Skip to main content

A prototype public docket site for the Connecticut Public Utilities Regulatory Authority

Utility Dockets and Filings

Compliance Filing

Compliance Filing, Order No. No

Compliance filingFiled by Eversource Energy24 files
Part of docket 26-08-07Open
  • Electric
Innovative Energy Solutions Program Cycle 5

Files24

Search terms highlighted
Eversource rate increase is on 5 pages across 2 files of the text below, highlighted. Go to the first matchClear highlighting
Words on different pages
2 pages match
Words on different pages

Text of ES-Attachment 2b 2026 TDRP-Appendix 8.pdf

Extracted from the file · 23 pages · 37,559 characters

Text of ES-Attachment 2b 2026 TDRP-Appendix 8.xlsx

Sheet names, column headings and text cells; numbers left out

Text of ES-Attachment 3.pdf

Extracted from the file · 1 page · 7,205 characters

Text of ES-Attachment 3.xlsx

Sheet names, column headings and text cells; numbers left out

Text of ES-Attachment 4.pdf

Extracted from the file · 44 pages · 108,591 characters

Text of ES-Attachment 4.xlsx

Sheet names, column headings and text cells; numbers left out

Text of ES-Attachment 5.pdf

Extracted from the file · 30 pages · 79,263 characters

Words on different pagesRead the text of ES-Attachment 5.pdf

Text of ES-Attachment 1.xlsx

Sheet names, column headings and text cells; numbers left out · first 300,000 characters

Text of ES-Attachment 1.xlsx

Sheet names, column headings and text cells; numbers left out · first 300,000 characters

Words on different pages
  1. Page 34 of 176

    03/31/2026 Docket No. 86-12-03 cycle; preserving the clearances where the UPZ Spec has already been applied; completing approximately 60% of the remining single phase circuit miles; and maintaining a total annual cost that is consistent with the approved expenditure levels. In Docket No. 24-10-04 the Authority subsequently determined the Company’s UPZ plan complied with direction given in the 22-08-08 Decision. Motion No.5 Ruling, Oct. 27, 2023, Docket No. 23-08-09, Annual Electric Distribution Company and Reliability and Resiliency Framework Review. The major components of UI’s proposed program are: 1. Utility Protection Zone Specification, (UPZ), is UI’s storm resiliency tree work specification, creating an eight-foot side clearance ground to sky, retaining desirable low height or ornamental trees within the zone or those that are planted under the Right Tree – Right Place program. Additionally, the Company identifies and removes whole or parts of hazardous trees from outside of the zone that could fall causing damage to utility infrastructure, facilities, or equipment. 2. Utility Protection Zone Maintenance (UPZM) maintains the previously established UPZ, or clearance within the rectangular area extending horizontally for a distance of eight feet from any outermost primary electrical conductor. Additionally, removal in whole or in part of hazardous trees that could fall from inside or outside of the zone causing damage to utility infrastructure, facilities or equipment. 3. UI documents and tracks all objections, requests for modification and decisions made by municipal tree wardens and the State Department of Transportation through the full execution of Public Act 14-151 that cause nonconformities, or areas where UI is not able to meet these specifications within and outside of the Utility Protection Zone (UPZ). Instances of outages caused by nonconforming trees will be documented and considered a reportable performance attribute. In 2025, tree contact incidents continue as a significant cause of customer outages in terms of the number of customers impacted. For 2025, tree contact incidents accounted for 17.2% of the outages within the Distribution System subcategory. The average of tree contact incidents as a percentage of the Distribution System subcategory during previous years, (2021-2024) totals 23.7%. Excluding transformer failures which are not a major source of customer minutes interrupted, equipment failures on the overhead system for 2025, as a percentage of the Distribution System subcategory, (28.5%), as in previous years, (24%), continue as a significant contributor to customer minutes interrupted. UI recognizes this situation, and is cautious in its selection of new equipment, so that it selects durable equipment and material to construct and maintain its overhead 34
  2. Page 35 of 176

