Due 7/9/2026…
Filed
- Type of filing
- Notice (Notice of Request for Written Comments)
- Date filed
- June 16, 2026
- Filed by
- Not recorded
- Files
- 1
As listed on the current system
Notice, Of Request for Written Comments 06/16/2026 (Due 7/9/2026 ... ) [26-08-05]
Files1
26-08-05 Notice of Request for Written Comments 1.pdf
PDF · 174 KB · 4 pagesText searchable
Download 26-08-05 Notice of Request for Written Comments 1.pdfRead the text of 26-08-05 Notice of Request for Written Comments 1.pdf
STATE OF CONNECTICUT
PUBLIC UTILITIES REGULATORY AUTHORITY
DOCKET NO. 26-08-05
ANNUAL ENERGY STORAGE SOLUTIONS
PROGRAM REVIEW – YEAR 6
NOTICE OF REQUEST FOR WRITTEN COMMENTS
(July 9, 2026)
In 2021, the Public Utilities Regulatory Authority (Authority) established a statewide
electric storage program, later re-named the Energy Storage Solutions Program (ESS
Program or Program). Decision, July 28, 2021, Docket No. 17-12-03RE03, PURA
Investigation into Distribution System Planning of the Electric Distribution Companies –
Electric Storage (Storage Decision). Pursuant to Section IV.E. of the Storage Decision,
the Authority conducts an annual proceeding to review key Program metrics and to make
strategic adjustments to ensure: (1) continued alignment with the program objectives
established in the Storage Decision; and (2) that the Program is on track to meet its
deployment targets. This proceeding serves as the administrative record for the
Authority’s Year 6 Program review. The Authority may include additional relevant topics
regarding Program implementation at its discretion.
NOTICE OF REQUEST FOR WRITTEN COMMENTS
To facilitate the Authority’s evaluation of the Program, the Authority requests that
docket participants and interested stakeholders file written comments on or before 4:00
p.m. on Thursday, July 9, 2026, addressing the following:
1. Enrollment Incentive Clawback
During the Year 5 ESS annual review cycle, the Authority adopted Construct 5,
which eliminated passive dispatch and significantly reduced upfront incentives in favor of
a predominantly performance-based compensation structure. Decision, Dec. 17, 2025,
Docket No. 25-08-05, Annual Energy Storage Solutions Program Review – Year 5 (Year
5 Decision), pp. 20–21. This construct was intended to minimize ratepayer exposure
while better aligning participant compensation with realized system value. Id. Construct
5 does not include a clawback provision tied to participation in active dispatch, as active
dispatch participation is not a condition for receipt of the enrollment incentive. Id., pp. 1415.
Further, Section 3.7 of the ESS Program Manual provides that, once a customer
who has received an enrollment incentive unenrolls from active dispatch, “there is no
requirement to return any portion of the Enrollment Incentive.” Motion No. 15, Jan. 6,
2026, Docket No. 25-08-05, Att. 2, p. 27.
10 Franklin Square, New Britain, CT 06051
An Equal Opportunity Employer
www.ct.gov/pura
Docket No. 26-08-05
2
In Section A of its January 13, 2026 ruling on Motion No. 15, the Authority directed
The Connecticut Light and Power Company d/b/a Eversource Energy (Eversource), The
United Illuminating Company (UI; collectively, with Eversource, the electric distribution
companies or EDCs), and the Connecticut Green Bank (CGB; collectively, with the EDCs,
the ESS Program Administrators) to implement a clawback mechanism for the enrollment
incentive where participants disenroll from the ESS Program prior to the expiration of their
10-year term. Motion No. 15 Ruling, Jan. 13, 2026, Docket No. 25-08-05, p. 2.
The Authority determined that, although the enrollment incentive under Construct
5 is not conditioned on active dispatch participation, it is premised on continued
participation in the ESS Program over the 10-year enrollment term. Id. Allowing a
participant to retain the full enrollment incentive despite early disenrollment could
undermine the structure and intent of Construct 5 by creating a potential incentive to enroll
solely to obtain the upfront payment without delivering sustained ratepayer benefits. Id.
The ESS Program Administrators objected and filed a motion for reconsideration
pursuant to General Statutes § 16-9. Motion No. 16, Jan. 21, 2026, Docket No. 25-0805, p. 2. The ESS Program Administrators raised concerns regarding the feasibility and
implementation of an enrollment incentive clawback requirement, including administrative
burden and cost, the potential for customers to be subject to clawbacks due to
circumstances beyond their control (such as manufacturer bankruptcy), and uncertainties
associated with customer relocation or transfer of battery ownership. Id., pp. 3-4. The
ESS Program Administrators requested that the issue be deferred to the Year 6 annual
ESS Program review to allow for broader stakeholder input. Id., p. 4.
