A prototype public docket site for the Connecticut Public Utilities Regulatory Authority.

Utility Dockets and FilingsConnecticut Public Utilities Regulatory Authority
CorrespondenceFiled by Avangrid

SCG Biennial Demand Supply Forecast

Part of

Docket 26-10-03Open

Review of the Connecticut Gas Utilities' Forecasts of Demand and Supply 2027-2031

Type of filing
Correspondence
Date filed
October 1, 2026
Filed by
Avangrid
Files
2
As listed on the current system: Corres. 10/01/2026 [26-10-03] (Avangrid) - SCG Biennial Demand Supply Forecast

This filing on the current system (opens in a new tab)

Files

Text of 2026-10-01 SCG Biennial Demand & Supply Forecast 2027-2031 Cover Ltr #26-10-03.pdf

Extracted from the file · 1,159 characters
October 1, 2026 Mr. Jeffrey R. Gaudiosi, Esq. Executive Secretary Public Utilities Regulatory Authority 10 Franklin Square New Britain, CT 06051 Re: Docket No. 26-10-03, Review of the Connecticut Gas Utilities’ Forecasts of Demand and Supply 2027-2031 Dear Mr. Gaudiosi: The Southern Connecticut Gas Company submits herewith the Biennial Forecast of Natural Gas Demand and Supply required by Section 16-32f of the General Statutes of the State of Connecticut. This filing forecast is available to the public by forwarding an e-mail to [email removed]. Copies of this report are also being furnished to the municipal, state, and regional officials and agencies as listed in Section 16-32f. Sincerely, James Nitz Manager, Regulatory Services UIL Holdings Corporation As Agent for The Southern Connecticut Gas Company cc: Municipal Chief Executive Officers, SCG Service Territory Regional Council of Governments Attorney General President Pro Tempore of the Senate Speaker of the House of Representatives Energy and Technology Committee Office of Consumer Counsel 180 Marsh Hill Road, Orange, CT 06477 www.soconngas.com An equal opportunity employer

Text of 2026-10-01 SCG Biennial Demand Supply Forecast #26-10-03.pdf

Extracted from the file · 60,000 characters (the first 60,000 are kept)
FORECAST of NATURAL GAS Demand and Supply 2027-2031 October 1, 2026 SCG TABLE OF CONTENTS I. Introduction Summary ...................................................................................................................... I.1 Organization of the Filing................................................................................................. I.2 II. Industry Developments Planning Issues.................................................................................................................II.1 III. Demand Forecast Introduction ....................................................................................................................III.1 Ex. D-1 – Projected Sales ...............................................................................................III.2 Econometric Forecast Development ...............................................................................III.3 Overview of Model Equations ........................................................................................III.4 Detailed Descriptions of Forecast Equations..................................................................III.8 Base Case Demand Forecast.........................................................................................III.12 Ex. D-2 – Historical Degree Days ................................................................................III.14 Ex. D-3 – Normal and Design Degree Days.................................................................III.15 Economy/Company Assumptions.................................................................................III.16 Ex. D-4 – Exogenous Assumptions to Econometric Models........................................III.17 Firm Base Case Forecast...............................................................................................III.18 Ex. D-5 – Residential Customers..................................................................................III.19 Ex. D-6 – Residential Sales ..........................................................................................III.20 Ex. D-7 – Commercial/Industrial Sales ........................................................................III.21 Transportation and Non-firm Forecasting ....................................................................III.22 Ex. D-8 – Interruptible Sales and Transportation Service ............................................III.23 Ex. D-9 – Sales by Class...............................................................................................III.24 Alternate Demand Scenarios.........................................................................................III.25 Ex. D-10 – Firm Throughput Scenario #1 ....................................................................III.26 Ex. D-11 – Firm Throughput Scenario #2 ....................................................................III.27 Ex. D-12 – Firm Throughput Scenario #3 ....................................................................III.28 IV. Supply Forecast Supply Forecast Methodology ....................................................................................... IV.1 Supply Forecast Assumptions........................................................................................ IV.2 Sendout – Gas Planning System .................................................................................... IV.4 Supply Forecast Conclusions......................................................................................... IV.7 Ex. S-1 – Seasonal Customer Requirements: Normal Weather..................................... IV.8 Ex. S-2 – Seasonal Customer Requirements: Design Weather.................................... IV.10 Ex. S-3.1 – Firm Transportation Contracts.................................................................. IV.12 Ex. S-3.2 – Firm Storage Contracts ............................................................................. IV.13 Ex. S-3.3 – Firm Storage Contract Ratchet Requirements .......................................... IV.14 Ex. S-3.4 – Peaking Resources .................................................................................... IV.18 Ex. S-3.5 – Firm Supply Contracts .............................................................................. IV.19 Ex. S-3.6 – Gas Flows to Connecticut (Map) .............................................................. IV.20 Peak Day/Peaking Requirements................................................................................. IV.21 Ex. S-4 – Projected Firm Peak Day Requirements ...................................................... IV.22 SCG TABLE OF CONTENTS Ex. S-5 – Peak Day Model Summary .......................................................................... IV.23 Ex. S-6 – Design Day Regression Model .................................................................... IV.24 Ex. S-7 – Not applicable for SCG Addressing Customer Demand .................................................................................... IV.25 Ex. S-8 – Incremental vs Rolled in Rates .................................................................... IV.28 Ex. S-9 – Top Ten Sendout by Year - Historical......................................................... IV.29 Ex. S-10 – Monthly Degree Days Since January 2006................................................ IV.31 Ex. S-11 – Projected Firm Peak Day Demand and Resources .................................... IV.32 Ex. S-12 – Projected and Actual Peak Day Resources ................................................ IV.33 V. Conservation Conservation Overview ...................................................................................................V.1 Conservation Planning .....................................................................................................V.2 Conservation Program Descriptions ................................................................................V.5 Conservation Summary Exhibits ...................................................................................V.11 Ex. C-1 – Avoided Costs ..............................................................................................V.12 Ex. C-2 – Annual MCF Savings from Conservation Programs.....................................V.13 Ex. C-3 – Peak Day MCF Savings from Conservation Programs .................................V.14 Ex. C-4 – Conservation Program Expenditures .............................................................V.15 Ex. C-5 – Estimates of Price induced Conservation ......................................................V.16 VI. Appendix Ex. A-1 – Residential Non-Heating Use Per Customer................................................. VI.1 Ex. A-2 – Residential Heating Use Per Customer ......................................................... VI.2 Ex. A-3 – Multifamily Billed MCF .............................................................................. VI.3 Ex. A-4 – Commercial / Industrial Billed MCF ........................................................... VI.4 I. INTRODUCTION DEMAND INTRODUCTION Summary Southern Connecticut Gas Company (“SCG” or the “Company”) hereby files its “Forecast of Natural Gas Demand and Supply Forecast 2027-2031” (the “Forecast”) to describe its planning process to regulators, customers, and other interested parties. The Forecast uses sophisticated forecast methods and takes into account the best available information in a dynamic environment and represents a point in time view. The Company’s long-standing focus is providing reliable and affordable natural gas service to our customers. The Company will continue to monitor the dynamic market conditions including customer energy choice decisions and trends, economic conditions, customer energy affordability and alternatives, technology, potential decarbonization efforts, state initiatives. SCG is filing the Forecast pursuant to Section 16-32f of the Connecticut General Statutes, as well as in compliance with Order No. 6 of the Department’s August 17, 1987, Decision in Docket No. 86-10-13. The Forecast takes into consideration the issues addressed on July 17, 1995, Decision in Docket Nos. 93/10/01 / 94-09-28, as well as any other requirements contained in subsequent PURA decisions. Organization of the Filing Section I: Section II: Section III: Contains an Introduction and describes the filing’s organization Contains a discussion on natural gas industry developments Contains a base case demand forecast, forecasting methods and assumptions, a discussion of forecast techniques, and alternative demand scenarios. Section IV: Contains the supply forecast, including projected 5-year supply requirements under normal and design weather conditions along with peak day requirements. Section V: Contains a description of the 2027 conservation programs, budget levels, discussion of the Conservation Adjustment Mechanism, the collaborative process, and plan development. Appendix: Contains additional support for Section II Industry Developments, and Section III Demand Forecast. I-1 II. INDUSTRY DEVELOPMENTS SUPPLY PLANNING ISSUES OVERVIEW SCG plans for, develops, manages and operates a portfolio of resources to provide best cost, fully reliable service to our customers under all weather conditions over all time horizons, now and into the future. The resource portfolio is designed based upon specific planning criteria and is comprised of a relatively balanced combination of firm transportation from supply production sources, firm transportation from gas storage withdrawal sources and a peaking facility. The gas supply picture in the US is extremely robust led by prolific Appalachian area and Gulf of Mexico/Texas area supplies. US gas production growth has been very strong with actual tenyear growth of 48% and twenty-year growth of 124%. Correspondingly, the robust and low- cost production has led to wellhead prices that have been generally declining over the last twenty-five years1. The gas supply picture is so robust that significant amounts of natural gas converted to liquid form as LNG are now exported from the US to worldwide markets. The Company primarily acquires gas at large supply regions, especially the Marcellus area and to a lesser extent at Dawn, Ontario, Canada “into the pipeline” primarily from producer suppliers. The Company holds firm transportation contracts on ten different pipelines, of which three of those pipelines Tennessee Gas Pipeline (“Tennessee”), Algonquin Gas Transmission (“Algonquin”) and Iroquois Gas Transmission (“Iroquois”) interconnect with city gates and the other pipelines provide indirect services upstream of the city gates. Firm underground natural gas storage capacity is contracted for using long-term contracts and is filled with gas in the summer for subsequent withdrawal in the winter. The storage facilities are located in PA, NY, WV, and in Ontario, Canada. The Company owns and operates an LNG facility attached to its distribution system. SCG’s demand forecast reflects continued relatively low growth over the forecast horizon. Conservation and demand side management reduce net growth the benefits which include helping to reduce the need for new capacity. Gas demand from new large fuel cell applications has been significant and is another example of why ensuring adequate capacity into the LDC system is important. The factors driving customer demand, occurring during the clean energy transition, are explained in the demand planning section of this IRP plan. SCG is in a good capacity position throughout the forecast period to meet existing and new customer demand. This is an advantageous position for our customers as the ability to offer low cost, reliable and environmentally advantaged natural gas to homes and businesses in our service areas promotes the ability for customers to choose their most suitable energy fuel and at the same time broadly helps the economy and the environment. 