    03/31/2026 Docket No. 86-12-03 and underground distribution system. UI has taken steps to analyze assets throughout their life cycle. One such analysis is the periodic in-service inspection of equipment to determine where the assets reside on their life cycle curves. This aids in making prudent asset replacement and/or rehabilitation decisions before customer reliability is impacted. Also, UI analyzes certain equipment failures to determine what type of equipment has a significant failure rate and is negatively impacting customer reliability. Referring to Appendix 11, “Five-Year Outage by Cause Summary (excluding major storms),” a comparison of 2025 data with previous years’ data (2021 - 2024) reveals the following: • Distribution system outages, defined as all outages other than Transmission/Power Supply, Customer Caused, Scheduled/Prearranged, or Major Storm, historically account for the majority of customer interruptions and customer minutes of interruption. • Within the distribution system subset, tree-related incidents, wildlife contacts, and failure of overhead equipment continue to comprise the majority of outage events. 35
  3. Page 36 of 176

    03/31/2026 Docket No. 86-12-03 VII. Reliability Improvement Programs and Budget Reliability programs are deterministic / reactive or probabilistic / proactive in nature, or a combination of both. Deterministic or reactive programs are designed to address circuit reliability or customer reliability outlier performance. Probabilistic or proactive programs are designed to prevent circuit or customer reliability performance from becoming an outlier. UI's policy is to design all distribution systems to meet the Company's Reliability Criteria (DEG 80). Each project is analyzed to determine what features (for example, tree-wire, buried cable, line reclosers, sectionalizing switches, lightning arresters, additional fusing, wildlife protection, etc.) are necessary to produce the desired level of reliability. Repair time and circuit backup requirements are analyzed such that rapid service restoration is possible through switching and sectionalizing to minimize the extent of an actual outage. Construction design standards provide additional details of how reliability is incorporated as a part of every project. This principal element is probabilistic in nature. Enhancements to the existing distribution system are based on both deterministic and probabilistic performance. In addition to the design of reliability into the systems themselves, UI reliability programs consist of five principal elements. Some programs significantly overlap the principal element types, such as: Installation of advanced two-way meters is exceeding current budgets for meter purchases. Meter exchanges are utilized for aging meters (meters greater than 20 years old and fully depreciated), power outage applications (Two-Meters per Transformer), Disconnect for Non-Payment (DNP), Get Customer Name (GCN) and Move in/Move Out orders (performs remote connect/disconnect activities without rolling a vehicle), estimates/consecutive estimate meter replacements (current population of one-way meters 14 years old and beginning to show signs of failure) and general exchanges to enhance the operation of the two-way network and customer service expectations. This is a customer facing activity which provides service to customers where accurately functioning meters is critical. L&G will stop supporting AMR meters by the end of 2026. Based on historical data and projected deployment strategy the 2026 scope for this project is as follows: • New Customers: This is a reactive program that has been consistently deploying ~3,500 units yearly and a similar figure is expected for 2026. • Defective Equipment: Reactive program anticipating ~4,500 failures per year based on forecast. • AMR/AMI Program: Plan to replace ~13,050 AMR meters in this category in 2026. • Solar/DG: UI saw ~3,000 solar requests in 2025, but due to the increasing volume of DG requests, the estimates have increased to around ~3,500 requests for 2026. 36
  4. Page 37 of 176

    03/31/2026 Docket No. 86-12-03 Scope New Customer Defective Equipment AMR/AMI Solar/DG Load Ctrl Adaptor 2026 Units 3,500 4,500 13,050 3,500 0 Unit Price $287.37 $325.22 $325.22 $287.37 $447.72 Total $1M $1.5M $4.2M $1M - The 2026 CAPEX budget for installing advanced two-way meters is approximately $7,719,173. Distribution line repairs ensure a safe and reliable electric distribution system by maintaining the infrastructure and performing maintenance and restoration activities. This is an on-going program which includes all overhead and underground distribution system work for customer connections, emergency repairs, corrective/reactive work, customer restoration resulting from failures, compliance work to meet company standards of construction, reliability improvements for red circuits and work related to replacing items found during infrared inspections, and all minor storm work. Types of work include, pole replacements, NESC adjustments, cable faults, equipment failure, and damage to electric system plant. The source of this work comes from customer requests, trouble calls, outages, emergency response, damage to electric infrastructure, preventive maintenance inspections and field inspections to meet standards and compliance. The 2026 CAPEX budget for distribution line repairs is approximately $15,029,646. The programs that can be clearly categorized within the five principal elements are as follows: 37
  5. Page 38 of 176

