107 Selden Street, Berlin, CT 06037
P.O. Box 270, Hartford, CT 06141-0270
Jennifer E. Galiette
Senior Counsel
[phone removed]
[email removed]
July 31, 2026
Mr. Jeffrey R. Gaudiosi, Esq.
Executive Secretary
Public Utilities Regulatory Authority
10 Franklin Square
New Britain, CT 06051
RE:
Docket No. 26-08-05 – Annual Energy Storage Solutions Program Review – Year 6
Compliance with Order No. 15 of Docket No. 25-08-05 (Interconnection Report)
Dear Mr. Gaudiosi:
The Connecticut Light and Power Company d/b/a Eversource Energy (“Eversource”) hereby submits an
Energy Storage Solutions (“ESS”) C&I Interconnection Status Report to the Public Utilities Regulatory
Authority (“PURA”) in compliance with Order No. 15 of the Authority’s final decision dated December
4, 2024 in Docket No. 24-08-05.
Specifically, Order No. 15 states:
No later than August 1, 2024, and annually thereafter, each EDC shall file as compliance
Reference Decision, Nov. 29, 2023, Docket No. 23-08-05, Order No. 26, p. 62: No later
than August 1, 2024, and annually thereafter, until the ESS program stops accepting new
enrollments, each EDC shall file as compliance an ESS Interconnection Report, as detailed
in Section IV.D., in the applicable annual review proceeding (i.e., in 2024, Docket No. 2408-05). The Report shall consist of a summary of the state of interconnection for all
commercial ESS projects and shall include, at a minimum: (1) the interconnection status
of each commercial ESS project; (2) the expected EDC interconnection approval due date
for each commercial project per EDC interconnection guidelines, as applicable; (3) the
date all required interconnection materials were submitted to the utility for each
commercial ESS project; (4) the number of days from when all required interconnection
materials were submitted to the utility for each commercial ESS project up to the
completion of the interconnection process; (5) the attrition rate for all commercial ESS
projects, based on the withdrawal of a project’s interconnection application; (6) a list of
the most common reasons for ESS interconnection delays; and (7) EDC-proposed solutions
for each of the most common reasons delaying ESS interconnections.
Pursuant to Order No. 15, Eversource’s ESS Interconnection Report is included as Attachment 1
hereto. Attachment A shows the interconnection status of each commercial ESS project.
Attachment B shows the number of days from when all required interconnection materials were
submitted to the utility for each commercial ESS project up to the completion of the
interconnection process.
If you have any questions concerning this filing, please do not hesitate to contact Jennifer Runyon,
Energy Efficiency Consultant, Eversource Energy, [email removed].
Sincerely,
Jennifer E. Galiette
Jennifer E. Galiette
Senior Counsel
On Behalf of CL&P dba Eversource Energy