Skip to main content

A prototype public docket site for the Connecticut Public Utilities Regulatory Authority

Utility Dockets and Filings

Compliance Filing

Compliance Filing, Order No. No

Compliance filingFiled by Eversource Energy24 files
Part of docket 26-08-07Open
  • Electric
Innovative Energy Solutions Program Cycle 5

Files24

Search terms highlighted
Eversource rate increase is on 5 pages across 2 files of the text below, highlighted. Go to the first matchClear highlighting
Words on different pages
2 pages match
Words on different pages

Text of ES-Attachment 2b 2026 TDRP-Appendix 8.pdf

Extracted from the file · 23 pages · 37,559 characters

Text of ES-Attachment 2b 2026 TDRP-Appendix 8.xlsx

Sheet names, column headings and text cells; numbers left out

Text of ES-Attachment 3.pdf

Extracted from the file · 1 page · 7,205 characters

Text of ES-Attachment 3.xlsx

Sheet names, column headings and text cells; numbers left out

Text of ES-Attachment 4.pdf

Extracted from the file · 44 pages · 108,591 characters

Text of ES-Attachment 4.xlsx

Sheet names, column headings and text cells; numbers left out

Text of ES-Attachment 5.pdf

Extracted from the file · 30 pages · 79,263 characters

Words on different pagesRead the text of ES-Attachment 5.pdf

Text of ES-Attachment 1.xlsx

Sheet names, column headings and text cells; numbers left out · first 300,000 characters

Text of ES-Attachment 1.xlsx

Sheet names, column headings and text cells; numbers left out · first 300,000 characters

Words on different pages
  1. Page 29 of 176

    03/31/2026 Docket No. 86-12-03 Cause of Outages 2025 By Meter Outages Chart VI-2.1 - Causes of Outages by Meter Outages (2025) 29
  2. Page 30 of 176

    03/31/2026 Docket No. 86-12-03 Cause of Outages 2021 - 2024 By Meter Outages Chart VI-2.2 - Causes of Outages by Meter Outages (2021 - 2024) 30
  3. Page 31 of 176

    03/31/2026 Docket No. 86-12-03 Cause of Outages 2025 By Meter Time Lost Chart V-3.1 - Causes of Outages by Meter Time Lost (2025) 31
  4. Page 32 of 176

    03/31/2026 Docket No. 86-12-03 Cause of Outages 2021 - 2024 By Meter Time Lost Chart V-3.2 - Causes of Outages by Meter Time Lost (2021 - 2024) 32
  5. Page 33 of 176

    03/31/2026 Docket No. 86-12-03 The outage category in which the Company can exercise significant influence is the "Distribution System" category. Although the actual number of interruptions, meter outages, and lost meter-time vary from year to year, UI believes that through continued efforts, outages in this category can be managed, with a balanced concern for economics. The percentages cited in the following paragraphs relate to the “Distribution System” subcategory, (“All Others” on the Pie Charts), and exclude outages related to major storms, forced transmission and power supply, planned outages and customer caused outages. In 2025, the number of wildlife contact incidents, as a percentage of the Distribution System (“All Others”) subcategory, 9.3%, (Chart V-1.1), as in previous years, 7%, (Chart V-1.2), has maintained a relatively level impact since completion of the project. The post-program impact of wildlife contacts has remained a reduction to the pre-program wildlife contact contribution to customer impact (SAIFI); this maintained status is a direct result of the three-year program (20152017) to replace wildlife guards. UI will continue to install wildlife guards on new transformer installations as well as coat the tops of critical overhead equipment, such as regulators and specific types of reclosers, with an insulating coating designed to minimize the potential for phase-toground squirrel or bird contacts. In response to Docket No. 13-01-19, “Application of The United Illuminating Company to Increase Rates and Charges”, PURA approved $100 million for an 8-year plan for vegetation management during 2014-2021. In response to Docket No. 16-06-04, “Application of The United Illuminating Company to Increase Rates and Charges”, PURA approved $162 million for a 12year plan for vegetation management extending the program to 2025. In Docket No. 22-08-08, “Application of The United Illuminating Company to Increase Rates and Charges”, the Authority approved a one-year rate plan, directed the Company to maintain the current annual funding levels for the UPZ program, and stipulated changes in the way the UPZ Program is being prioritized and executed, via Order 21, that: “UI shall develop and submit for Authority review and approval in Docket No. 23-08-09, Annual Electric Distribution Company Reliability and Resilience Framework Review a four-year work plan to implement the UPZ priorities for years 2024 to 2027 and to transition to a four-year trimming cycle by 2027.” Order 21 further stipulates that this work plan shall also demonstrate compliance with the following priorities (as outlined in section VI.A.15 of its Ruling). • Start the transition to four-year cycle trimming • Address first pass of remining single-phase system • Perform a second pass of full UPZ clearance of three-phase systems The Company has modified the priorities, annual scope, schedule, and the annual cost of the program to align with the Authority’s directives. The modifications are underway and being effectuated without any increase to the approved annual expenditure levels. The vegetation management work plan for 2024 through 2027 emphasizes transitioning to a 4-year trimming 33
  6. Page 34 of 176

