STATE OF CONNECTICUT
PUBLIC UTILITIES REGULATORY AUTHORITY
ANNUAL SHARED CLEAN ENERGY
FACILITY PROGRAM REVIEW – YEAR 8
DOCKET NO. 26-08-04
September 14, 2026
WRITTEN COMMENTS OF ALLCO FINANCE LIMITED
Allco Finance Limited ("Allco"), respectfully submits these written comments pursuant to
the Authority’s August 25, 2026 Notice of Request for Written Comments (the "Notice"). These
comments respond to three of the four topics identified in the Notice and, where indicated, to the
Joint Written Comments filed by Eversource and The United Illuminating Company (the "EDCs")
on September 11, 2026 (the "EDC Comments").
I.
PROCUREMENT PRICE CAP (NOTICE TOPIC 1)
The Authority should establish a different price cap for UI. The EDC Comments establish
why. In their comments the “EDCs recognize that initial Year 7 procurement results in UI’s service
territory were comparatively undersubscribed.” And as the EDCs also admit “[t]he availability of
suitable sites for SCEF development is materially more constrained within UI’s comparatively
urban service territory, including limitations associated with the availability of developable land.”
That latter constraint is a function of price. There are sites available in UI territory but not at a
cost that the current price cap would support. In their comments the EDC’s also “recognize that
project development costs remain subject to evolving market conditions, including changes in
federal trade policy and equipment costs,” all of which involve increases in price.
This is the last year for the SCEF program. Any unused capacity is lost forever. At least
for SCEF projects connecting with UI, the price cap should be eliminated. If the Authority
nonetheless retains a cap for UI-territory projects, it should be set no lower than $261.34/MWh.
That figure is not Allco’s invention; it is the Authority’s own. The Year 7 SCEF cap of
$182.94/MWh was borrowed from the 2026 NRES large zero-emission buy-all cap in order "to
Page 1 of 6
minimize potential intra-program competition between the NRES and SCEF Programs." Year 7
Decision at 10-11. But the 2026 NRES caps the Authority approved are differentiated by project
size and site type precisely because constrained sites cost more: $250.42/MWh for small zeroemission projects; $236.74/MWh for medium zero-emission projects; $261.34/MWh for large
zero-emission projects that are 100% solar canopy or carport; and $338.20/MWh for medium
canopy projects. The sites that exist in UI’s "comparatively urban" territory — the EDCs’ own
words — are overwhelmingly of the small, canopy, rooftop, and constrained-parcel character for
which the Authority’s NRES caps already recognize costs 29% to 85% above the large-project
figure. Tying UI-territory SCEF bids to a cap built for large greenfield economics does not
"minimize intra-program competition"; it guarantees that every viable UI site clears the SCEF cap
and is either bid into NRES instead or not built at all — which is exactly the undersubscription the
Year 7 results recorded.
Ratepayers need no cap to protect them here, and certainly no cap below the Authority’s
own NRES levels. The SCEF budget is fixed; a higher cap cannot increase the dollars spent, only
the capacity procured for those dollars, with competitive bidding below the cap setting the actual
clearing prices. In the Program’s final year, a binding cap in an undersubscribed territory does not
save ratepayers money — it forfeits renewable capacity the budget has already been approved to
buy.
II.
BUDGET REALLOCATION (NOTICE TOPIC 2)
Allco supports a middle ground. As the EDCs’ comments urge, the allocation should be
consistent with prior years and not revert to a starting reset point of 80/20, at least initially.
Keeping the same methodology will provide UI customers with the opportunity to which they
should be entitled to participate in the SCEF program. To the extent, however, that after all awards
are made by UI there is unused capacity, that unused capacity should at that point be added to
Eversource’s budget.
Page 2 of 6
III.
PROPOSED PROGRAMMATIC CHANGES (NOTICE TOPIC 4).
The Notice invites "discrete, incremental improvements, such as clarifying existing
requirements or definitions; or improving transparency or efficiency in the application or selection
process." Allco proposes six such improvements. Each is drawn directly from documented
Program administration problems in Years 5 through 7, and each can be implemented through
targeted edits to the Program Manual and RFP without structural change. The six suggested
improvements and clarifications Allco proposes are precisely the "transparency or efficiency"
improvements the Notice invites.
A. Clarify the Section 5.2.12 "partial award" exception and add an EDC-delay
exception.
Section 5.2.12 of the Year 7 RFP renders a bid ineligible where an existing sametechnology project at the site is not yet in service, subject to an express exception for "projects
issued a partial award in a previous SCEF solicitation," up to 5 MW minus the prior award. In the
Year 7 procurement, Eversource disqualified two Allco bids on April 9, 2026 based on an
interpretive gloss that appears nowhere in the RFP text — that a "partial award" exists only where
the prior award was smaller than the capacity sought in the earlier bid, rather than smaller than the
5 MW Program cap. The Authority should resolve this ambiguity for Year 8 by adding one
sentence to Section 5.2.12: "For purposes of this exception, a ‘partial award’ means any award
in a prior SCEF solicitation of less than five (5) MW for the Project Site." The Authority should
further add: "The in-service condition of this Section shall not apply where the existing project’s
failure to achieve its In-Service Date is attributable in whole or substantial part to the EDC’s
interconnection process." Without that second clarification, an EDC can disqualify new bids based
on the not-in-service status of projects that the EDC’s own interconnection delays have kept out
of service — a circularity that penalizes developers for the EDC’s performance. The rate case
record confirms this is not hypothetical: the EDC itself reports 550+ MW of large solar stuck in
its queues and "queue stagnation and project withdrawals." Docket No. 26-05-10, Exhibit CLPTSP-2 at 43.