1 Five-year average NYMEX prices; June 2001-May 2006 =$5.69/dth, June 2021- May 2026 = $3.90/dth II-1 III. DEMAND FORECAST INTRODUCTION The base case demand forecast includes Southern Connecticut Gas end-user requirements through the year 2031 for both firm and interruptible customers. The base case forecast is driven by a combination of econometric results and information on marketing and conservation efforts. The following sections present the forecasts and their development:  Econometric Forecast Development  Base Case Demand Forecast  Transportation and Non-firm Forecasting  Alternate Demand Scenarios The forecasting methods and assumptions are described in the following pages. SCG is continually improving its forecasting techniques and refining the results of its forecast equations. Several iterations of the forecast equations are run using different exogenous variables in an attempt to improve forecast results. The projected sales are reflected on Exhibit D-1, and explanatory text of the various company equations follow. III-1 SOUTHERN CONNECTICUT GAS COMPANY EXHIBIT D-1 PROJECTED SALES (MCFs) 2027 2028 2029 2030 2031 Residential Total 16,876,284 16,825,379 16,764,552 16,724,615 16,687,794 Commercial Total 14,031,429 14,310,093 14,407,636 14,505,735 14,597,247 Industrial Total 464,421 464,422 464,423 464,424 464,425 Firm Special Contract 1,327,974 1,327,974 1,327,974 1,327,974 1,327,974 FIRM SALES TOTAL 32,700,109 32,927,868 32,964,586 33,022,748 33,077,440 INTERRUPTIBLE SALES 3,959,769 3,959,769 3,959,769 3,959,769 3,959,769 SALES TOTAL 36,659,878 36,887,637 36,924,355 36,982,517 37,037,209 Firm Transportation 2,729,738 2,747,448 2,765,047 2,783,104 2,799,505 17,139 17,139 17,139 17,139 17,139 TRANSPORTATION TOTAL 2,746,877 2,764,587 2,782,186 2,800,244 2,816,644 THROUGHPUT TOTAL 39,406,755 39,652,224 39,706,541 39,782,761 39,853,853 On System Non-Firm Transp III-2 ECONOMETRIC FORECAST DEVELOPMENT Forecasts were developed using an econometric modeling methodology to estimate the relationship between certain explanatory or independent variables, and the dependent variable, which in this case, is monthly residential, multi-family and commercial & industrial (Use Per Customer) (“UPC”) as well as residential and multi-family customer counts. Commercial & Industrial customer forecasts were derived from an exponential smoothing model. An exponential smoothing model is a univariate (customer counts) forecasting method that is widely used in business forecasting. Historical UPC data from January 2021- December 2025 was used in residential models. Historical UPC data from January 2018- December 2025 was used in the multifamily model. Historical UPC data from January 2017- December 2025 was used in the commercial & industrial model. Actual monthly customer counts from January 2015- December 2025 were used in the models. January 2026- December 2036 forecasts were developed using MetrixND computer software. Connecticut economic and demographic data was obtained from IHS Markit May 2026 release. III-3 Overview of Model Equations Customer Count Models SCG General Residential customer model input includes a one month lagged dependent, monthly seasonal binary variables and a trend variable. The general class customer count was allocated to classes based on historical trends. Model coefficients and statistics for the residential customer count model are presented below: III-4 SCG heating residential customer model input includes a one month lagged dependent, monthly seasonal binary variables and Connecticut population. The heating class customer count was allocated to classes based on historical trends. Model coefficients and statistics for the residential customer count model are presented below: Model Statistics Iterations 39 Adjusted Observations 132 Deg. of Freedom for Error 115 R-Squared 0.988 Adjusted R-Squared 0.986 AIC 13.951 BIC 14.323 F-Statistic 579.479 Prob (F-Statistic) 0.0000 Log-Likelihood -1,091.08 Model Sum of Squares 9,421,512,054.56 Variable Coefficient StdErr T-Stat P-Value Sum of Squared Errors 116,858,533.41 CONST -105232.790 13424.443 -7.839 0.00% Mean Squared Error 1,016,161.16 Calendar.Jan -689.792 400.335 -1.723 8.76% Calendar.Feb -1285.740 492.551 -2.610 1.02% Std. Error of Regression 1,008.05 Calendar.Mar -289.533 489.765 -0.591 55.56% Mean Abs. Dev. (MAD) 713.64 Calendar.Apr -994.466 505.570 -1.967 5.16% 0.43% Calendar.May -2660.233 523.513 -5.082 0.00% Mean Abs. % Err. (MAPE) Calendar.Jun -2142.307 515.256 -4.158 0.01% Durbin-Watson Statistic 1.562 Calendar.Jul -2800.242 514.092 -5.447 0.00% Durbin-H Statistic 3.217 Calendar.Aug -3102.279 510.701 -6.075 0.00% 84.13 Calendar.Sep -3088.152 509.777 -6.058 0.00% Ljung-Box Statistic Calendar.Oct -2745.156 509.675 -5.386 0.00% Prob (Ljung-Box) 0.0000 Calendar.Nov -1552.087 384.072 -4.041 0.01% Skewness 0.955 RSH_Custs.Nov2025_Binary -15293.303 1042.416 -14.671 0.00% RSH_Custs.PostCOVIDSummers 1618.457 413.694 3.912 0.02% Kurtosis 6.686 IHS_Monthly.QHALL 130.328 14.987 8.696 0.00% Jarque-Bera 94.766 RSH_Custs.LagDep(1) 0.519 0.054 9.561 0.00% 0.0000 MA(1) 0.409 0.098 4.180 0.01% Prob (Jarque-Bera) Multi-Family and Commercial/Industrial customer count forecasts were developed using exponential smoothing models. III-5 Model Statistics Iterations 39 Adjusted Observations 132 Deg. of Freedom for Error 129 R-Squared 0.822 Adjusted R-Squared 0.819 AIC 10.515 BIC 10.580 F-Statistic #NA Prob (F-Statistic) #NA Log-Likelihood -878.28 Model Sum of Squares 21,478,849 Sum of Squared Errors 4,649,419 Mean Squared