    03/31/2026 Docket No. 86-12-03 cycle; preserving the clearances where the UPZ Spec has already been applied; completing approximately 60% of the remining single phase circuit miles; and maintaining a total annual cost that is consistent with the approved expenditure levels. In Docket No. 24-10-04 the Authority subsequently determined the Company’s UPZ plan complied with direction given in the 22-08-08 Decision. Motion No.5 Ruling, Oct. 27, 2023, Docket No. 23-08-09, Annual Electric Distribution Company and Reliability and Resiliency Framework Review. The major components of UI’s proposed program are: 1. Utility Protection Zone Specification, (UPZ), is UI’s storm resiliency tree work specification, creating an eight-foot side clearance ground to sky, retaining desirable low height or ornamental trees within the zone or those that are planted under the Right Tree – Right Place program. Additionally, the Company identifies and removes whole or parts of hazardous trees from outside of the zone that could fall causing damage to utility infrastructure, facilities, or equipment. 2. Utility Protection Zone Maintenance (UPZM) maintains the previously established UPZ, or clearance within the rectangular area extending horizontally for a distance of eight feet from any outermost primary electrical conductor. Additionally, removal in whole or in part of hazardous trees that could fall from inside or outside of the zone causing damage to utility infrastructure, facilities or equipment. 3. UI documents and tracks all objections, requests for modification and decisions made by municipal tree wardens and the State Department of Transportation through the full execution of Public Act 14-151 that cause nonconformities, or areas where UI is not able to meet these specifications within and outside of the Utility Protection Zone (UPZ). Instances of outages caused by nonconforming trees will be documented and considered a reportable performance attribute. In 2025, tree contact incidents continue as a significant cause of customer outages in terms of the number of customers impacted. For 2025, tree contact incidents accounted for 17.2% of the outages within the Distribution System subcategory. The average of tree contact incidents as a percentage of the Distribution System subcategory during previous years, (2021-2024) totals 23.7%. Excluding transformer failures which are not a major source of customer minutes interrupted, equipment failures on the overhead system for 2025, as a percentage of the Distribution System subcategory, (28.5%), as in previous years, (24%), continue as a significant contributor to customer minutes interrupted. UI recognizes this situation, and is cautious in its selection of new equipment, so that it selects durable equipment and material to construct and maintain its overhead 34
  7. Page 35 of 176

