Skip to main content

A prototype public docket site for the Connecticut Public Utilities Regulatory Authority

Utility Dockets and Filings

Compliance Filing

Compliance Filing, Order No. No

Compliance filingFiled by Eversource Energy24 files
Part of docket 26-08-07Open
  • Electric
Innovative Energy Solutions Program Cycle 5

Files24

Search terms highlighted
Eversource rate increase is on 5 pages across 2 files of the text below, highlighted. Go to the first matchClear highlighting
Words on different pages
2 pages match
Words on different pages

Text of ES-Attachment 2b 2026 TDRP-Appendix 8.pdf

Extracted from the file · 23 pages · 37,559 characters

Text of ES-Attachment 2b 2026 TDRP-Appendix 8.xlsx

Sheet names, column headings and text cells; numbers left out

Text of ES-Attachment 3.pdf

Extracted from the file · 1 page · 7,205 characters

Text of ES-Attachment 3.xlsx

Sheet names, column headings and text cells; numbers left out

Text of ES-Attachment 4.pdf

Extracted from the file · 44 pages · 108,591 characters

Text of ES-Attachment 4.xlsx

Sheet names, column headings and text cells; numbers left out

Text of ES-Attachment 5.pdf

Extracted from the file · 30 pages · 79,263 characters

Words on different pagesRead the text of ES-Attachment 5.pdf

Text of ES-Attachment 1.xlsx

Sheet names, column headings and text cells; numbers left out · first 300,000 characters

Text of ES-Attachment 1.xlsx

Sheet names, column headings and text cells; numbers left out · first 300,000 characters

Text of UI-Attachment 1.pdf

Extracted from the file · 176 pages · 247,894 characters

Words on different pagesRead the text of UI-Attachment 1.pdf

Text of UI-Attachment 2.pdf

Extracted from the file · 108 pages · 171,300 characters

Text of UI-Attachment 3.pdf

Extracted from the file · 79 pages · 105,929 characters

Words on different pagesRead the text of UI-Attachment 3.pdf

Text of UI-Attachment 4a.pdf

Extracted from the file · 60 pages · 136,974 characters

Words on different pages
  1. Page 13 of 32

    protection devices required at the generator. However, if a Generator meets certain requirements, the EDC may elect to waive the separate protection devices at the PCC. In order for the EDC to consider waiving the separate protection devices at the PCC all of the following conditions must be met (unless waived by the EDC): a. Total Generation Facility Capacity is less than 1MW. b. Generation Facility Capacity is less than 1/3 of its total minimum load. c. Generating Facility is designed as a net-import facility at all times (no power exported to EPS). d. Generator has interrupting and protection devices meeting all other requirements in this document. 1.14.14 Voltage relays that can be connected directly to the Generating Facility’s line voltage without a voltage transformer (VT) are acceptable to the EDC 1.14.15 Unless otherwise agreed by the EDC in writing, protective relay schemes shall be hardwired to the device they are tripping. Test switches are required in the current, voltage and trip circuits. 1.14.16 Current Transformer (CT) ratios and accuracy classes for CTs as used in the Generating Facility protection shall be consistent with ANSI and IEEE standards. 1.14.17 Voltage Transformers The Generating Facility shall be equipped with a direct voltage connection or a VT, which shall be connected to the EDC’s side of the interrupting device. For three-phase applications, a VT for each phase is required. If the interconnecting voltage transformer is ungrounded at the EDC voltage, this VT shall be a single three-phase device or three single-phase devices connected from each phase to ground on the EDC’s side of the Generating Facility’s interconnecting transformer, rated for phaseto phase voltage. The secondary winding shall be connected in open delta, have a loading resistor to prevent ferroresonance, and supply a zero-sequence over-voltage relay. On one side of the relay/resistor, the connection shall be grounded. Relays that (i) are capable of calculating zero-sequence voltages, and (ii) can be directly connected at the utilization voltage, may be utilized in lieu of grounded-wye to open delta VTs. 1.14.18 Data Requests for Fault Current, Impedance, and Transformer Specs A common need for third-party developers when designing details of an interconnection proposal is certain EDC distribution system data specific to the proposed location. This information includes available fault current, impedance data, and transformer sizing information. The EDC will gather this information at a billable cost to the developer based on the following process parameters:
  2. Page 14 of 32

