STATE OF CONNECTICUT
PUBLIC UTILITIES REGULATORY AUTHORITY
ANNUAL ENERGY STORAGE
SOLUTIONS
PROGRAM REVIEW – YEAR 6
:
:
:
DOCKET NO. 26-08-05
AUGUST 27, 2026
WRITTEN COMMENTS OF THE UNITED ILLUMINATING COMPANY
The United Illuminating Company (“UI” or the “Company”) provides the following
Written Comments, in response to the Notice of Request for Written Comments (the “Notice”),
issued by the Public Utilities Regulatory Authority (“PURA” or the “Authority”) on August 12,
2026, in the above captioned docket.
The Notice requests that docket participants file written comments concerning two topics:
the Program Administrator’s Recommended Programmatic Changes and the Bidirectional Electric
Vehicle Working Group Final Report.
1. Recommended Programmatic Changes
BACKGROUND
The Connecticut Green Bank, Eversource Energy, and UI (collectively, “the Program
Administrators” or “the PAs”) proposed several modifications to the Energy Storage Solutions
(“ESS”) Program Manual in Attachment 4 of the Program Administrators’ Compliance with
Standing Order 3. Overall, these proposed changes are reasonable, administrative in nature, and
aid in advancing the ESS Program’s foundational objectives established in the Final Decision,
issued on July 1, 2021 in Docket No. 17-12-03RE03 (the “Storage Decision”). Specifically, the
recommendations support continued delivery of ratepayer benefits, facilitating the deployment of
distributed storage resources, reducing barriers to participation, further improving program
administration, and preserving market confidence.
a. Alignment with Objective 1: Positive Net Present Value for Ratepayers
Program Objective 1 of the Storage Decision directs the Program to provide positive net
present value to ratepayers. Several proposed modifications within the Program Manual improve
program efficiency and reduce administrative burden without proposing modified incentive levels
or expanding ratepayer obligations. The removal of passive dispatch enrollment provisions,
clarification of enrollment requirements, consolidation of legacy program information into
supplemental materials, and streamlining of program documentation reduce administrative
complexity and implementation costs. Likewise, the removal of annual performance incentive
payments reflects practical limitations of DERMS administration and is expected to streamline
customer program performance comprehension without materially affecting customer
performance incentive disbursement. These proposed modifications help ensure that the program
administrators remain focused on delivering measurable grid and customer benefits while
maintaining prudent use of ratepayer funds.
b. Alignment with Objective 2: Multiple Grid Benefits
The ESS Program was designed to provide multiple grid benefits, including peak reduction,
increased resilience, and support for distributed energy resources. The proposed operational
revisions to allow for alternative communications protocols where OpenADR integration is not
feasible can continue to encourage expanded participation by aggregators, operators, and original
equipment manufacturers that may otherwise be unable to participate. Increasing the number and
diversity of integrated storage assets enhances the ability of the Program to deliver reliable grid
services and maintain active participation during peak reduction events. Additionally, enhanced
provisions allowing case-by-case add-on systems and reasonable change orders may facilitate
incremental storage deployment that can increase available grid capacity over time.
c. Alignment with Objective 3: Sustained and Orderly Development of Connecticut’s
Storage Industry
Many of the proposed changes directly support Program Objective 3 of the Storage
Decision. The establishment of the broader “Eligible Provider” definition, clarification of
participant roles, modernization of payment beneficiary provisions, transfer flexibility, improved
enrollment procedures, and accommodation of add-on systems reduce uncertainty for contractors,
third-party owners, aggregators, lenders, and customers. These changes increase the ease of
customer participation and increase forecasting outlooks, while also preserving program controls.
d. Alignment with Objective 4: Resilience for Priority Populations
While the proposed modifications are primarily administrative, they support resilience
objectives by reducing administrative hurdles that could otherwise delay project development.
More efficient enrollment pathways, clearer eligibility timelines, accommodation of system
expansions, and reasonable project change order provisions allow for eligible customers to
successfully complete projects and receive resilience benefits associated with storage ownership.
Continued program accessibility remains important for underserved, low-income, and resiliencefocused customer segments.
e. Alignment with Objective 5: Lowering Barriers to Storage Deployment
Program Objective 5 of the Storage Decision receives the largest impact overall from the
PAs proposed program modifications. The revisions simplify enrollment requirements, clarify
eligibility deadlines, modernize insurance requirements, provide flexibility for legacy customers
seeking system expansions, allow reasonable project modifications, and reduce administrative
ambiguity through the Program Manual.
The proposal to measure the six-month enrollment incentive eligibility period from
approval-to-energize regardless of provider approval status establishes a straightforward and easily
comprehended rule. Similarly, the proposed add-on battery provisions and reasonable change-
order accommodation address practical issues encountered by customers and contractors after
project approval. These reforms reduce avoidable market friction while preserving program
integrity.
f. Alignment with Objective 6: Environmental Benefits
Although the recommended changes do not directly modify dispatch requirements or
incentive structures associated with emissions reductions; they support continued deployment of
battery storage systems that further reduce reliance on fossil-fuel peaking resources and facilitate
greater integration of renewable generation resources. By improving participation pathways and
lowering administrative burdens, these changes can incrementally contribute to additional storage
adoption and their associated environmental benefits.
g. Alignment with Objective 7: Maximizing Wholesale Capacity Market Benefits
The proposed modifications preserve the Program’s existing operational structure while
allowing additional flexibility in communications and participant administration. By supporting
participation from aggregators, operators, and third-party owners, the changes may improve the
ability of enrolled resources to perform consistently and deliver capacity-related value. Improved
market participation and operational reliability ultimately support the Program’s goal of
maximizing benefits derived from storage participation while maintaining benefits for Connecticut
ratepayers.
