STATE OF CONNECTICUT
PUBLIC UTILITIES REGULATORY AUTHORITY
DOCKET NO. 26-08-08
NON-WIRES SOLUTIONS PROCESS CYCLE 2
NOTICE OF DOCKET CLOSING & PROCEDURAL ORDER
NOTICE OF DOCKET CLOSING
On November 9, 2022, the Public Utilities Regulatory Authority (Authority or PURA)
established a Non-Wires Solutions (NWS) Process applicable to The Connecticut Light
and Power Company d/b/a Eversource Energy (Eversource) and The United Illuminating
Company (UI; together, with Eversource, the Companies or EDCs). Decision, Nov. 9,
2022, Docket No. 17-12-03RE07, PURA Investigation Into Distribution System Planning
of the Electric Distribution Companies – Non-Wires Alternatives (NWS Decision).
On December 18, 2024, the Authority approved key NWS Process Materials and
design documents subject to certain modifications, which concluded the Process Initiation
Phase of the NWS Process. Decision, Dec. 18, 2024, Docket No. 24-08-08, Non-Wires
Solutions Process Initiation Phase (24-08-08 Decision).
On January 23, 2026, the Authority initiated the instant proceeding to serve as the
administrative record of the second annual NWS Process Cycle pursuant to the NWS
Decision, the 24-08-08 Decision, and General Statutes § 16-19e(a).
Throughout the first two process cycles, the Authority and the Process Monitor
have identified structural and methodological limitations impacting the NWS program’s
effectiveness. Docket No. 25-08-08, Non-Wires Solutions Process Cycle 1, Dunsky
Corresp. Mar. 4, 2026, Process Monitor Year End Report, (PM Year End Report); First
Process Cycle Decision, p. 11. Therefore, program reforms are warranted to successfully
implement an effective NWS process in Connecticut. Accordingly, the Authority is closing
this docket without issuing a Screening Decision, pausing further process cycles, and
initiating an NWS process redesign docket to consider program reforms.
Despite closing the proceeding, the EDCs should continue to submit the
compliance filings set forth in the NWS and 24-08-08 Decision, respectively. Additionally,
the Authority may choose to issue interrogatories to the EDCs from time to time regarding
such compliance fillings. Accordingly, the orders of the NWS Decision and the 24-08-08
Decision remain in effect until the Authority indicates otherwise. As such, the EDCs shall
continue filing the annual EDC Data and Grid Needs Filing as well as the quarterly filings
in the instant proceeding.
PROCEDURAL ORDER
The EDCs and the Process Monitor collaborated to develop a benefit-cost
analysis (BCA) tool to aid in the screening of grid needs. PM Year End Report, p. 5;
Docket No. 26-08-08
Page 2
Docket No. 25-08-08, Non-Wires Solutions Process Cycle 1, Eversource Corresp., Sep.
5, 2025, Att. 1, p. 2.
The Authority directs the EDCs to:
1. Submit as compliance the BCA tool, a narrative description of the tool, and a
worked example of how the BCA tool would be used or has been used to
evaluate the feasibility of pursuing an alternative to traditional wires solution at
the screening phase. The Compliance shall be submitted no later than May 8,
2026, at 4:00 p.m.
By the following commissioners,
Thomas H. Wiehl
Chairman
David Arconti, Jr.
Vice Chairman
Everett Smith
Commissioner
Janice A. Beecher
Commissioner
Holly H. Cheeseman
Commissioner
Dated at New Britain, Connecticut, this 17th day of April, 2026.