    - If an interconnection project is required to undergo a Distribution System Impact Study, this information will be provided as part of the Impact Study analysis, typically as part of the report or within 15 business days from commencement of an Impact Study. The estimate costs to gather this information will be built into the Impact Study Agreement. Please see Section 4 within the Fast Track & Study Guidelines for more information regarding the Impact Study process. - If an interconnection project does not need to undergo a Distribution System Impact Study, this information will be provided upon request within 15 business days during the Contingent Approval phase of the interconnection process, with the applicable data request fee charged to and paid for by the developer. 1.15 Additional Requirements for Inverter-Based Installations Current inverter systems are capable of performing many of the required protective functions internally, without the need for additional protective equipment. Therefore, additional standards are applicable to inverter-based technologies. Two external standards shall apply to inverter-based Interconnections: (1) IEEE Standard 1547, (Standard for Interconnecting Distributed Resources with Electric Power Systems): and (2) UL Standard 1741 and UL Standard 1741 SA, “Inverters, Converters, Controllers and Interconnection System Equipment for use with Distributed Energy Resources.” These standards set forth the nominal voltage and frequency parameters that must be met and the limits allowed for anomalies such as flicker and interference, as well as the time allowed for disconnection when the required parameters are no longer being met or for reconnection following a system failure or automatic disconnection. The EDC recognizes the concept of “Type Certification” (sometimes called pre-certification) which requires that the inverter-based units undergo standardized testing, usually by an Accredited Nationally Recognized Testing Laboratory (e.g., Underwriter’s Laboratory), and that the results of those tests be made publicly available. Type certified units typically must also be “listed” by the laboratory and the equipment labeled as such. Advanced inverters also provide grid support functionality and can assist with resource availability in the event of a bulk power system or other disturbance. As such and unless agreed upon by the EDC, inverters must also be set as per the guidance provided in Appendix C. 1.15.1 The technical requirements for certified inverter based Generating Facilities, 25kW and less, are found in a separate document, the Eversource Energy/UI “Guidelines for the Interconnection of Residential Single Phase Certified Inverter-Based Generating Facilities of 25 kW (ac) or Less.”
  3. Page 15 of 32

    1.15.2 The requirements of UL 1741may be applied to inverters with photovoltaic and other electric energy sources. An inverter is considered approved if it is certified to the UL 1741 testing procedure and it has passed the required tests without failure to comply with IEEE C62.41 and C62.45. Proof of certification under UL1741 and compliance with IEEE C62.41, and C62.45 shall be required. As of May 7, 2007, UL 1741 includes the requirements within it of IEEE C62.41, and C62.45. Therefore, equipment tested to UL 1741 after that date need only prove compliance with UL 1741. 1.15.3 It is the Generator’s responsibility to submit written evidence that the proposed Generating Facility has been UL 1741 certified. Generators should contact the Generating Facility’s supplier to determine if it has been listed. 1.15.4 Non-certified inverters must have either non-islanding or anti-islanding protection as defined by IEEE 1547 and conform to the maximum harmonic limits prescribed in IEEE 519. Non-certified inverters must be protected by certified or Utility-Grade Relays, using settings approved by the EDC. 1.15.5 Self-commutated inverters with external frequency sensing may be used to synchronize the Generating Facility with the EPS. The following requirements apply to such inverters: 1.15.5.1 The Generator shall use one or more synchronizing devices such as motorized breakers, contactor/ breaker combinations, or a fused contactor (if mutually agreeable) to connect the Generating Facility to the EPS. This synchronizing device shall not be the Interconnection interrupting device. This synchronizing device shall be capable of interrupting the current produced when the Generating Facility is connected out of phase with the EPS consistent with IEEE 1547, Section 4.1.8.3. 1.15.5.2 All synchronizing shall be done by the Generator at the Generating Facility. The Generating Facility shall not be used to energize a de-energized EDC circuit. 1.15.5.3 In-line breakers, contactors, or switches without synchronizing devices require electrical or mechanical interlocks to prevent out-of-phase closing with the EPS. 1.15.5.4 All synchronizing schemes used for interconnecting a Generating Facility with the EPS must conform to the synchronizing requirements of the latest version of IEEE 1547. Automatic synchronizing schemes are preferred.
  4. Page 16 of 32