Error 36,042.01 Std. Error of Regression 189.85 Mean Abs. Dev. (MAD) 135.49 Mean Abs. % Err. (MAPE) 0.69% Durbin-Watson Statistic 1.893 Durbin-H Statistic 0.000 Ljung-Box Statistic 65.62 Prob (Ljung-Box) 0.0000 Variable Coefficient StdErr T-Stat P-Value Skewness -1.265 Simple 0.399 0.075 5.295 0.000 Kurtosis 8.936 Trend 0.009 0.020 0.449 0.654 Jarque-Bera 229.0 Seasonal 0.028 0.103 0.269 0.788 Prob (Jarque-Bera) 0.0000 III-6 UPC Models The usage (UPC) models forecast monthly normalized UPC. All models utilize multiple regression. Weather variables are used to capture the difference from normal to produce a forecast under normal conditions. Seasonal variation in billed MCF and or UPC was modeled using monthly dummy (binary) variables. Different economic and trend variables are tested to capture the variation in billed usage. Trend variables were tested to help account for a variety of factors that could influence the change in energy use over time including equipment upgrades, equipment replacement, turnover of the building stock and the penetration of new energy technologies. Different versions of trend variables were used including ones that do not trend the summer months (June through September). In some cases, these variants produced better statistical estimation of the historical data and thus more accurate forecasts. Several alternative and theoretically valid model specifications were tested for each rate code. The decision on which specification to use was based on a combination of Goodness-of-fit statistics (adjusted R-squared and forecast error), coefficient signs1, statistical significance (tstatistics2) of individual coefficients and forecast performance of the model. The final model selection was also based on out-of-sample tests, where some of the historic data was held out of the model development and used to test the forecast accuracy of the model. Serial correlation (which can be defined as the correlation of a variable and itself N periods later) was tested using both the Durbin-Watson and the Ljung-Box tests. The DurbinWatson test checks for autocorrelation in the first lag of the residual errors. The Ljung-Box test checks for autocorrelation in the first several lags of the residual errors. When detected by these tests, we attempted to correct for serial correlation of the residuals using the Cochrane-Orcutt estimation procedure. The selection of the final variable set was not based solely on the significance of the parameter estimates (typically represented by the t-statistics on the individual coefficient estimates). Wherever possible, we left variables in the model even if they were marginally significant (based upon the t–test criterion), to maintain consistency from rate class to rate class. Insignificant variables, in and of themselves, typically do not significantly affect other variable estimates, or the forecast of the dependent variable. However, if an independent variable displayed the wrong sign and/or exhibited multicollinearity3 with another variable, then it was removed from the equation. The company tested several equation model specifications in the model re-estimation process. 1 The sign of the coefficient on a variable is an important statistical determinant. For example, price variables are generally expected to have negative coefficient, since in theory sales will decrease as price increases. Variables with the wrong sign are omitted from the model to avoid misspecification. 2 Statistical significance of the parameter estimates is typically represented by the t-statistics on the individual coefficient estimates. Statistical significance, using the t-test, can use a value of 2.0 (1.96), as a test criterion at a 95% level of confidence (two-tailed test). A different level of statistical confidence (e.g. 90%, two-tailed) would employ a different test value (1.76) in evaluating the parameter estimate. 3 This occurs when two independent variables are highly correlated with each other. When this occurs, one of the variables can be omitted from the equation. III-7 Detailed Descriptions of Forecast Equations The discussions of the re-estimated equations used to forecast billed UPC are organized by customer class: RSG, RSH, Multi-family, and Commercial/Industrial. The discussion on each forecast equation is supplemented by regression model results and corresponding statistics located in the Appendix. General Residential: The model specification to estimate billed UPC for Residential General customers is: RSG_UPC = mth1DUM + ……..+ mth8DUM + mth9DUM + mth10DUM + mth11DUM + MA3_SCGrealResrate + cwHDD + TrendVar + NovDec2025trinary + intercept Billed UPC for Residential General customers is driven by: A set of monthly indicator variables measuring deviations in average monthly throughput from the December level (mthIDUM, where I = a specific month). A 3-month moving average gas price variable (expressed in real terms) A Weather variable (Actual cycle-weighted HDD for historical period, Normal cycle-weighted HDD for forecast period) A yearly trend variable A trinary variable An Intercept term. Exhibit A-1 contains the output for this model. III-8 Heating Residential: The model specification to estimate billed UPC for Residential Heating customers is: RSH_UPC = mth1DUM + ……..+ mth8DUM + mth9DUM + mth10DUM + mth11DUM + MA3_SCGrealResrate + cwHDD + TrendVar + NovDec2025trinary + intercept Billed UPC for Residential Heating customers is driven by: A set of monthly indicator variables measuring deviations in average monthly throughput from the December level (mthIDUM, where I = a specific month). A 3-month moving average gas price variable (expressed in real terms) A Weather variable (Actual cycle-weighted HDD for historical period, Normal cycle-weighted HDD for forecast period) A yearly trend variable A trinary variable An Intercept term. Exhibit A-2 contains the output for this model. Multi-Family: The model specification to estimate billed mcf for Multifamily customers is: MultiMCF = mth1DUM + ……..