CONCLUSION
The Program Administrator’s recommended modifications are generally administrative
refinements that reflect lessons learned during ESS Program implementation and the continued
evolution of Connecticut’s energy storage market. Collectively, the proposed changes advance
multiple ESS Program Objectives, particularly Objectives 1, 3, and 5 by improving administrative
efficiency, reducing barriers to participation, enhancing market certainty, supporting continued
investment and deployment of distributed energy resources. The proposed revisions maintain the
core structure and policy established by PURA while providing the flexibility needed to support
continued program growth and effective administration. UI recommends the Authority proceed
with the approval of the Program Administrator’s recommendations as proposed.
2. Bidirectional Electric Vehicle (EV) Participation
UI appreciates the extensive work completed by the ESS Program Administrators,
Customized Energize Solutions, Working Group participants, and PURA staff regarding the
potential integration of bidirectional electric vehicles (“V2G”) into the ESS Program. UI would
like to reinforce the support for the PA recommendations and agreement that the final report
establishes a thoughtful, data-driven framework for incorporating V2G assets into Connecticut’s
ESS Program and distributed energy resource landscape.
UI agrees with the PA conclusion that a phased approach is the most prudent path forward.
The report highlights that while commercial applications including electric school bus and other
fleet deployments have demonstrated increasing technological maturity, residential V2G
deployments continue to face unresolved questions regarding customer behavior, interoperability,
DERMS coordination, interconnection processes, managed charging interactions, metering
requirements, and co-located distributed generation. The PAs determined that these issues must be
comprehensively addressed prior to opening the ESS program to broader, residential participation.
Specifically, UI supports the recommendation to allow the enrollment of qualifying
commercial EVSE beginning with the 2027 ESS season, subject to the proposed eligibility
requirements, including installation behind a commercial meter, a minimum discharge capability
of 20kW per port, and exclusion from simultaneous participation in the light-duty Managed
Charging Program. The report appropriately identifies commercial fleet operators as the most
mature and operationally capable initial participants, offering the greatest likelihood of delivering
measurable grid benefits while allowing the PAs to gain practical implementation experience.
UI further agrees that the ESS and Managed Charging Program participation should not be
combined until the significant operational and customer experience challenges identified by the
Working Group have been resolved. The report appropriately recognizes that unmanaged
interactions between charging and discharging programs could cause conflicting dispatch signals,
increased customer confusion, technology integration challenges, and encourage adverse charging
behaviors that undermine both program’s objectives. Given the importance of maintaining
customer confidence in V2G technologies, UI agrees that these challenges must be addressed prior
to dual participation approval being granted.
Additionally, UI supports the recommendation to maintain alignment with ongoing
interconnection efforts to gain experience from both the Connecticut Innovative Energy Solutions
pilots and the Massachusetts Clean Energy Center V2X demonstration prior to expanding
participation to residential customers. The findings documented in the report demonstrate that realworld deployments continue to identify issues involving interoperability, metering,
communications standards, solar co-location, and interconnection requirements that should be
better understood before a statewide expansion were to occur.
Most importantly, UI notes that the Working Group’s discussions repeatedly demonstrated
that V2G implementation extends far beyond the scope of any single PURA proceeding. As
documented throughout the report, V2G intersects with ESS program design, Managed Charging,
EV charging tariffs, make-ready incentives, the Medium and Heavy-Duty EV Program,
interconnection requirements, distributed generation policies, telemetry standards, DERMS
integration, and future renewable compensation frameworks. The breadth of these interactions
makes it incredibly difficult to comprehensively address V2G issues within existing dockets.
UI supports the Program Administrators' recommendation that PURA consider establishing
a dedicated V2G proceeding to address the broader policy, program design, managed charging,
interconnection, and implementation issues associated with bidirectional vehicles. A dedicated
V2G docket would provide a centralized forum to resolve these issues in a coordinated manner
rather than addressing them through multiple proceedings.
UI therefore encourages PURA to adopt the PAs phased implementation recommendations,
authorize the commercial rollout for 2027, and establish a dedicated V2G proceeding in 2027 to
serve as the primary avenue for addressing the broader policy and implementation questions
necessary to support long-term V2G deployment in Connecticut.
Respectfully submitted,
THE UNITED ILLUMINATING COMPANY
By: AlexE. Soter
Alex E. Soter
Counsel
UIL Holdings Corporation
180 Marsh Hill Road
Orange, CT 06477
Phone: [phone removed]
Email: [email removed]
CERTIFICATION
I hereby certify that on August 28, 2026, the foregoing document was filed with the Public Utilities
Regulatory Authority, and copies of the foregoing document were served upon each person
designated on the Authority’s official service list in this proceeding in accordance with R.C.S.A.
§ 16-1-15.
By: AlexE. Soter
Alex E. Soter
Counsel
As listed on the current system
Written Comments - 08/27/2026 [26-08-05] (Avangrid)