In light of these concerns, the Authority stayed Section A of its Motion No. 15
Ruling and indicated its intent to revisit the issue during the Year 6 annual ESS Program
review. Motion No. 16 Ruling, Jan. 29, 2026, Docket No. 25-08-05, p. 3. The Authority
further clarified that the absence of a clawback provision in the Year 5 Decision reflected
a determination specific to dispatch participation requirements, rather than continued
enrollment in the ESS Program. Id., p. 2; Year 5 Decision, pp. 14-15.
Accordingly, the Authority seeks stakeholder input on whether an enrollment
incentive clawback should be implemented such that, if a project disenrolls prior to the
conclusion of its 10-year enrollment term, a prorated portion of the enrollment incentive
must be repaid. For example, a project that disenrolls after one year could be required
to return 90% of the incentive. Consistent with prior determinations, any clawback could
be conditioned solely on continued ESS Program enrollment and not on participation in
active dispatch.
The Authority specifically requests comments on: (1) whether the expected
ratepayer benefits of an enrollment incentive clawback mechanism outweigh the
associated costs to participants and Program Administrators; (2) how responsibility for
repayment should be allocated in cases of early disenrollment; and (3) whether such a
requirement should apply universally or be limited to particular customer classes or
incentive thresholds.
Docket No. 26-08-05
3
2. Front-of-the-Meter (FTM) Storage Tariff
During the Year 2 annual ESS Program review, the Authority convened an FTM
Storage Working Group to develop a comprehensive set of FTM storage tariff and
incentive design proposals for Authority consideration. Decision, Dec. 21, 2022, Docket
No. 22-08-05, Annual Energy Storage Solutions Program Review – Year 2, p. 39.
Following that effort, the EDCs each developed Wholesale Distribution Access
Tariffs (WDATs) to enable FTM storage resources to interconnect with the distribution
system and participate in wholesale markets. EDC Compliance, Docket No. 22-08-05,
Dec. 29, 2023. The EDCs subsequently filed their respective WDATs with the Federal
Energy Regulatory Commission (FERC), which approved each proposal.1
However, the record in Docket No. 25-02-14, Renewable Energy Tariff Programs
Successor Study, indicated that the WDAT framework is limited in scope. Specifically,
the WDATs facilitate the sale of energy into wholesale markets but do not provide a
mechanism for FTM storage resources to purchase energy from the EDCs at retail (i.e.,
the WDAT functions as a one-way tariff). PURA Corresp., Feb. 27, 2026, Docket No. 2502-14, p. 106. In that proceeding, the Solar Energy Industry Association (SEIA) and New
Leaf advocated for the development of a bidirectional time-of-use (TOU) retail rate
applicable to standalone FTM storage. New Leaf Corresp., Sept. 23, 2025, Docket No.
25-02-14, p. 8; SEIA Comments, Sept. 10, 2025, Docket No. 25-02-14, p. 4. UI further
noted that standalone storage is not currently eligible to participate in any existing retail
TOU tariffs in Connecticut as a distinct resource class. UI Interrog. Resp. CAE-49, Docket
No. 25-02-14, p. 2. Although the WDATs approved by FERC include TOU constructs,
those provisions apply solely to wholesale transactions and do not establish retail rate
structures. Id.
In light of these limitations, the Authority expressed interest in directing the EDCs,
in a future proceeding, to develop retail TOU rates for standalone FTM storage to support
its effective integration and operation. PURA Corresp., Feb. 27, 2026, Docket No. 25-0214, p. 106.
Accordingly, the Authority seeks stakeholder input on the appropriate process for
developing retail TOU rates for standalone FTM storage, as well as the key design
features such rates should include. In particular, the Authority requests comment on
issues such as: (1) rate structure (including the number and definition of TOU periods);
(2) alignment with the EDCs’ WDATs; (3) metering requirements; (4) eligibility criteria for
participation: and (5) the stakeholder process and EDC timeline needed to develop and
implement such rates.
The Authority notes that any retail TOU rates for standalone FTM storage
developed through this or a separate proceeding would be revenue neutral. That is, such
rates would not include incremental ratepayer-funded incentives to support FTM storage
See
FERC
dockets
ER24-3153-000
https://elibrary.ferc.gov/eLibrary/search.
1
and
ER24-2939,
available
at:
Docket No. 26-08-05
4
deployment, but would instead establish a functional retail rate structure that enables FTM
storage resources to purchase energy from the EDCs where no such mechanism
currently exists, while maintaining appropriate cost allocation and avoiding crosssubsidization among customer classes.
Dated at New Britain, Connecticut this 16th day of June, 2026.
By direction of the Presiding Officer,
Jeffrey R. Gaudiosi, Esq.
Executive Secretary