+ mth8DUM + mth9DUM + mth10DUM + mth11DUM + MA3_SCGmultirealrates + CWHDD + TrendVar + intercept Billed UPC for Multifamily customers is driven by: A set of monthly indicator variables measuring deviations in average monthly throughput from the December level (mthIDUM, where I = a specific month). A gas price variable (expressed in real terms). A 3-month moving average gas price variable (expressed in real terms) A Weather variable (Actual cycle-weighted HDD for historical period, Normal cycle-weighted HDD for forecast period) A yearly trend variable An Intercept term Exhibit A-3 contains the output for this model. III-9 Commercial & Industrial: The model specification to estimate billed mcf for Commercial & Industrial customers is: CIMCF = mth1DUM + ……+ mth8DUM + mth9DUM + mth10DUM + mth11DUM + CIrealrate + cwHDD + LN_Employment + intercept Billed MCF for Commercial & Industrial customers is driven by: A set of monthly indicator variables measuring deviations in average monthly throughput from the December level (mthIDUM, where I = a specific month). A gas price variable (expressed in real terms). A Weather variable (Actual cycle-weighted HDD for historical period, Normal cycle-weighted HDD for forecast period) A log natural of an employment variable. An Intercept term. Exhibit A-4 contains the output for this model. III-10 Model Validation The econometric models and exponential forecasting models have very strong summary statistics, fit the datasets, and generalize well. Model coefficients are significant and indicate the appropriate response (sign of coefficient). Durbin-Watson statistics indicates an absence of serial correlation in the model residuals. Several additional factors were tested and analyzed to determine the model’s goodness of fit. The first test statistic is called the Coefficient of Determination, better known as the R-squared. An R-squared value of 1 means that the dependent variable is, on average, completely explained by the explanatory variables, while a value of 0 means that no explanatory relationship between the dependent variable and the independent variables can be estimated from the sample data. The second test statistic is called the Mean Absolute Percent Error (“MAPE”). The MAPE is the ratio of the absolute value difference between the monthly forecast value derived from the model and the actual monthly value averaged over the entire dataset of actual values. In this case for the MCF models only Winter MAPEs (November through April) were calculated because most gas usage occurs during those months. The smaller the MAPE, the better. A model that results in a high R-squared value and a small MAPE is said to have strong summary statistics. Another common test for checking if a model performs well is the Ex Post forecast test. For this test, a portion of the sample is withheld, and the model is estimated on the remaining sample. An estimate or forecast of the withheld data is then generated by the model which is compared to the withheld dataset. Summary statistics are analyzed to see how well the model forecasts the withheld sample. The primary statistic analyzed for an Ex Post test is the MAPE. A summary of model validation tests is provided below: MODEL Customers RSG RSH RMDS ComInd MCF* RSG (UPC) RSH (UPC) RMDS (UPC) ComInd (UPC) R2 FORECAST MODEL MAPE * 1-YR Ex Post ** MAPE * 2-YR Ex Post *** MAPE * 0.992 0.988 0.988 0.894 0.75% 0.43% 0.43% 0.43% 1.14% 1.15% 2.14% 1.26% 1.01% 0.81% 1.68% 1.12% 0.822 0.998 0.975 0.980 0.69% 4.15% 7.80% 6.05% 9.30% 1.11% 7.50% 2.22% 5.49% 1.36% 5.14% 2.22% III-11 BASE CASE DEMAND FORECAST WEATHER Background SCG uses information furnished by the National Oceanic and Atmospheric Administration (NOAA) published for Sikorsky Airport, Bridgeport to establish its weather assumptions for planning. The Company uses NOAA because their information is complete, going back for more than the thirty-year period presently used by the Company. Actual Degree Days The actual degree days experienced in Bridgeport for the five most recent years of 2021-2025 are lower than the calculated normal in the last five years and significantly lower than the annual design degree days. Calendar years 2021-2025 averaged 4,770 degree-days compared to the 30-year normal of 5,072 and annual design of 5,972 degree-days. The five-year average is 5.9% lower than normal, and 20.1% below annual design. Historic degree-days for the service area is shown in Exhibit D-2. Normal Degree Days The normal degree-days for the Bridgeport area over the period 1996-2025 are 5,073. Normal degree-days are shown in Exhibit D-3. Annual Design Degree Days Annual design degree-days are based on the coldest year in the thirty-year period of 19962025 and then adjusted to include the design peak day. Bridgeport’s design degree-days are 5,972 based on the gas year (Nov-Oct) 2003. Design degree-days are shown in Exhibit D-3. Design Peak Day SCG utilizes a rolling 30-year period for its peak day weather assumptions. Prior to the 2015/2016 winter period, the coldest single day in the last thirty years occurred on January 15, 2004 with a 68 EDD. On February 13, 2016, an even higher single day EDD occurred with 70 EDD. However, the peak day models also consider the weather that occurred on the day prior. The combination of the peak day and day prior EDD’s of 68/60 from January 15, 2004, produces a higher design day demand than February 13, 2016, and day prior EDD’s of 70/46. Based on its priority of ensuring reliable service for customers under all weather conditions, SCG utilized January 15, 2004, and day prior EDD combination of 68/60 to estimate the design peak day demand. Refer to the “Peak Day / Peaking Requirements” section (page IV-20) of this document for a more in-depth discussion of this topic. III-12 Adjustments The econometric models include the effects of historical conservation programs on forecasted demand. Out-of-model adjustments are made to the econometric results. These out-of-model adjustments include loads from cogeneration projects. Separately, the Company has included Alternative Demand Scenarios to reflect varying levels of new customer growth, normalized use per customer, regulatory or legislative initiatives, and conservation programs (see exhibits D10-D12). III-13 SOUTHERN CONNECTICUT GAS COMPANY EXHIBIT D-2 HISTORICAL DEGREE DAYS * 2021-2025 January February March April May June July August September October November December TOTAL 2021 978 905 706 421 173 7 3 0 9 128 615 756 4,701 2022 1,135 867 718 467 154 12 0 0 38 291 497 890 5,069 2023 772 796 720 394 178 31 0 0 59 208 635 739 4,532 2024 936 816 598 424 120 0 0 0 17 211 460 902 4,484 2025 1,076 892 652 378 148 21 0 1 15 273 601 1,007 5,064 5-Year Avg 4,770 * Source: NOAA-National Oceanic and Atmospheric Administration Published for Sikorsky Airport (Bridgeport service area). III-14 SOUTHERN CONNECTICUT GAS COMPANY EXHIBIT D-3 NORMAL AND DESIGN DEGREE DAYS * January February March April May June July August