Written Comments in response to the opportunity to comment on retention of consultants
Filed by Avangrid
- Type of filing
- Correspondence
- Date filed
- March 6, 2026
- Filed by
- Avangrid
- Files
- 1
As listed on the current system
Corres. 03/06/2026 [26-08-08] (Avangrid) - Written Comments in response to the opportunity to comment on retention of consultants
Files1
2026-03-06 UI Written Comments #26-08-08.pdf
PDF · 190 KB · 2 pagesText searchable
Download 2026-03-06 UI Written Comments #26-08-08.pdfRead the text of 2026-03-06 UI Written Comments #26-08-08.pdf
March 6, 2026
Mr. Jeffrey R. Gaudiosi, Esq.
Executive Secretary
Public Utilities Regulatory Authority
10 Franklin Square
New Britain, CT 06051
Re:
PURA Docket No. 26-08-08, Non-Wires Solutions Process Cycle 2, UI’s Opposition to the
Retention of Consultants by the Public Utilities Regulatory Authority
Dear Mr. Gaudiosi:
The United Illuminating Company (“UI”) submits this correspondence in opposition to the Public
Utilities Regulatory Authority’s (“PURA’s”) February 27, 2026 Notice of Opportunity to Comment
on the Retention of Consultants (the “Notice”) in the above-referenced docket.
In the Notice, PURA identifies that it intends to continue its retention of Dunsky Energy + Climate
Advisors (“Dunsky”) as the Process Monitor in this Docket. The Notice invites Docket Participants to
comment on the necessity or desirability of Dunsky’s services.
In order to retain a consultant, C.G.S. § 16-18a requires that the consultant provides expertise in areas
where PURA’s staff lacks expertise or where it is necessary to supplement the existing expertise of
PURA’s staff. Further, C.G.S. § 16-18a requires PURA to find that the services of the consultant are
necessary or desirable and limits the expenses of the consultant to no more than two hundred thousand
dollars per proceeding. This cap may only be exceeded for good cause. As discussed below, given
the expertise that PURA has developed in the Cycle 1 process docket, the engagement of any
third‑party consulting firm to serve in a Process Monitor role is no longer necessary or desirable, and
good cause does not exist to exceed the statutory cap on expenses.
Docket No. 26-08-08 represents the second annual Non-Wires Solutions (“NWS”) process cycle
undertaken by PURA. While this process is still relatively new, several observations were made
throughout last year’s inaugural review, which form the basis of UI’s comments and opposition.
First, affordability is a significant focus of Connecticut residents, the Connecticut General Assembly,1
PURA, and UI. UI continuously balances the needs of their electric distribution system with the burden
that investments may place on customers. The annual NWS process was specifically developed to
illustrate the affordability decisions UI makes. The NWS Process is a transparent mechanism to
leverage competitive forces to fully capture the benefits of NWS in meeting distribution system needs,
with the ultimate objective of improving outcomes for ratepayers and advancing Connecticut’s public
1
See, e.g., Conn. Pub. Act No. 25-173, An Act Concerning Energy Affordability, Access and Accountability, 2025.
-1-
policy goals.2 The use of consultants for the Process Monitor in the past NWS dockets3 have totaled
to a significant cost of $341,991.694 to customers. While a consultant may have been helpful to PURA
to develop the review and analysis process for this program, that process has now been established and
PURA staff should be capable of assuming the role of Process Monitor for this and future cycles.
Avoiding consultant costs in this docket will contribute toward a more affordable process for
customers.
Second, keeping the Process Monitor function within PURA may reduce the risk of inconsistent
communications during the annual process. In Docket No. 25-08-08, the Process Monitor was
responsible for analyzing UI’s filings in the docket, facilitating discussion meetings with the docket’s
stakeholders at various times throughout the year, and providing comments and suggested conclusions
on UI’s filed plans. While the Process Monitor and UI worked through numerous questions and
comments throughout the year; it was not clear to UI whether PURA staff were actively involved in or
aware of those discussions. The Proposed Screening Decision in Docket No. 25-08-08 contained
several determinations that differed from the months of discussions held with the Process Monitor,
suggesting that miscommunication occurred between the consultant and the PURA staff responsible
for drafting the Proposed Screening Decision. Having PURA act as the Process Monitor would
eliminate the potential for any miscommunication.
Alternatively, if PURA determines that the continued retention of Dunsky is necessary or desirable,
UI respectfully request that the Process Monitor’s role be clearly communicated and limited to only
those tasks necessary to supplement PURA’s existing expertise. Additionally, Dunsky should provide
a budget of their expected costs for the year. PURA’s staff should undertake as much of the Process
Monitor’s responsibilities as is practicable, in order to mitigate excessive consultant‑related costs,
avoid redundant work, and reduce unnecessary procedural delays. In the event that Dunsky is retained,
UI expects PURA’s staff to support the onboarding of the consultant, including engaging with UI to
ensure Dunsky meets the criteria required by the UI to view confidential data.
UI appreciates the opportunity to comment on the retention of consultants by PURA in this docket. If
you have any questions regarding UI’s position, please contact the undersigned.
Sincerely,
Alex Soter
Alex Soter
Counsel
On behalf of the United Illuminating
Company
cc: Service List
See PURA’s November 9, 2022 Decision in Docket No. 17-12-03RE07 at 1.
See PURA Docket Nos. 24-08-08, Non-Wires Solutions Process Initial Phase, and 25-08-08, Non-Wires Solutions
Process Cycle 1.
4
This figure is a summation of invoices received by both UI and Eversource from the Process Monitor since the
inception of the NWS program.
2
3
-2-