    1.16 Additional Requirements for Energy Storage Systems 1.16.1 Impact Study Requirements: 1.16.1.1 In order to conduct a distribution impact study for a Storage System, a proposed dispatch limiting schedule (DLS) shall be provided to the EDC by the developer. The DLS will include the maximum dispatch schedule for both charging and discharging activity of the system as shown in the sample tables below. The time shown in the table row is for reference only and can be changed by the developer to fit their intended operational schedule. See Table 4-1 and Table 4-2 below. 1.16.1.2 Prior to developing a DLS, the EDC must provide minimum load or peak load data for the substation and circuit. The minimum load data for charging and discharging will be provided for all four seasons, Spring (March, April and May), summer (June, July and August), Fall (September, October and November) and Winter (December, January and February). The following data will be developed during a distribution Feasibility study as described in the Guidelines for Generator Interconnection Fast Track and Study Process. Alternatively, such data may be provided in the EDC hosting capacity maps in which case, no study will be required. 1.16.1.3 The EDC’s will conduct a Distribution Impact Study based on submitted DSL within the schedule windows proposed for the peak load and minimum load/peak generation day. Based on results of the study analysis, the EDC may communicate the need for adjustments to the DSL in order to avoid distribution system upgrades.
  5. Page 17 of 32

    1.16.1.4 Compliance with the approved DSL for each project will be treated as a required operational restriction and detailed in the Interconnection Agreement. Enforcement of this required compliance, such as a Real Time Automatic Controller or a DER management system, will be determined by the EDC. Refer to section 6 for Monitoring and control requirements. Maximum Discharge (MW) Discharge Limiting Schedule 8:00 – 10:00 10:00 – 16:00 16:00 – 18:00 18:00 – 8:00 Spring (March, April, May) Summer (June, July, August) Fall (Sep, Oct, Nov) Winter (Dec, Jan, Feb) Table 0-1 Maximum Charge (MW) Charge Limiting Schedule 8:00 – 10:00 10:00 – 16:00 16:00 – 18:00 18:00 – 8:00 Spring (March, April, May) Summer (June, July, August) Fall (Sep, Oct, Nov) Winter (Dec, Jan, Feb) Table 0-2 1.17 Additional Requirements for Induction Generators Unless the EDC shall determine otherwise, there are no additional protection requirements applicable only to Induction Generators. 1.18 Additional Requirements for Synchronous Generators The following additional relay functions are required for Synchronous Generators. Settings for these relays shall be submitted to the EDC for review. See Appendix 4.2.8A for setting guidance. 1.18.1 Relays for Synchronous Generators a. 51V Over-Current (Voltage Control or Restrained). This element provides backup phase overcurrent protection for system faults under a collapsed voltage condition.
  6. Page 18 of 32

    b. 59G Over-Voltage (Ground). This element detects ground faults in the event that a ground N over-current source is lost. When studies show it can operate reliably, an alternative to the 59G is a 51N over-current (Ground). This element provides ground over-current protection and operates with an inverse time-current characteristic when its input current exceeds a predetermined value. c. 25 Synchronizing or Synch-Check. This element supervises the operation of the Generator automatic or manual synchronizing system by ensuring proper voltage phase angle matching and, where appropriate, slip frequency between the EPS and the Generating Facility before the breaker is allowed to close. 1.18.2 Relays settings for Synchronous Generators Any or all of the following additional relay functions may be required by the EDC. Settings for these relays shall be submitted to the EDC for review. See Appendix A for setting guidance. 1.18.2.1 32R Reverse Power. This element is used on systems designed as import only systems to ensure no power is exported onto the EPS. 1.18.2.2 32U Under-Power. This element performs a similar function to the 32R element, except it ensures the Generating Facility is always importing some level of power. 1.18.2.3 46 Negative Sequence Current. This element serves to protect both the EPS and the Generator system from system unbalances including single phasing. 1.18.2.4 51 Phase Over-Current. This element provides over-current protection and operates with an inverse time-current characteristic when its input current exceeds a predetermined value. 1.18.2.5 51N Ground Over-Current. This element provides ground over-current protection and operates with an inverse time-current characteristic when its input current exceeds a predetermined value. 1.18.2.6 67 Directional Phase Over-Current. This element provides directional phase over-current protection and operates with an inverse time-current characteristic when its input current exceeds a predetermined value in a specified direction. 1.18.2.7 67N Directional Ground Over-Current. This element provides directional ground over-current protection and operates with an inverse time-current characteristic when its current exceeds a predetermined value in a specified direction.
  7. Page 19 of 32