September October November December TOTAL Normal 1,035 880 763 446 184 25 0 1 37 270 569 863 5,073 Design (1) 1,204 1,062 830 567 266 61 0 0 23 340 657 962 5,972 * Source: NOAA-National Oceanic and Atmospheric Administration Published for Sikorsky Airport Calculated from the period of 1996-2025. Totals do not reflect a Leap Year (1) Bridgeport highest annual gas year (Nov-Oct) actual degree day total in the last 30 years = 2003. III-15 ASSUMPTIONS (ECONOMY/COMPANY) The U.S. economy is projected to continue to move slowly forward with modest growth expected during the forecast period. The Gross Domestic Product (GDP) index is projected to grow at an annual average rate of 2.5% for the period of 2027 through 2031. Consumer prices, a common measure of inflation, are projected at an average rate of 1.9% annually during 2027-2031. Several economic independent variables are reviewed when preparing the Company’s econometric demand forecasting models. Such variables include, but are not limited to, population, households and employment. Price variables are also reviewed and include SCG’s natural gas prices to various classes, oil prices, as well as other distillate prices. Historical and projected economic data is obtained from the firms Moody’s Analytics and IHS Markit. Inflation represented by the implicit price deflator for the Gross Domestic Product, Consumer Price and Producer Price was used in the determination of price forecast assumptions as well as various cost calculations in the conservation section. The history and forecast for economic and price variables used in the econometric models are presented in Exhibit D-4. III-16 SOUTHERN CONNECTICUT GAS COMPANY Exhibit D-4 Exogenous Asssumptions to Econometric Models Exogenous Variables US Economy- Moodys January 2026 2024 2025 2026 2027 2028 2029 2030 2031 Comsumer Price Index (Index 1982-84=100, SA) 314 $125 255 23,306 323 $129 261 23,667 333 $133 264 23,967 341 $135 265 24,385 347 $138 268 24,933 353 $140 272 25,530 360 $142 276 26,201 367 $145 280 26,895 1,710 1,465 3,675 1,717 1,474 3,688 1,718 1,480 3,688 1,711 1,485 3,684 1,711 1,490 3,677 1,714 1,496 3,670 1,714 1,501 3,666 1,712 1,506 3,661 $51.58 $9.50 $8.82 $54.89 $10.21 $8.93 $52.63 $9.91 $8.91 $52.63 $9.91 $8.91 $52.63 $9.91 $8.91 $52.63 $9.91 $8.91 $52.63 $9.91 $8.91 $52.63 $9.91 $8.91 Implicit price Deflator- GDP (Index 2017=100, SA) Producer Price Index (Index 1982=100, NSA) Gross Domestic Product (Bil. Ch. 2017 USD, SAAR) Connecticut- IHS Q2 2026 Total Employment (Thous.) Households (Thous.) Population (Thous.) SCG Price Price of Gas to SCG Customers - Residential Price of Gas to SCG Customers - Residential Multi-dwelling Price of Gas to SCG Customers - Commercial/Industrial III - 17 FIRM BASE CASE FORECAST Residential Sales and Customers The summary of residential sales and customers, including conservation is presented in Exhibits D-5 and D-6. Residential non-heating, heating and multifamily throughputs are forecasted using econometric models. Commercial and Industrial Sales Commercial and Industrial sales are derived using econometric models. The commercial and industrial sales forecast is presented in Exhibit D-7. III-18 SOUTHERN CONNECTICUT GAS COMPANY EXHIBIT D-5 RESIDENTIAL CUSTOMERS HISTORY 2022 2023 2024 2025 Non-Heating 16,559 15,960 14,715 13,958 8,734 Heating 166,290 169,659 174,615 175,452 118,693 857 879 988 991 661 183,706 186,498 190,318 190,401 128,088 Multi-Dwelling Residential Customers 2026 * *Current year includes 8 months of actual and 4 months of forecasted data. FORECAST 2027 2028 2029 2030 2031 Non-Heating 11,992 11,059 10,126 9,192 8,259 Heating 182,000 183,106 184,215 185,524 186,892 1,006 1,010 1,014 1,018 1,023 194,999 195,175 195,354 195,735 196,174 Multi-Dwelling Residential Customers III-19 SOUTHERN CONNECTICUT GAS COMPANY EXHIBIT D-6 RESIDENTIAL SALES (MCF) HISTORY 2022 2023 2024 2025 365,099 346,140 365,890 325,123 268,915 14,388,614 13,233,352 14,025,983 14,946,400 15,186,419 Multi-Dwelling 980,182 1,066,089 1,177,344 1,194,849 1,168,130 Residential Sales 15,733,894 14,645,581 15,569,217 16,466,371 16,623,464 Non-Heating Heating 2026 * *Current year includes 8 months of actual and 4 months of forecasted data. FORECAST 2027 2028 2029 2030 2031 262,239 240,016 217,874 195,786 173,730 Heating 15,334,491 15,302,029 15,289,544 15,280,083 15,257,313 Multi-Dwelling 1,228,648 1,222,507 1,217,197 1,211,925 1,205,804 Residential Sales 16,825,379 16,764,552 16,724,615 16,687,794 16,636,848 Non-Heating III-20 SOUTHERN CONNECTICUT GAS COMPANY EXHIBIT D-7 COMMERCIAL & INDUSTRIAL SALES (MCF) HISTORY 2022 2023 2024 2025 Commericial General Commericial Heating Commercial Sales 5,128,273 6,208,444 11,336,717 5,490,821 5,964,454 11,455,275 6,272,397 6,089,651 12,362,048 5,652,050 6,411,940 12,063,990 5,397,983 6,523,564 11,921,547 Industrial General Industrial Heating Industrial Sales 289,243 227,548 516,790 258,296 203,153 461,449 317,108 193,455 510,563 242,221 150,742 392,962 205,131 147,015 352,146 Firm Special Contract 1,307,607 1,351,025 1,599,976 1,448,454 1,052,577 13,161,115 13,267,750 14,472,587 13,905,406 13,326,270 Commerical & Industrial Sales 2026 * *Current year includes 8 months of actual and 4 months of forecasted data. FORECAST 2027 2028 2029 2030 2031 Commericial General Commericial Heating Commercial Sales 5,652,050 6,411,940 12,063,990 6,184,690 7,910,973 14,095,663 6,226,178 8,144,804 14,370,982 6,267,423 8,197,723 14,465,146 6,309,318 8,250,513 14,559,831 Industrial General Industrial Heating Industrial Sales 242,221 150,742 392,962 251,811 148,376 400,187 254,032 149,501 403,533 256,239 150,674 406,913 258,487 151,840 410,327 Firm Special Contract 1,448,454 1,327,974 1,327,974 1,327,974 1,327,974 13,905,406 15,823,825 16,102,489 16,200,033 16,298,133 Commerical & Industrial Sales III-21 TRANSPORTATION AND NON-FIRM FORECASTING Firm Transportation When SCG’s firm throughput is forecasted using econometric models, the firm transportation and firm sales are combined in the models for better accuracy. The model results are then allocated to the applicable sales and transportation categories using historical percentages. Firm Special Contract These special contracts have specific operational and financial negotiated terms and conditions approved by the PURA and are therefore treated separately. On System Interruptible The methodology for forecasting non-firm sales continues to be one where judgement is heavily relied on. For on system interruptible sales, historical