    03/31/2026 Docket No. 86-12-03 A. New Customers Added UI is obligated to connect all customers within its franchise area to the electric distribution system in accordance with specific Terms & Conditions, Construction Standards, the National Electrical Safety Code (NESC), UI’s Guidebook of Requirements for Electric Service, policies, and procedures, etc. as approved by the Connecticut Public Utilities Regulatory Authority (PURA). This is an annual blanket program covering hundreds of individual customer related service requests for a given year. Construction work for services to commercial & industrial customers supplied by either overhead or underground powerlines for new, increase, replacement, removal, or demolition electric services. Each individual customer request is a unique project which has its own design scope of work, schedule, and cost. The scope of the job can include distribution primary system upgrades to serve the new customer by installing, new poles, transformers, primary wires, and other system equipment. The average cost from the last three years for this program has been used to determine the high-level cost estimate. The COVID years showed a decline in industrial and commercial development activity between 2020 and 2023. However, starting in 2024, the Company has seen a rebound in such development, especially in the downtown Bridgeport and New Haven areas (averaging ~$7m per year after CIAC). The Company’s current forecast reflects the planned project cost for known projects and provides a level of funding for future ones. The 2026 budget for New Customer installations is approximately $6,770,000. The planned P26 budget amount is actually around $9.52M. This amount is being reduced by about $2.755M, as offsets are being provided to four specific projects under this category. These customer projects were originally planned to be completed by the end of 2025 but are now rolling into 2026. The following projects are: • 19 Elm St - New Network Vault ($855k) • 300 State St - New Customer Service ($1.03M) • 855 Main St Bridgeport - Office to Condo ($219k) • Steelpointe Harbor - New Residential/Retail ($651k) i. Residential Line UI has an obligation to serve all customers within its franchise area. This project is required for new customer connections. This includes service work for temporary and permanent construction (new, increases, replacements, removals, and demolitions). The work is required to satisfy customer needs to purchase new or additional power for their consumption. 38
  6. Page 39 of 176

    03/31/2026 Docket No. 86-12-03 This is an on-going program for residential overhead and underground new services, underground residential cable repairs, rebuilds, secondary line extension, initial installation of equipment for every subdivision on-going program for commercial and residential overhead and underground new services, underground residential cable repairs, rebuilds, secondary line extension, initial installation of equipment for every subdivision (single phase or multiple phases). The scope, designs, estimates and construction is based on customer requests that come in throughout the year. This includes new residential service for 3-phase primary overhead or underground, single premise which would be for a multi-unit apartment building with separate metering, requiring a 3-phase transformer. This would include distribution primary system upgrades to serve this new customer. The scope of the construction may include installing new poles, transformers, and primary/secondary/service wires. Additionally, the scope would include interconnecting with a neighboring Utility. The 2026 budget for Residential Line is approximately $4,507,719. ii. Street Lights This is an on-going program to install/replace/relocate/remove existing customer private area lighting. The scope includes lights that are fed from overhead and underground, secondary and service wire work, poles and light heads and civil work for bases and conduit and miscellaneous hardware. The sources of the work come from customer requests to install new lighting, repair damaged lighting and from routine inspections. The 2026 scope will include any new requests or notifications of damaged lights that come in throughout the year. The Company ensures that equipment is installed to meet customer commitment and ensuring it is maintained to provide the service the customer is paying for. Customer satisfaction. State Statutes require utilities to repair 'Light Out' calls within 3 business days. UI receives notifications for Light-Out and schedules the next day through mobility. The 2026 budget for Street Light CAP is approximately $1,954,265. 39
  7. Page 40 of 176

    03/31/2026 Docket No. 86-12-03 B. Infrastructure Replacement i. Bulk Substation Replacement UI currently operates 25 – 115/13.8 kV substations to deliver electricity to its customers. These substations transform power from the 115-kV transmission system down to the 13.8 kV level to be distributed on utility poles. The performance of a single substation can impact up to 10,000 to 20,000 customers. Many of the substations are nearing the end of their useful life. In 2025, a large number of UI’s 115/13.8 kV substations were forty years old or older. This concentration of assets in the fourth quartile of their useful life represents a significant risk to the Company and its customers. It takes four years or longer to bring a new 115/13.8 kV substation project from planning to design, siting approval and construction and requires many engineering, project management, and construction resources to complete. As a result, the Company’s ability to site and build 115/13.8 kV substations is finite. The Company continues a proactive replacement program to address this situation, through component replacement programs or entire substation rebuilds if warranted. The Pequonnock Substation was placed into service in 1956 and is located in Bridgeport, CT immediately adjacent to the Long Island Sound. The substation serves approximately 8,240 customers. The site experienced flooding one to two feet above the yard elevation during Tropical Storm Irene and approximately 10 feet NAVD 88 (North American Vertical Datum of 1988) during Superstorm Sandy or within inches of the control room floor. Along with the flooding concerns, there were several known asset condition deficiencies at this site. The Pequonnock project called for the rebuilding of the existing substation further inland. The project is expected to be completed this year. A set of comprehensive evaluations were performed to determine the future viability of the Old Town Substation. The substation serves approximately 18,000 customers. The Full Replacement solution was selected based on a review of all of the factors associated with maintaining adequate, safe and reliable service to the Old Town distribution area. This solution is superior in the key areas of construction outage requirements, minimization of construction hazards, future expansion capabilities, overall project cost as well as in the area of life of equipment. The life of equipment concerns for Old Town Substation stemmed from the age of the station. The work for this project is still ongoing. The 2026 budget for the Old Town Substation Rebuild is approximately $11,608,131 ($10,384,472 Transmission + $1,223,659 Distribution). 40
  8. Page 41 of 176