    1.18.2.8 86 Lockout Relay. This auxiliary relay is electrically tripped by the Generating Facility protection and in turn trips the isolating circuit breaker(s). It can only be reset manually after all protective trips have been cleared. 1.18.3 Synchronizing Devices 1.18.3.1 The Generator shall designate one or more synchronizing device(s) such as motorized breakers, contactor/breaker combinations, or a fused contactor (if mutually agreeable) to be used to connect the Generating Facility to the EPS. This synchronizing device may be a device other than the Interconnection interrupting device. The synchronizing device must be capable of interrupting the current produced when the Generating Facility is connected out of phase with the EPS consistent with IEEE 1547, Section 4.1.8.3 as amended from time to time. 1.18.3.2 All synchronizing will be done by the Generator at the Generating Facility. The Generating Facility shall not be used to energize a de-energized EDC circuit. 1.18.3.3 In-line breakers, contactors, or switches without synchronizing devices require electrical or mechanical interlocks to prevent out-of-phase closing with the EPS. 1.18.3.4 All synchronizing schemes used for interconnecting a Generating Facility with the EPS must conform to the synchronizing requirements within the current version of IEEE 1547. Automatic synchronizing schemes are preferred. 1.18.3.5 The Generator shall provide relaying functions to clear both phase and ground short circuit faults on the EDC’s distribution circuit. The operating characteristics thereof shall be subject to review and approval by the EDC. 1.19 Closed Transition Generators 1.19.1 A closed transition, “make-before-break” Generating Facility must be synchronized with the EPS prior to transfer occurring. The transfer scheme will then parallel the Generating Facility with the EPS for less than 100 milliseconds. During this brief period, the load will be either transferred to the Generating Facility from the EPS or to the EPS from the Generating Facility. The design of the transfer scheme shall prevent the possibility of sustained parallel operation of the Generating Facility with the EPS. 1.19.2 The closed transition scheme and transition equipment used by the Generator must be reviewed
  8. Page 20 of 32

    and approved by the EDC prior to operation of the Generating Facility. The closed transition scheme must provide voltage, frequency and phase angle matching as appropriate to provide a smooth transition. It must also provide maximum paralleling time protection. This protection is described below in Section 4.6.3. 1.19.3 Protective relays isolating the Generating Facility from faults in the EPS shall not be required if the paralleling operation is automatic and takes place for less than 100 milliseconds. Maximum paralleling time protection must be provided by a separate device from the equipment used for control and paralleling of the generator and operation of the transfer switch. (See Appendix B for details on the required logic for this protection.) This protection shall (i) use a discrete solid-state timer (pneumatic timers are unacceptable for this purpose), (ii) be powered by the generator battery and (iii) trip an interrupting device (which may be the generator breaker) that ceases parallel operation of the generator. This requirement shall prevent sustained operation should the control equipment malfunction. 1.19.4 The parallel operation of a closed transition Generating Facility lasting 100 milliseconds or more requires the same protective relay functions as would a Generating Facility operating in sustained parallel operation with the EPS as described in these Technical Requirements. 1.19.5 The Generator, at a minimum, must perform the following functional tests after its transfer equipment has been energized, but before the closed-transition transfer is allowed on the EPS as a normal operation: a. Voltage, frequency, and phase rotation. b. Transfer test (maximum paralleling time must be less than 100 milliseconds); and c. Excessive parallel time test (when the EDC source switch fails to open), the protection must trip an interrupting device (which may be the Generating Facility’s breaker) that ceases parallel operation of the generator. The EDC must be notified ten (10) Business Days in advance of such testing so that it may, at its option, have its personnel observe the testing, and/or inspect the installation. 1.19.6 Before the approval of closed-transition transfer is granted by the EDC, the Generator must provide to the EDC a report attesting to the successful completion of the above testing. Upon receipt by the EDC of the approved test and inspection reports, along with a verification of the local Electrical Inspector’s approval, the EDC will issue a written notice of approval of closed-transition transfer to
  9. Page 21 of 32