    03/31/2026 Docket No. 86-12-03 and underground distribution system. UI has taken steps to analyze assets throughout their life cycle. One such analysis is the periodic in-service inspection of equipment to determine where the assets reside on their life cycle curves. This aids in making prudent asset replacement and/or rehabilitation decisions before customer reliability is impacted. Also, UI analyzes certain equipment failures to determine what type of equipment has a significant failure rate and is negatively impacting customer reliability. Referring to Appendix 11, “Five-Year Outage by Cause Summary (excluding major storms),” a comparison of 2025 data with previous years’ data (2021 - 2024) reveals the following: • Distribution system outages, defined as all outages other than Transmission/Power Supply, Customer Caused, Scheduled/Prearranged, or Major Storm, historically account for the majority of customer interruptions and customer minutes of interruption. • Within the distribution system subset, tree-related incidents, wildlife contacts, and failure of overhead equipment continue to comprise the majority of outage events. 35
  8. Page 36 of 176

    03/31/2026 Docket No. 86-12-03 VII. Reliability Improvement Programs and Budget Reliability programs are deterministic / reactive or probabilistic / proactive in nature, or a combination of both. Deterministic or reactive programs are designed to address circuit reliability or customer reliability outlier performance. Probabilistic or proactive programs are designed to prevent circuit or customer reliability performance from becoming an outlier. UI's policy is to design all distribution systems to meet the Company's Reliability Criteria (DEG 80). Each project is analyzed to determine what features (for example, tree-wire, buried cable, line reclosers, sectionalizing switches, lightning arresters, additional fusing, wildlife protection, etc.) are necessary to produce the desired level of reliability. Repair time and circuit backup requirements are analyzed such that rapid service restoration is possible through switching and sectionalizing to minimize the extent of an actual outage. Construction design standards provide additional details of how reliability is incorporated as a part of every project. This principal element is probabilistic in nature. Enhancements to the existing distribution system are based on both deterministic and probabilistic performance. In addition to the design of reliability into the systems themselves, UI reliability programs consist of five principal elements. Some programs significantly overlap the principal element types, such as: Installation of advanced two-way meters is exceeding current budgets for meter purchases. Meter exchanges are utilized for aging meters (meters greater than 20 years old and fully depreciated), power outage applications (Two-Meters per Transformer), Disconnect for Non-Payment (DNP), Get Customer Name (GCN) and Move in/Move Out orders (performs remote connect/disconnect activities without rolling a vehicle), estimates/consecutive estimate meter replacements (current population of one-way meters 14 years old and beginning to show signs of failure) and general exchanges to enhance the operation of the two-way network and customer service expectations. This is a customer facing activity which provides service to customers where accurately functioning meters is critical. L&G will stop supporting AMR meters by the end of 2026. Based on historical data and projected deployment strategy the 2026 scope for this project is as follows: • New Customers: This is a reactive program that has been consistently deploying ~3,500 units yearly and a similar figure is expected for 2026. • Defective Equipment: Reactive program anticipating ~4,500 failures per year based on forecast. • AMR/AMI Program: Plan to replace ~13,050 AMR meters in this category in 2026. • Solar/DG: UI saw ~3,000 solar requests in 2025, but due to the increasing volume of DG requests, the estimates have increased to around ~3,500 requests for 2026. 36
  9. Page 37 of 176

    03/31/2026 Docket No. 86-12-03 Scope New Customer Defective Equipment AMR/AMI Solar/DG Load Ctrl Adaptor 2026 Units 3,500 4,500 13,050 3,500 0 Unit Price $287.37 $325.22 $325.22 $287.37 $447.72 Total $1M $1.5M $4.2M $1M - The 2026 CAPEX budget for installing advanced two-way meters is approximately $7,719,173. Distribution line repairs ensure a safe and reliable electric distribution system by maintaining the infrastructure and performing maintenance and restoration activities. This is an on-going program which includes all overhead and underground distribution system work for customer connections, emergency repairs, corrective/reactive work, customer restoration resulting from failures, compliance work to meet company standards of construction, reliability improvements for red circuits and work related to replacing items found during infrared inspections, and all minor storm work. Types of work include, pole replacements, NESC adjustments, cable faults, equipment failure, and damage to electric system plant. The source of this work comes from customer requests, trouble calls, outages, emergency response, damage to electric infrastructure, preventive maintenance inspections and field inspections to meet standards and compliance. The 2026 CAPEX budget for distribution line repairs is approximately $15,029,646. The programs that can be clearly categorized within the five principal elements are as follows: 37
  10. Page 38 of 176