    03/31/2026 Docket No. 86-12-03 ii. Low Voltage Distribution Substation Removal Low Voltage Distribution substations originated at the dawn of the utility industry in the early 1900’s. These substations transform the voltage down from 13.8 kV to the 4.16 kV or 2.4 kV voltages that were predominantly the distribution voltages during the 1920s, 1930s and 1940s. The program objective is to complete the removal of service and retirement of assets associated with all 4.16 kV and 2.4 kV substations on the distribution system due to the age of the equipment and the inability to maintain this obsolete equipment. The age range of these substations is 50-70 years old. Removal of low voltage (4.16kV) substations is accomplished through either total conversion of the distribution infrastructure supported by the low substation to 13.8kV or through partial conversion to 13.8kV and the utilization of Step Down Banks where there is significant remaining life in the distribution infrastructure. The Low Voltage Substation Removal program was developed as a result of a formal condition assessment of all low voltage substations in 2006. The main concerns resulting from this assessment were: • Potential safety hazards associated with the risk of failure of equipment that has exceeded its useful life • The risk of long duration power outages related to obsolete or end of useful life substation equipment • Continued maintenance required to keep obsolete substation equipment operational This program mitigates the risks associated with age, obsolescence, inadequate maintenance practices, and exposure to adverse/harsh service conditions. Harsh service conditions or inadequate maintenance practices can accelerate the aging process, and can cause failures to occur. Obsolescence can result in long lead times, high costs, or complete unavailability for repair parts, and could result in long outages if equipment fails. From the perspective of operability and maintainability, in some cases, the condition of the equipment and the clearances around it can make access to the equipment difficult and can raise potential safety concerns for the Company’s field personnel. Overall, this program helps to maintain reliability and reduces hazards to our employees and the public by reducing the risk of failure of equipment that has exceeded its useful life. Due to equipment condition, obsolescence, and maintenance issues, the Company has been implementing the removal of distribution substations for many years. Originally, the Company had over 100 of these substations in service. Whitney Ave was the last one remaining and was finally de-energized in 2025. This was originally slated to take place in 2026 due to capital budget constraints. The increasing risks and dangers that the substation equipment posed to UI crews increased its prioritization. The Low Voltage Distribution Substation Removal program is now complete. 41
  9. Page 42 of 176

    03/31/2026 Docket No. 86-12-03 iii. Splicing Chambers The Company owns and maintains over 3,000 underground splicing chambers, the vast majority of which are located in public roads. Fifteen hundred of these splicing chambers are greater than 60 years old including many constructed with roofs supported by steel railroad rails that are susceptible to corrosion. Additionally, prior to the 1950s, these structures were typically constructed with dimensions that do not meet current working clearance requirements. The Splice Chamber Rebuild Program replaces underground cable splicing structures before they fail which could cause bodily injury or an extended system outage. By prioritizing these structures based on an annual inspection program, a systematic approach can be taken to design, procure, and construct the replacement structures before failure. Replaced structures comply with the latest version of the NESC and the latest advances in materials. The pace of the program is intended to remediate the remaining steel rail structures over the next 20-30 years. These projects are costly, complicated and impactful to the local communities because they impact busy urban roadways. The Company’s strategy is to mitigate these risk steadily over a long period of time to avoid lengthy widespread outages and public and employee safety impacts. Maintenance inspections for every splice chamber are performed on a 10-year basis. Every year 300 are inspected by this program and another 100 are inspected as part of other inspections. Depending on the deficiency and severity a complete replacement or partial remediation will be required. Structures that have only a deteriorated roof require only a roof replacement. Splice chambers that have significant structural deterioration present in the walls or floor or are not in compliance with the latest version of the NESC for horizontal working clearance must be wholly replaced. UI has inspected all of its splicing chambers. Inspections determined the need to remediate almost 500 chambers and as of the end of 2025 approximately 481 splicing chambers (an increase of 0) have been remediated. For 2026, UI does not have plans for any complete splice chamber replacements. The 2026 budget is planned to address three emergency roof replacements listed below, and to develop the plan for 2027. The three proposed locations are: • SC 91 at 49 Cannon St, Bridgeport • SC's 754 and 753 on Willow St, New Haven The estimated cost for Splicing Chamber Inspections in 2026 is approximately $90,000. The 2026 budget for Splicing Chamber Remediation is approximately $876,637. 42
  10. Page 43 of 176

