Skip to main content

A prototype public docket site for the Connecticut Public Utilities Regulatory Authority

Utility Dockets and Filings

Compliance Filing

Compliance Filing, Order No. No

Compliance filingFiled by Eversource Energy24 files
Part of docket 26-08-07Open
  • Electric
Innovative Energy Solutions Program Cycle 5

Files24

Search terms highlighted
Eversource rate increase is on 5 pages across 2 files of the text below, highlighted. Go to the first matchClear highlighting
Words on different pages
2 pages match
Words on different pages

Text of ES-Attachment 2b 2026 TDRP-Appendix 8.pdf

Extracted from the file · 23 pages · 37,559 characters

Text of ES-Attachment 2b 2026 TDRP-Appendix 8.xlsx

Sheet names, column headings and text cells; numbers left out

Text of ES-Attachment 3.pdf

Extracted from the file · 1 page · 7,205 characters

Text of ES-Attachment 3.xlsx

Sheet names, column headings and text cells; numbers left out

Text of ES-Attachment 4.pdf

Extracted from the file · 44 pages · 108,591 characters

Text of ES-Attachment 4.xlsx

Sheet names, column headings and text cells; numbers left out

Text of ES-Attachment 5.pdf

Extracted from the file · 30 pages · 79,263 characters

Words on different pagesRead the text of ES-Attachment 5.pdf

Text of ES-Attachment 1.xlsx

Sheet names, column headings and text cells; numbers left out · first 300,000 characters

Text of ES-Attachment 1.xlsx

Sheet names, column headings and text cells; numbers left out · first 300,000 characters

Text of UI-Attachment 1.pdf

Extracted from the file · 176 pages · 247,894 characters

Words on different pagesRead the text of UI-Attachment 1.pdf

Text of UI-Attachment 2.pdf

Extracted from the file · 108 pages · 171,300 characters

Text of UI-Attachment 3.pdf

Extracted from the file · 79 pages · 105,929 characters

Words on different pagesRead the text of UI-Attachment 3.pdf
Words on different pages
  1. Page 5 of 60

    The Connecticut Light & Power Company and The United Illuminating Company look forward to working with Generators to facilitate a safe, reliable and successful Interconnection in accordance with these Guidelines. 1.2 Executive Summary Interconnection Process for Generators smaller than 20 MW: These Interconnection Guidelines provide general guidance for interconnections of Generating Facilities, also known as Distributed Energy Resources (DERs), that are smaller than 20 MW. DER interconnections vary significantly in complexity depending on the generator size, location, and customer requirements; consequently, it is not practical to expect that these Guidelines should always be rigidly observed for all interconnections. The Electric Distribution Company’s (EDC’s) Facilitator will work closely with the Generator to help achieve a successful interconnection. This Executive Summary provides a quick overview of the Interconnection process and is not meant to replace the more detailed description of requirements contained in the remainder of these Interconnection Guidelines. These Guidelines only apply to Generating Facilities intending to interconnect onto the EDC distribution system. Any Generator project intending to interconnect onto the transmission system will be required to follow the most recent Federal Energy Regulatory Commission (FERC) guidelines and processes, which are administered by the Independent System Operator – New England, Inc. (ISO-NE). State Jurisdictional Interconnections: DERs that intend to interconnect directly to the distribution level of the EPS will fall under the State of Connecticut Public Utility Regulatory Authority (PURA) jurisdiction, and are administered by the EDC. The state-jurisdictional Interconnection process begins when a Generator submits an application to the EDC, which includes supporting documentation such as electrical line drawings, site plans, wiring schematics, planned operational schedules and procedures, etc. The EDC will review the application and submittals and work with the customer to resolve any discrepancy and obtain any missing information. The EDC will then conclude the initial application review within fifteen (15) Business Days and submit the results to the Generator. Upon completion of the application review, which could include multiple design revisions based on feedback, if an Interconnection Study (Feasibility, Impact and/or Facility) is required, the EDC will provide a Study Agreement and an estimate of the costs to complete the Study. The EDC will request that the Generator execute the Agreement within thirty (30) Business Days and pay the estimated cost of the Study. Some or all of the Studies may be required, and the EDC will work with the Generator to identify the required Studies. Each Study will require its own Study Agreement. Once the study agreement is signed and all outstanding milestone deliverables are received, the EDC may notify the Generator when the study begins, along with providing an expected timeframe for completion. This information may also be included in the respective study agreement. Distribution Studies usually require approximately thirty to sixty (30 to 60) Business Days for completion of each Study and may include a Feasibility Study, an Impact Study and a 5
  2. Page 6 of 60