    the Generator. 1.20 Open Transition Generating Facilities Connection of a Generating Facility with open transition transfer does not require an Interconnection Application and is permissible on the condition that such Generating Facility’s manual or automatic transfer switch will not allow any parallel operation of the Generating Facility with the EPS. This electrical state (i.e., open transition transfer) is typically referred to as “breakbefore-make,” which means that the Generating Facility’s transfer switch must be designed and operated to prevent the EPS-provided power and the Generating Facility-provided power from powering the Generator’s facility circuits (i.e., load) at the same time. Consequently, this mode of operation will also prevent the Generating Facility from potentially energizing the EPS. 1.21 Special Protection Systems 1.21.1 The EDC May Require additional anti islanding protection Whenever: 1.21.1.1 The minimum load to generation on a circuit creates the possibility that an unacceptable abnormal operating condition could occur. 1.21.1.2 It is determined that the Generating Facility’s protective relaying may not operate during certain conditions or faults; or 1.21.1.3 The installation could increase the length of outages on a distribution circuit or jeopardize the reliability of the circuit. The Generator shall be responsible for all costs and expenses incurred by the EDC to install additional anti-islanding protection. EDC may require a Dynamic Risk of Islanding Study in order to evaluate the risk of unintentional islanding. 1.21.2 High Speed Protection If the EDC determines that relaying used traditionally on the distribution system cannot operate quickly enough to avoid adverse system impacts, the EDC may require that the Generating Facility use either direct transfer tripping techniques or more sophisticated techniques that rely on protective relay communication to increase operating speed.
  10. Page 22 of 32

    1.21.3 Recloser Schemes Any Generating Facility proposed for Interconnection at a point on the EPS that is supplied by an existing recloser scheme shall require special studies to determine the feasibility of that Interconnection as proposed. The Interconnection of the Generating Facility to the EPS shall not degrade the reliability of the EPS as a result of either its operation or changes to the EPS to accommodate the Interconnection. If the Generating Facility’s protection cannot be designed to meet these requirements, other anti-Islanding measures will be required (such as a dedicated circuit supply or DTT protective relaying from all EDC isolation points). Any changes to the EPS’s protective schemes or settings, or to the Generating Facility necessary to accommodate the Interconnection shall be at the Generator’s sole cost and expense. 1.22 Protection System Changes 1.22.1 The Generator shall provide the EDC with reasonable advance notice of any proposed modifications to the Generating Facility’s protective relay system, relay settings, operating procedures or other equipment affecting the Interconnection. The EDC will determine if such proposed modifications require re-acceptance of the Interconnection per the requirements of this Section 4. 1.22.2 The EDC shall provide the Generator with reasonable advance notice of any proposed changes to be made to its protective relay system, relay settings, operating procedures or other equipment that affects the Interconnection. Interconnecting Generators with Network Systems Other sections of these Technical Requirements are applicable to Generating Facilities interconnected with radial primary or secondary distribution circuits, the most common distribution configuration. In large cities, however, a number of electric utility companies use lowvoltage network systems. These low-voltage networks are of two subtypes: (1) the secondary grid network (also referred to as an area network, grid network, or street network) that serve; numerous sites, usually several city blocks, from a highly interconnected grid at 120/208 V, threephase; and (2) the Spot Network that serve independent, large buildings usually at 277/480 V, three-phase.

Text of UI-Attachment 5.pdf

Extracted from the file · 10 pages · 12,154 characters

Words on different pagesRead the text of UI-Attachment 5.pdf

Text of UI-Attachment 6.pdf

Extracted from the file · 29 pages · 55,721 characters

Words on different pagesRead the text of UI-Attachment 6.pdf

Text of UI-Attachment 7.pdf

Extracted from the file · 33 pages · 83,950 characters

Words on different pagesRead the text of UI-Attachment 7.pdf

Text of UI-Attachment 9.pdf

Extracted from the file · 14 pages · 33,843 characters

Words on different pagesRead the text of UI-Attachment 9.pdf

Text of UI-Attachment 11.pdf

Extracted from the file · 4 pages · 13,890 characters

Text of UI-Attachment 12.pdf

Extracted from the file · 36 pages, 2 without text · 106,019 characters

As listed on the current system

Compliance Filings, 10/01/2026 [26-08-07] Order No.No 4 in docket 17-12-03RE05 / Eversource Energy /

This filing on the current system (opens in a new tab)