Page 3 of 6
B. Codify automatic, deadline-bound refunds of bid deposits.
Section 3.5 of the Program Manual already provides that the EDC "shall return the
Development Period Security to the bidder if . . . the Bid is not selected." The Manual should be
clarified to make that obligation self-executing: "The EDC shall return the Development Period
Security to each non-selected bidder, without the need for any request or other action by the
bidder, within thirty (30) days of the issuance of selection results. Amounts not returned within
thirty (30) days shall accrue interest at the prevailing prime rate. The EDC shall report quarterly
to the Authority all Development Period Security held, refunded, and outstanding, by bid and
date." Allco’s Year 6 experience demonstrates the need: $225,000 in deposits on three nonselected bids remained unreturned for more than fifteen months after selection results, and were
released only after repeated inquiries and the EDC’s imposition of a "company letterhead" request
requirement found nowhere in the Program documents. A refund obligation that the Manual states
in mandatory terms should not depend on the persistence of the bidder.
C. Set deadlines for EDC metering, witness tests, and Approval to Energize.
The Program Manual obligates the EDC to meter SCEF facilities (§ 4.1) and makes the
EDC’s own Approval to Energize letter the trigger for the In-Service Date and the start of tariff
payments — but sets no deadline for the EDC to act. The Manual should provide: "Upon written
notice from a Subscriber Organization that a facility is mechanically complete and ready for
interconnection, the EDC shall complete any required metering installation within thirty (30)
days; shall schedule any required witness test within fifteen (15) days of a Subscriber
Organization’s request; and shall issue the Approval to Energize letter within ten (10) days of a
successful witness test. If the EDC fails to meet these deadlines for reasons not attributable to the
Subscriber Organization, the In-Service Date shall be deemed to occur, and Tariff payments shall
commence, on the date the deadlines would have been met."
D. Require reasoned, reviewable disqualification decisions.
The Manual and RFP should be clarified to provide that any bid disqualification must (a)
be issued in writing, citing the specific RFP or Manual provision relied upon; (b) afford the bidder
Page 4 of 6
five (5) business days to respond or cure before the disqualification becomes final; and (c) be
reported to the Authority with the EDC’s selection results, together with the bidder’s response. In
Year 7, Eversource initially asserted a second disqualification ground (§ 5.2.5) against an Allco
bid and then abandoned it without explanation after Allco refuted it — but no Program mechanism
required the EDC to explain, or the Authority to see, either the assertion or the retraction. Where
the procurement administrator is also the interconnecting utility — with its own commercial and
regulatory interests concerning the same parcels and circuits — basic administrative transparency
is a discrete, low-cost safeguard.
E. The project slope requirement should be eliminated.
The Year 7 RFP requires that no more than 10% of the project site contain slopes greater
than 15%. That restriction should be eliminated. It is a sledge-hammer pre-judgment of how a
project would fare under the general stormwater permit — an independent process, administered
by DEEP under delegated Clean Water Act authority, that already evaluates slope, soil, and runoff
conditions site-by-site with engineering controls. Sites that can satisfy the stormwater permit
should not be categorically excluded from bidding by a one-size-fits-all screen; the screen simply
removes otherwise-viable, lower-cost sites from the bid pool and raises clearing prices.
F. The prime farmland restriction should be eliminated.
Under the current requirements, a solar Shared Clean Energy Facility cannot be located, in
whole or in part, on Prime Farmland unless the bidder accepts financially burdensome or
prohibitive dual-use agrivoltaics conditions. That restriction should be eliminated. It appears
nowhere in General Statutes § 16-244z; it is a program-document overlay that raises project costs
for no corresponding ratepayer benefit, suppresses bids in the very rural areas with the most
developable land, and thereby denies low-income subscribers in surrounding communities the bill
credits the Program exists to deliver. Agricultural-land policy has its own siting forum; in the
Program’s final year, the Authority should let the budget buy the capacity the statute promises
rather than pricing it out through a restriction the legislature never enacted for this Program.
Respectfully submitted,
Page 5 of 6
ALLCO FINANCE LIMITED
/s/ Thomas Melone
Thomas Melone
Allco Finance Limited
777 West Putnam Avenue, Suite 300
Greenwich, CT 06830
Phone: [phone removed]
Email: [email removed]
CERTIFICATION
I hereby certify that on September 14, 2026, a copy of the foregoing was filed with the
Public Utilities Regulatory Authority and served upon each person designated on the official
service list in this proceeding in accordance with R.C.S.A. § 16-1-15.
/s/ Thomas Melone
Thomas Melone