    Facility Study. Upon completion of each respective Distribution Study, the EDC will share the applicable results with the Generator. Transmission studies may be required for some Interconnections even if the Generator Interconnection falls under state rules. Transmission studies are more complex and must be conducted in accordance with applicable ISO-NE rules and procedures. These Guidelines do not address the transmission studies process required by ISO-NE. The Generator may obtain guidance from the ISO-NE Tariff, Schedule 22 and 23 and Section I.3.9. However, during the Interconnection process, the EDC will provide guidance including information concerning the scope, duration and cost of the transmission studies. At the conclusion of the studies including any Transmission studies or additional requirements from ISO-NE, the EDC will submit an Interconnection Agreement (IA) to the Generator with payment milestones included within the Agreement. In order to move forward with the execution of the project, the Generator will be required to sign the IA within thirty (30) Business Days and comply with payment milestones specified within the Agreement. At the conclusion of the project, the EDC will reconcile actual vs. estimated cost and reimburse or bill the Generator accordingly. It is important to note that these Guidelines do not consider Transmission upgrades or delays due to such upgrades. Once the upgrades are implemented, the following steps will be required to allow the Generator to interconnect to the EDC. • Provide Proof of Municipal approval for the Generating Facility. • Request the EDC to witness the commissioning test. Within ten (10) Business Days of the receipt of the Municipal approval, the EDC will aim to schedule and perform any required meter work and witness the commissioning test. If the EDC is unable to schedule and complete the required work within the ten (10) Business Day timeframe, the EDC will communicate the reason for such delay promptly and provide an expected schedule and plan of action to complete the work. Following successful completion of that test, the EDC will send a final approval authorizing the interconnection to the Generator. Additional Process Steps for compliance with ISO-NE Planning Procedure Regardless of the Interconnection jurisdiction, each Generator wishing to interconnect a Generating Facility must comply with the ISO-NE Planning Procedure 5 (PP5), which is the procedure for a Proposed Plan Application (PPA) under Section I.3.9 of the ISO-NE Tariff. This process must be completed before the Generator may Interconnect such Generating Facility. It is important to note that the PPA process is an ISO-NE requirement, even if the Interconnection of such facility falls under state jurisdiction. From timeto-time ISO-NE has made changes to the ISO-NE Planning Procedure which are out of EDC control and the details of which are not included in this document. The EDCs will post the most recent ISO-NE requirements on their respective web pages as they become available. 6
  3. Page 7 of 60