    03/31/2026 Docket No. 86-12-03 iv. Utility Poles UI is the custodian of roughly 147,000 poles in the service territory. This program replaces deteriorated poles identified in the UI maintenance pole inspection program that do not meet established NESC standards for the amount of solid wood remaining at the base of the pole. Additionally, this program also replaces poles identified by visual inspections or resulting from field visits by UI field personnel. The volume of pole replacements is forecast based on the planned number of poles to be inspected multiplied by the historical average failure rate per year (typically 3.1%). This program is necessary to achieve compliance with NESC requirements, which maintains safety for the public and utility workers. Additionally, the UI distribution system reliability and resiliency are improved, as poles are replaced based on current standards and as pole loading analysis determines (per the NESC Northeast NESC wind and radial ice modeling parameters). In 2025, approximately 34 poles were replaced. A total of 26 were replaced as part of the Pole Management Program and an additional 8 Non-Program Poles were replaced as well. The inspections that were conducted in 2023, 2024 and 2025 have produced a reject rate of 1.10% which equates to a backlog of 2023 (86 poles), 2024 (87 poles) and 2025 (98 poles), totaling 271 poles. The rejects identified have inspection ratings varying in severity. In 2026, the Company plans to complete a portion of the backlog of pole replacements originating from 2023-2025. The replacements will be prioritized based on the severity rating from the inspections. For 2026, approximately 138 poles will be replaced based on the severity rating for poles identified from the 2023-2025 inspections. The estimate includes 102 single phase pole replacements at $8,394/pole and 36 three phase pole replacements at $13,440/pole. The estimated cost of these replacements is approximately $1.34M. The inspection program in 2026 will identify ~20 emergency priority rejects which will require around an additional $225k. In 2026, in addition to the ground line deteriorated pole inspections, the Company will also be commencing an overhead inspection cycle, and it is expected that investment will be required to remediate critical deficiencies such as cracked pole tops, primary cable off pins, etc. Additional funding may be required for these items and will be monitored as the overhead inspections are completed. The pole replacement program budget for 2026 is approximately $1,550,574. 43

Text of UI-Attachment 2.pdf

Extracted from the file · 108 pages · 171,300 characters

Text of UI-Attachment 3.pdf

Extracted from the file · 79 pages · 105,929 characters

Words on different pagesRead the text of UI-Attachment 3.pdf

Text of UI-Attachment 4a.pdf

Extracted from the file · 60 pages · 136,974 characters

Text of UI-Attachment 4b.pdf

Extracted from the file · 32 pages · 73,024 characters

Text of UI-Attachment 5.pdf

Extracted from the file · 10 pages · 12,154 characters

Words on different pagesRead the text of UI-Attachment 5.pdf

Text of UI-Attachment 6.pdf

Extracted from the file · 29 pages · 55,721 characters

Words on different pagesRead the text of UI-Attachment 6.pdf

Text of UI-Attachment 7.pdf

Extracted from the file · 33 pages · 83,950 characters

Words on different pagesRead the text of UI-Attachment 7.pdf

Text of UI-Attachment 9.pdf

Extracted from the file · 14 pages · 33,843 characters

Words on different pagesRead the text of UI-Attachment 9.pdf

Text of UI-Attachment 11.pdf

Extracted from the file · 4 pages · 13,890 characters

Text of UI-Attachment 12.pdf

Extracted from the file · 36 pages, 2 without text · 106,019 characters

As listed on the current system

Compliance Filings, 10/01/2026 [26-08-07] Order No.No 4 in docket 17-12-03RE05 / Eversource Energy /

This filing on the current system (opens in a new tab)