STATE OF CONNECTICUT
PUBLIC UTILITIES REGULATORY AUTHORITY
ANNUAL EV CHARGING PROGRAM
REVIEW – YEAR 6
:
:
:
DOCKET NO. 26-08-06
FEBRUARY 2, 2026
JOINT MOTION FOR CLARIFICATION
The Connecticut Light and Power Company d/b/a Eversource Energy (“Eversource”) and
The United Illuminating Company (“UI”) (together, the “EDCs” or “Program Administrators”)
respectfully submit this motion (“Motion”) requesting that the Public Utilities Regulatory
Authority (“PURA” or the “Authority”) clarify whether port deployment targets for any given
segment not met during one program cycle are able to be added to the subsequent program cycle’s
target. For the purposes of this Motion, the DCFC Program Area is used as an illustrative example.
In its Final Decision, dated November 29, 2023, in Docket No. 23-08-06 (“Year 3
Decision”), the Authority allocated additional ports to the DCFC Program Area deployment targets
within the 2022-2024 Program Cycle. This additional allocation was in response to strong
customer demand which exceeded the original 2022-2024 Program Cycle targets. Specifically,
PURA found that:
it is necessary to allocate additional ports to the DCFC Program Area deployment
targets within the 2022–2024 Program Cycle. Specifically, the Authority allocates
an additional 110 ports for Eversource and 27 ports for UI in Year 3, and the
associated funding to support such deployments for the DCFC Program Area,
subject to the existing maximum site incentives. The Authority finds it appropriate
to return to the original 2022-2024 Program Cycle DCFC deployment target of
137 ports for Year 3 given that the NEVI Phase 1 will also incentivize DCFC
deployment during 2024.
Year 3 Decision at 31. This allocation was additive to the 137 ports for Eversource and 27 ports
for UI for the DCFC Program Area that the Authority allocated to the 2022-2024 Program Cycle
port deployment targets as part of the Final Decision, dated December 14, 2022, in Docket No. 22-
08-06 (“Year 2 Decision”). The allocation of additional ports to the DCFC Program Area from
both the Year 2 Decision and Year 3 Decision resulted in the following DCFC Port Deployment
Targets:
Table 1: DCFC Program Deployment Targets
NUMBER OF PORTS (STATEWIDE)
Program Area
DCFC
Utility
2022-2024
2025-2027
2028-2030
Total
Eversource
357
138
138
633
UI
81
34
34
149
Total
438
172
172
782
Ultimately, of all of the projects that Eversource selected in the 2022-2024 Program Cycle, 219 of
the DCFC ports were successfully awarded; however, 138 of the total 357 port deployment target
were unawarded1. For UI, 52 of the DCFC ports were successfully awarded; however, 29 of the
total 81 port deployment target were unawarded.
The EDCs seek clarification on whether the ports that were unawarded in the 2022-2024
Program Cycle target can be added to the 2025-2027 Program Cycle target. For Eversource, that
would mean that the 2025-2027 Program Cycle target for DCFC would be the original 138 ports
plus the 138 ports that were unawarded in the previous cycle, or a total of 276 ports. For UI, that
would mean that the 2025-2027 Program Cycle target for DCFC would be the original 34 ports
plus the 29 ports that were unawarded in the previous cycle, or a total of 63 ports. Eversource notes
that 94 DCFC ports were awarded as part of the 2025 DCFC application process, while UI notes
that it awarded 35 DCFC ports. If the unawarded 2022-2024 Program Cycle ports are not added
1
Unawarded ports are defined as those ports that were either not awarded, or awarded but subsequently
canceled by either the Company or the Customer.
to the original 2025-2027 DCFC port deployment target, then Eversource only has 44 more DCFC
ports to award during the term, while UI will have exceeded its 2025-2027 DCFC port deployment
target by 1 port. However, if the unawarded 2022-2024 Program Cycle ports are added to the
original 2025-2027 DCFC port deployment target, then Eversource has 182 more DCFC ports to
award during the term and UI has 28 more DCFC ports.
WHEREFORE, the Program Administrators request that PURA clarify whether port
deployment targets for any given segment not met during one program cycle are able to be added
to the subsequent program cycle’s target.
RESPECTFULLY SUBMITTED,
THE CONNECTICUT LIGHT AND POWER
COMPANY
THE UNITED ILLUMINATING
COMPANY
Daniel T. Crisp
Alex E. Soter
Daniel T. Crisp
Senior Counsel
As Agent for The Connecticut Light and
Power Company d/b/a Eversource Energy
P.O. Box 270
Hartford, CT 06141
Alex E. Soter
Counsel
As Agent for The United Illuminating
Company
180 Marsh Hill Road
Orange, CT 06477
CERTIFICATION
This is to certify that on this 2nd day of February 2026, the foregoing document was filed
with the Authority, and copies of the foregoing document were served upon each person designated
on the Authority’s official service list in this proceeding in accordance with R.C.S.A. § 16-1-15.
By:
Daniel T. Crisp
Daniel T. Crisp
As listed on the current system
Motion No. 003 02/02/2026 (UI joint with Eversource Energy) - Joint Motion for Clarification [26-08-06]