    While the Generator is ultimately responsible for the PPA application and the associated data to be submitted to ISO-NE, the EDC will provide support to the Generator if the Generator is not a “Governance Participant” (as such term is defined in the Participants Agreement; among ISO-NE and the New England Power Pool) at the time the PPA is submitted to the EDC. Typically, the EDC will file the PPA on behalf of such non- Governance Participant Generator. Additionally, the EDC will represent such Generator in ISO-NE proceedings in accordance with the current ISO-NE rules; provided, however, that such Generator shall remain solely responsible for, among other things: (a) the completion of the PPA and the accuracy of the information contained therein, (b) the advance payment based on a non-binding good faith estimate of all costs in connection with any required Transmission System Impact Study, and (c) the payment of all costs associated with transmission upgrades identified through the ISO-NE approval process. Each non-Governance Participant Generator wishing to Interconnect a Generating Facility must read and be familiar with PP5, Section I.3.9 of the ISO- NE Tariff and other relevant ISO-NE guidance on the PPA process. Further, such non- Governance Participant Generator can communicate directly with ISO-NE to seek assistance concerning the applicable PPA requirements and associated issues. For non-Governance Participant Generators, the EDC notifies ISO-NE of receipt of the Interconnection Application, under current ISO-NE practice. Further, the EDC submits a complete copy of the PPA application to ISO-NE in order to secure an ISO-NE queue position. An ISO-NE queue position will not be established by ISO-NE until all the data required by ISONE is complete. Governance Participants are responsible for filing their own PPA with the ISO-NE and representing themselves in connection with all ISO-NE proceedings. Interconnection Process for Generators greater than 20 MW: The time frames and processes described in these guidelines are applicable to Generating Facilities smaller than 20 MW and represent the majority of Distribution interconnections. Generating Facilities larger than 20 MW are only rarely interconnect to the EPS. However, from time to time the EDC will receive requests for Interconnecting Generating Facilities greater than 20 MW seeking an interconnection to the EPS. When this situation occurs and provided that an interconnection to the EPS is feasible and appropriate, the EDC will use these Guidelines; however, the time frames to conduct the Application Review and Studies will be adjusted in accordance with the ISO-NE Tariff, Schedule 22. 7
  4. Page 8 of 60

    2 Application Requirements and Interconnection Request 2.1 Interconnection Request Prior to submitting an Interconnection Application, customers should refer to the hosting capacity maps located on the respective EDC websites to review project viability. An Interconnection Request must be submitted through the respective EDC’s online application portal. A processing fee is required with each Interconnection Request. The applicable fee is as follows: Process Generator Applicability Fast Track (1) 0-2 MW, unless Generating Facility does not qualify for the Fast Track process, or (2) Is 25 kW or less, certified but did not pass the 25 kW or Less screen(s). (1) is larger than 2 MW, (2) is 2 MW or less and is not certified, or (3) is 2 MW or less and is certified but did not pass the Fast Track Process. Study Application Study Fee Fee $500 Actual Cost $1000 Actual Cost Table 1 Application Fees a) The Interconnecting EDC shall date- and timestamp the Interconnection Request upon receipt. Such date and timestamp shall be used for the purposes of the timetables set forth in these Guidelines. b) Within three (3) Business Days of the receipt of the Interconnection Request, the Interconnecting EDC shall confirm receipt of such Interconnection Request using the form attached hereto as Attachment II. c) Within ten (10) Business Days of the receipt of the Interconnection Request, the Interconnecting EDC shall notify the Generator if such Interconnection Request is incomplete using the form attached hereto as Attachment III. The Generator will have fifteen (15) Business Days from the date of such notice to submit the listed information or to request an extension of time to provide such information. If the Generator does not provide the listed information or a request for an extension of time within such fifteen (15) day period, then the Interconnection Request will be deemed withdrawn, and such deemed 8
  5. Page 9 of 60

    withdrawal shall be subject to Section 3.8. An Interconnection Request will be deemed complete upon receipt of the listed information by the Interconnecting EDC. 2.2 Insurance Requirements Generators interconnecting a Generating Facility to the EPS of an EDC shall maintain general liability insurance in the amounts set forth in the following table, per Interconnection at all times during the Interconnection. Nameplate Rating* Less than 100 kW Minimum Liability Insurance Required $300,000 Greater than 100 kW to 1 MW $1,000,000 Greater than 1 MW to 5 MW $2,000,000 Greater than 5 MW $5,000,000 All Nameplate Ratings are based on aggregate generation at the site. Table 2 Liability Insurance General Liability: In connection with Generator’s performance of its duties and obligations under the Interconnection Agreement, Generator shall maintain, at all times during the Interconnection, general liability insurance with a combined single limit of not less than: Three hundred thousand dollars ($300,000) per occurrence and in the aggregate for bodily injury and/or property damage claims where the Gross Nameplate Rating of the Generators Facility is less than or equal to 100 kW. One million dollars ($1,000,000) per occurrence and in the aggregate for bodily injury and/or property damage claims where the gross nameplate rating of the Generators Facility is greater than 100 kW and less than or equal to 1 MW. Two million dollars ($2,000,000) per occurrence and in the aggregate for bodily injury and/or property damage claims where the gross nameplate rating of the Generators Facility is greater than 1 MW and less than or equal to 5 MW. Five million dollars ($5,000,000) per occurrence and in the aggregate for bodily injury and/or property damage claims where the gross nameplate rating of the Generators Facility is greater than 5 MW and less than or equal to 20 MW. 9
  6. Page 10 of 60