    03/31/2026 Docket No. 86-12-03 A. New Customers Added UI is obligated to connect all customers within its franchise area to the electric distribution system in accordance with specific Terms & Conditions, Construction Standards, the National Electrical Safety Code (NESC), UI’s Guidebook of Requirements for Electric Service, policies, and procedures, etc. as approved by the Connecticut Public Utilities Regulatory Authority (PURA). This is an annual blanket program covering hundreds of individual customer related service requests for a given year. Construction work for services to commercial & industrial customers supplied by either overhead or underground powerlines for new, increase, replacement, removal, or demolition electric services. Each individual customer request is a unique project which has its own design scope of work, schedule, and cost. The scope of the job can include distribution primary system upgrades to serve the new customer by installing, new poles, transformers, primary wires, and other system equipment. The average cost from the last three years for this program has been used to determine the high-level cost estimate. The COVID years showed a decline in industrial and commercial development activity between 2020 and 2023. However, starting in 2024, the Company has seen a rebound in such development, especially in the downtown Bridgeport and New Haven areas (averaging ~$7m per year after CIAC). The Company’s current forecast reflects the planned project cost for known projects and provides a level of funding for future ones. The 2026 budget for New Customer installations is approximately $6,770,000. The planned P26 budget amount is actually around $9.52M. This amount is being reduced by about $2.755M, as offsets are being provided to four specific projects under this category. These customer projects were originally planned to be completed by the end of 2025 but are now rolling into 2026. The following projects are: • 19 Elm St - New Network Vault ($855k) • 300 State St - New Customer Service ($1.03M) • 855 Main St Bridgeport - Office to Condo ($219k) • Steelpointe Harbor - New Residential/Retail ($651k) i. Residential Line UI has an obligation to serve all customers within its franchise area. This project is required for new customer connections. This includes service work for temporary and permanent construction (new, increases, replacements, removals, and demolitions). The work is required to satisfy customer needs to purchase new or additional power for their consumption. 38

Text of UI-Attachment 2.pdf

Extracted from the file · 108 pages · 171,300 characters

Text of UI-Attachment 3.pdf

Extracted from the file · 79 pages · 105,929 characters

Words on different pagesRead the text of UI-Attachment 3.pdf

Text of UI-Attachment 4a.pdf

Extracted from the file · 60 pages · 136,974 characters

Text of UI-Attachment 4b.pdf

Extracted from the file · 32 pages · 73,024 characters

Text of UI-Attachment 5.pdf

Extracted from the file · 10 pages · 12,154 characters

Words on different pagesRead the text of UI-Attachment 5.pdf

Text of UI-Attachment 6.pdf

Extracted from the file · 29 pages · 55,721 characters

Words on different pagesRead the text of UI-Attachment 6.pdf

Text of UI-Attachment 7.pdf

Extracted from the file · 33 pages · 83,950 characters

Words on different pagesRead the text of UI-Attachment 7.pdf

Text of UI-Attachment 9.pdf

Extracted from the file · 14 pages · 33,843 characters

Words on different pagesRead the text of UI-Attachment 9.pdf

Text of UI-Attachment 11.pdf

Extracted from the file · 4 pages · 13,890 characters

Text of UI-Attachment 12.pdf

Extracted from the file · 36 pages, 2 without text · 106,019 characters

As listed on the current system

Compliance Filings, 10/01/2026 [26-08-07] Order No.No 4 in docket 17-12-03RE05 / Eversource Energy /

This filing on the current system (opens in a new tab)