its response to Appendix B of the SCEF Program Manual, as filed concurrently with a project bid filing in response
to a Request for Proposals issued by Eversource or United Illuminating, whichever is applicable, are true and
complete and that it will also amend said submission while the project bid filing is pending if any substantial
changes occur regarding the information provided in the submission within ten days of any such change.
That the facts above set forth are true and correct to the best of his/her knowledge, information, and belief and that he/she
expects said Applicant to be able to prove the same at any hearing hereof.
Signature of Affiant
Printed Name of Affiant
Date
Title (relationship to Applicant)
Address of project site:
STATE OF
}
} ss.
COUNTY OF
}
(Town)
The foregoing was subscribed to and sworn to before me this
day of
(day)
,
(month)
by
.
(year)
(Signature of Notary Public or other official)
(Printed Name of Notary Public or other official)
My commission expires
.
Attachment 4
Applicant Compliance Information
Applicant Name:
Mailing Address:
City/Town:
State:
Business Phone:
ext.:
Contact Person:
Phone:
Zip Code:
ext.
*E-mail:
If you answer yes to any of the questions below, you must complete the Table of Enforcement Actions on the
reverse side of this sheet as directed in the instructions for your permit application.
A. During the five years immediately preceding submission of this application, has the applicant been convicted in
any jurisdiction of a criminal violation of any environmental law?
Yes
No
B. During the five years immediately preceding submission of this application, has a civil penalty been imposed
upon the applicant in any state, including Connecticut, or federal judicial proceeding for any violation of an
environmental law?
Yes
No
C. During the five years immediately preceding submission of this application, has a civil penalty exceeding five
thousand dollars been imposed on the applicant in any state, including Connecticut, or federal administrative
proceeding for any violation of an environmental law?
Yes
No
D. During the five years immediately preceding submission of this application, has any state, including
Connecticut, or federal court issued any order or entered any judgement to the applicant concerning a violation
of any environmental law?
Yes
No
E. During the five years immediately preceding submission of this application, has any state, including
Connecticut, or federal administrative agency issued any order to the applicant concerning a violation of any
environmental law?
Yes
No
(1)
(2a)
Type of
Action
Date
Commenced
(2b)
Date
Terminated
(4)
(3)
Jurisdiction
Case/Docket/
Order No.
(5)
Description
of Violation
Table of Enforcement Actions
Check the box if additional sheets are attached. Copies of this form may be duplicated for additional
space.