    Insurer Requirements and Endorsements All required insurance shall be carried by reputable insurers qualified to underwrite insurance in Connecticut. In addition, all insurance shall: (a) include the EDC as an additional insured for all Generating facilities greater than 1 MW; (b) contain a severability of interest clause or cross-liability clause; (c) provide that the EDC shall not incur liability to the insurance carrier for payment of premium for such insurance; and (c) provide for thirty (30) Calendar Days’ written notice to the EDC prior to cancellation, termination, or material change of such insurance. Evidence of Insurance Evidence of the insurance required shall state that coverage provided is primary and is not in excess of or contributing with any insurance or self-insurance maintained by the EDC. The Generator is responsible for providing the EDC with evidence of insurance in compliance with this Guideline on an annual basis. Prior to the EDC commencing work on system modifications, the Generator shall have its insurer furnish to the EDC certificates of insurance evidencing the insurance coverage required above. The Generator shall notify and send to the EDC a certificate of insurance for any policy written on a "claims-made" basis. The EDC may at its discretion require the Generator to maintain tail coverage for three years on all policies written on a "claimsmade" basis. All insurance certificates, statements of self insurance, endorsements, cancellations, terminations, alterations, and material changes of such insurance shall be issued and submitted to the appropriate EDC Facilitator. 2.3 Facility Security, Access and Contact Information Infrastructure Security The security of the electric system infrastructure is essential. FERC requires the EDCs, market participants, and Generating Facilities interconnected with an EDC’s EPS to comply with the recommendations offered by the National Infrastructure Advisory Council and best practice recommendations from NERC. All public utilities must meet basic standards for electric system infrastructure and operational security, including physical, operational, and cyber-security practices where required. Interconnection Requests will be reviewed in light of infrastructure security concerns. Emergency Reporting In accordance with Section 6.4.1 of the Interconnection Agreement, the EDC and the Generator shall each provide to the other (and shall update as necessary) a telephone number that can be used at all times to allow the other to report an emergency. 10
  7. Page 11 of 60

    Access to EDC Equipment and Facilities In accordance with Section 6.4.2 of the Interconnection Agreement, the Generator shall allow the EDC access to the EDC’s equipment and the EDC’s facilities located on the Generating Facility’s premises. Access to Isolation Device In accordance with Section 6.4.3 of the Interconnection Agreement, the EDC shall have access to the Isolation Device of the Generating Facility at all times. 2.4 Modification and Non-Material changes Any modification to machine data, equipment configuration or the Interconnection site not agreed to in writing by the Interconnecting EDC may be deemed a withdrawal of the Interconnection Request. In the event of a deemed withdrawal, the provisions of Section 2.7 shall apply. In cases when a reduction in size may avoid significant upgrades, and is proposed by the developer prior to the project application receiving Contingent Approval to Install (CATI), such modifications will not be considered Material modifications and will not impact the current project queue position. However, all project documentations including one lines, layout, and application in Power Clerk must be updated by the developer in order for the revised modification take effect, and may require additional technical analysis to be performed by the EDC. 2.5 Site Control Documentation evidencing site control must be submitted with the Interconnection Request. Site control may be demonstrated through: a) Ownership of, a leasehold interest in, or a right to develop a site for the purpose of constructing the Generating Facility. b) An irrevocable option to acquire any of the property rights set forth in Section 3.6.1; or c) An exclusivity or other business relationship between the Generator and an entity having the right to sell, lease, or grant the Generator the right to possess or occupy a site for such purpose; or d) Filed applications for required permits with respect to a site on Federal or State property. 2.6 Queue Position The Interconnecting EDC shall assign to each Interconnection Request a queue position based upon date of the date-stamp described in Section 2.1.a The queue position of each Interconnection Request will be used to determine the cost responsibility for any upgrades necessary to accommodate the Interconnection. The EDC shall maintain a single Distribution 11
  8. Page 12 of 60

    queue. 2.7 Withdrawal a) The Generator may withdraw its Interconnection Request at any time by written notice of such withdrawal to the Interconnecting EDC. b) In addition, if the Generator fails to adhere to all requirements of these Guidelines, subject to Section 2.7.c, the Interconnecting EDC shall deem the Interconnection Request to be withdrawn and shall provide written notice to the Generator of the deemed withdrawal and an explanation of the reasons for such deemed withdrawal. c) Upon receipt of such written notice, if the Generator wishes to dispute the withdrawal notice, the Generator shall have fifteen (15) Business Days in which to either respond with information or actions that cure the deficiency or to notify the Interconnecting EDC of its intent to pursue dispute resolution in accordance with Section 5.2. d) Withdrawal of an Interconnection Request shall result in the loss of queue position assigned to such Interconnection Request. e) If a Generator disputes such withdrawal and loss of queue position, then the Generator’s Interconnection Request shall be removed from the queue until such time that the outcome of the dispute restores its queue position. f) Within thirty (30) days following a withdrawal, a Generator that withdraws or is deemed to have withdrawn its Interconnection Request shall pay to the Interconnecting EDC and any Affected Parties all costs prudently incurred with respect to such Interconnection Request prior to the receipt of notices described Section 2.7.a or 2.7.b, as the case may be. g) A Generator who fails to pay all monies due pursuant to Section 2.7.f shall not be eligible to obtain any Interconnection Study reports or submit subsequent Interconnection Requests. 12
  9. Page 13 of 60

    3 Fast Track Process 3.1 Applicability The Fast Track Process is available to any Generator proposing to interconnect its Generating Facility with the Distribution System if (a) the proposed Generating Facility is 50 kW or less, certified, but did not pass the 50 kW or less screen(s) (b) the proposed Generating Facility is no larger than 2 MW and passes the technical screens associated with the Fast Track process, and (c) the proposed Generating Facility (i) meets the Codes and Standards and other certification requirements of these Guidelines or (ii) is determined to be safe to operate by the Interconnecting EDC, in its sole discretion. 3.2 Initial Review Within fifteen (15) Business Days after the Interconnecting EDC notifies the Generator it has received a complete Interconnection Request, the Interconnecting EDC shall perform an initial review using the screens set forth below, shall notify the Generator of the results, and include with the notification copies of the analysis and data underlying the determinations under the screens. DER Rating and Export Capabilities The technical evaluation will be conducted based on the name plate rating or the Maximum Export Capacity or Derated Name plate rating of the DER. Refer to section 4.2.8 in the Exhibit B Technical Requirements document for further guidance on and acceptable methods for export limitation. Consult with the applicable EDC on the specific acceptable options for formal equipment derating. These may include a recertification letter or memo from the equipment manufacturer, updating the physical nameplate affixed to the equipment, and/or other approved means. Screen Criteria The EDC will use the following criteria for performing screening evaluations of all proposed Generating Facilities greater than 50 kW and less than or equal to 2 MW: a) For Interconnection of a proposed Generating Facility, the aggregated nameplate generation capacity shall not exceed the nameplate rating of the service transformer for those Generating Facilities directly connected to the distribution transformer. b) For Interconnection of a proposed Generating Facility based to a radial distribution circuit, the aggregated generation including the proposed Generating Facility, on the circuit shall not exceed fifteen percent (15%) of the Line Section annual peak load as most recently measured at the substation. A line section is that portion of an Interconnecting EDC’s electric system connected to a customer bounded by automatic sectionalizing devices or the end of the distribution line. Alternatively, the EDC may use internal data and modeling tools for any proposed Generating Facility to determine if the screen passes. NOTE: EDC-approved methods of export limitation and equipment derating may 13
  10. Page 14 of 60

    be considered as acceptable means to pass this screen. Refer to section 4.2.8 in the Exhibit B Technical Requirements document for further guidance. c) For Interconnection of a proposed Generating Facility to the load side of Spot Network protectors, the proposed Generating Facility must utilize an inverter-based equipment package and, together with the aggregated other inverter-based generation, shall not exceed the lesser of five percent (5%) of a Spot Network's maximum load or 50 kW. d) For Interconnection of a proposed Generating Facility to the load side of an area network, the following screen will be conducted: a. The unit is a Certified Inverter-based generator or inverter based using a utility grade relay package exclusively in its design. b. The network primary feeders supplying the network to which the generation is attached are from the same electrical bus or normally tied buses. c. The maximum DG size will be limited to 50 kW at any location. A location is defined as any manhole or service box where the DG is connected to the network secondary system. This will ensure that no more than 50 kW of DG is located between the same set(s) of cable limiters. d. Total aggregate DG interconnected to an area network will be limited to 3% of the maximum network transformer connected kVA with the feeder supplying the largest number of network units out of service, or a maximum of 500 kW, whichever is less. e) The proposed Generating Facility, in aggregation with other generation on the distribution circuit, shall not contribute more than ten percent (10%) to the distribution circuit's maximum fault current at the point on the high voltage (primary) level nearest the proposed point of change of ownership. f) The proposed Generating Facility, in aggregation with other generation on the distribution circuit, shall not cause any distribution protective devices and equipment (including, but not limited to, substation breakers, fuse cutouts, load-break elbows, and line reclosers), or Generating Facility equipment on the EPS to exceed eighty-seven and one-half percent (87.5%) of the short circuit interrupting capability; nor shall the Interconnection be permitted for a circuit that already exceeds eighty-seven and one-half percent (87.5%) of the short circuit interrupting capability. g) The table below sets forth the type of Interconnection applicable to each type of primary distribution line. This screen criterion includes a review of the type of electrical service provided to the Generator, including line configuration and the transformer connection to limit the potential for creating over-voltages on the Interconnecting EDC’s EPS due to a loss of ground during the operating time of any anti-islanding function. 14

Text of UI-Attachment 4b.pdf

Extracted from the file · 32 pages · 73,024 characters

Text of UI-Attachment 5.pdf

Extracted from the file · 10 pages · 12,154 characters

Words on different pagesRead the text of UI-Attachment 5.pdf

Text of UI-Attachment 6.pdf

Extracted from the file · 29 pages · 55,721 characters

Words on different pagesRead the text of UI-Attachment 6.pdf

Text of UI-Attachment 7.pdf

Extracted from the file · 33 pages · 83,950 characters

Words on different pagesRead the text of UI-Attachment 7.pdf

Text of UI-Attachment 9.pdf

Extracted from the file · 14 pages · 33,843 characters

Words on different pagesRead the text of UI-Attachment 9.pdf

Text of UI-Attachment 11.pdf

Extracted from the file · 4 pages · 13,890 characters

Text of UI-Attachment 12.pdf

Extracted from the file · 36 pages, 2 without text · 106,019 characters

As listed on the current system

Compliance Filings, 10/01/2026 [26-08-07] Order No.No 4 in docket 17-12-03RE05 / Eversource Energy /

This filing on the current system (opens in a new tab)