class (i.e. by alternative fuel type) average usage and marketing knowledge were used to project sales and customer counts. This technique was deemed the most accurate and takes into account customer migrations from and/or additions to the interruptible class. Off-System Off system sales history does not impact the integrated resource planning process because the Companies do not acquire gas capacity to make off system sales. The transportation and non-firm Sales forecast are presented in Exhibit D-8. The total sales by class for both firm and interruptible throughput is presented in Exhibit D-9. III-22 SOUTHERN CONNECTICUT GAS COMPANY EXHIBIT D-8 INTERRUPTIBLE SALES AND TRANSPORTATION SERVICES (MCFs) HISTORY 2022 2023 2024 2025 Interruptible Sales 3,682,917 3,546,807 5,020,859 4,332,940 2,872,671 Firm Transportation 3,233,105 2,763,401 2,985,887 2,681,488 2,437,092 40,348 15,558 15,179 20,352 16,165 6,956,371 6,325,766 8,021,925 7,034,780 5,325,928 Interruptible Transportation TOTAL 2026 * *Current year includes 8 months of actual and 4 months of forecasted data. FORECAST 2027 2028 2029 2030 2031 Interruptible Sales 3,959,769 3,959,769 3,959,769 3,959,769 3,959,769 Firm Transportation 2,729,738 2,747,448 2,765,047 2,783,104 2,799,505 17,139 17,139 17,139 17,139 17,139 6,706,646 6,724,356 6,741,955 6,760,013 6,776,413 Interruptible Transportation Transportation Total III-23 SOUTHERN CONNECTICUT GAS COMPANY EXHIBIT D-9 SALES BY CLASS (MMCFS) Actual 2021 - 2025, Budget 2026 8 & 4, Forecast 2027 - 2031 Sales (S) Actuals * 8&4 ** Forecast *** Calendar 2021 2022 2023 2024 2025 Residential 15,700 15,734 14,646 15,569 16,466 Firm (F) Commercial & Industrial 11,011 11,854 11,917 12,873 12,457 Special Contracts 1,268 1,308 1,351 1,600 1,448 Total 27,979 28,895 27,913 30,042 30,372 Interruptible (I) F&I Transportation(T) F&I S&T F&I Total 3,877 3,683 3,547 5,021 4,333 Total 31,855 32,578 31,460 35,063 34,705 Transportation 3,734 3,273 2,779 3,001 2,702 Total 35,589 35,851 34,239 38,064 37,407 2026 16,623 12,274 1,053 29,950 2,873 32,822 2,453 35,276 2027 2028 2029 2030 2031 16,876 16,825 16,765 16,725 16,688 14,496 14,775 14,872 14,970 15,062 1,328 1,328 1,328 1,328 1,328 32,700 32,928 32,965 33,023 33,077 3,960 3,960 3,960 3,960 3,960 36,660 36,888 36,924 36,983 37,037 2,747 2,765 2,782 2,800 2,817 39,407 39,652 39,707 39,783 39,854 * Not Normalized ** Represents 8 months actuals and 4 months forecast *** Normalized III-24 ALTERNATE DEMAND SCENARIOS Introduction There are several different business drivers that can affect the Company’s demand for natural gas. Of these drivers, new customer growth, Normalized Use Per Customer (NUPC), Regulatory or Legislative initiatives, and conservation programs are the main contributors to demand forecasting variability. Any one of these drivers can significantly change the Company’s resource needs. Also, many combinations of these variables can also result in substantially different demand scenarios. Assumptions behind the Alternate Scenarios The drivers of the alternate scenarios include:  High and low customer growth scenarios. The “Base” and “High” customer growth assumption relies on the Company’s forecasted natural gas conversions while the low growth assumes attaining 90% of these projections.  High and low NUPC scenarios. NUPC may have a significant effect on the accuracy of long-term forecasting. Historically NUPC has exhibited a declining trend resulting from increased energy efficiencies, utility conservation programs, and general awareness of energy consumption. Further, NUPC can be influenced by the price of natural gas. The anticipated stable and comparatively low natural gas prices suggest less variability in NUPC trends over the forecast horizon. The “High” demand scenario assumes a 1% higher annual growth rate from the baseline assumption, while the “Low” forecast assumes a 1% lower annual growth rate.  High and low conservation scenarios. The Company’s econometric models implicitly include the impact of historical conservation. The base demand scenario assumes the conservation contemplated in the 2027 Conservation Plan as included in this filing. The high demand scenario assumes conservation savings equal to 1% of firm demand and the low scenario assumes conservation savings equal to 0.12% of firm demand.  Regulatory or Legislative initiatives are primarily focused on the State of Connecticut Department of Energy and Environmental Protection’s (“DEEP”) and PURA policies. The results of these various combinations are presented in Exhibits D-10 through D-12. Exhibit D-10 represents the Company’s most likely (Base) resource requirement, as well as the estimated upper and lower requirements. Exhibit D-11 presents a second base-high-low scenario that contemplates varying degrees of new customer additions to the Company’s distribution system. Exhibit D-12 presents the base-high-low demand estimates assuming varying levels of conservation. III-25 SOUTHERN CONNECTICUT GAS COMPANY EXHIBIT D-10 ALTERNATIVE DEMAND SCENARIOS Total Throughput - Alternative #1 43 42 41 High NUPC, Base Growth, Low Conservation Base Case 40 MMCF's 39 38 37 36 Low NUPC, Low Growth, High Conservation 35 34 33 2027 2028 2029 III-26 2030 2031 SOUTHERN CONNECTICUT GAS COMPANY EXHIBIT D-11 ALTERNATIVE DEMAND SCENARIOS Total Throughput - Alternative #2 42 41 High NUPC, Base Growth, Base Conservation Base Case 40 MMCF's 39 38 Base NUPC, Low Growth, Base Conservation 37 36 35 34 33 2027 2028 2029 III-27 2030 2031 SOUTHERN CONNECTICUT GAS COMPANY EXHIBIT D-12 ALTERNATIVE DEMAND SCENARIOS Total Throughput - Alternative #3 41 Base NUPC, Base Growth, Low Conservation 40 Base Case 39 MMCF's 38 37 Base NUPC, Base Growth, High Conservation 36 35 34 33 2027 2028 2029 III-28 2030 2031 IV. SUPPLY FORECAST SUPPLY FORECAST METHODOLOGY The basic quantitative modeling approach SCG follows in developing the supply to meet anticipated requirements begins with an examination of the various sources of supply that are available on a daily, seasonal, and monthly basis, recognizing the contractual obligations for delivery. As part of this process the Company works to satisfy the projected requirements for every day throughout the forecast at the best possible cost. These supply forecast methodologies consist of transforming the demand forecasts into calendar month usage factors. This requires that the information be segregated into base and heat usage by sales category and service territory so that heat usage factors (heat use per sales category per degree day) can be calculated. Monthly unbilled sales are calculated to transform the billing period sales into calendar period sales so that the supplies can be dispatched on a calendar month basis. The unbilled sales are then allocated to the demand classes. Additional requirements that are also calculated at this point include company use and unaccounted for gas (UAF). All assumptions relating to gas supplies, transportation contracts, storage facilities, and demand projections are entered into the SENDOUT® model. These assumptions are discussed in detail in the appropriate sections of this filing. The SENDOUT® model then determines the best cost manner in which to allocate supplies, determines the appropriate level of curtailments to the company's interruptible sales classes, and calculates the amount of fuel gas required to meet SCG's customer’s needs. The gas supply planning process is focused on the objective of full reliability over the short and long term for firm customers under all weather conditions on a best cost basis. The forecast planning process also involves continuous monitoring and participation in the external environment which is a qualitative aspect of the strategic supply planning process. This involves working closely with demand planning, marketing, and conservation in coordination of planning activities. There is a complicated and sometimes controversial set of factors that can impact energy demand and supply. Externally the gas supply department is closely involved with customers, pipelines, regulators, producers, peer companies, financial companies, industry groups and associations and other stakeholders to understand industry dynamics. Issues that impact demand and supply are reviewed including, but not limited to, regional infrastructure reviews, energy issues and analysis, state legislative and regulatory policy related to the energy industry and particularly topics that affect capacity planning, federal regulatory policies and legislation that may impact gas demand and the role of various fuels, decarbonization/clean energy matters and trends, monitoring of new gas supply sources and activities of producers and developers, monitoring new technologies related to exploration, production, transport, relative emissions and use of natural gas, monitoring the role of renewable energy and ongoing evaluation of energy issues and markets in the region and including electricity and alternate fuels as well. IV-1 SUPPLY FORECAST ASSUMPTIONS The purpose of the gas supply planning process is to provide best cost, fully reliable service to our customers under all weather conditions over all time horizons to address growth and foster customer satisfaction. Certain key assumptions support the objectives of the process that take into account energy market facts, conditions and projections from the source of supply to the customer burner tip, customer needs and projections for use of gas compared to other energy sources, regulatory decisions and policies, relevant industry information and issues, operational and other considerations and strategic matters. The following are key assumptions that underlie this supply plan. Existing Portfolio of Supply, Firm Transportation, Storage and Peaking The Company, over decades through present using a continuous strategic process has developed, manages and operates a PURA regulated portfolio of resources to provide best cost, fully reliable service to our customers under all weather conditions over all time horizons, now and into the future. The resource portfolio is designed based upon specific planning criteria and it is comprised of a relatively balanced combination of firm transportation from supply sources, firm transportation from gas storage withdrawal sources and a peaking facility. The Company holds many interstate pipeline firm transportation and storage contracts and operates a peaking facility on behalf of our customers as part of the portfolio. Current Contract Portfolios Exhibits S-3.1- S-3.5 contains details of the Company’s current contract portfolios comprised of transportation and storage and peaking. The existing contract portfolios are maintained for the forecast horizon and expiring firm transportation and storage contracts are assumed to be extended per the rights available to the Company per FERC tariffs. Conservation/IRP The Company’s planning process considers the overall impact of conservation plus capacity needs. Cost effective conservation vis-à-vis avoided capacity costs is applied as a reduction to peak day demand and capacity needs, as are demand side management techniques. After applying the cost-effective conservation, the current level of capacity resources under contract is projected to remain required. Detailed information regarding conservation is included in the annual Conservation Plans filed with the Department. Gas Storage Injections and Withdrawals The gas storage withdrawal season has been generally defined as the period between November 1 and March 31 of each year. The gas storage injection season has been defined as the period between April 1 and October 31 of each year. Demand The forecasted customer demand and seasonal supply balances are reflected on a normal (Exhibit S-1) and design weather basis (Exhibit S-2). Customer demand projections being supported by the supply plan are based upon facts and sophisticated projections. The projections are made from a realistic, best information perspective and may or may not be consistent with all opinions and aspirations. There is a recognition that such forecasts are predictions and, as such, are prone to variation. From a supply planning perspective it is appropriate to be conservative and safe on behalf of the customer/public need for reliability and to strive to reduce supply/capacity risk. IV-2 Transportation Service Based upon the Department’s various decisions related to reliability of service and provision of transportation service for commercial and industrial customers, the Company’s forecast reflects the following principles: 1) LDCs must plan for and maintain sufficient capacity to meet 100% of firm gas customer’s requirements on the design day. 2) Primary firm pipeline capacity and on-site peak shaving are used for design day needs. 3) LDCs perform the supplier of last resort function for 100% of firm gas customer’s requirements excluding special contracts. Capacity not assigned/used for the services provided for #4 below, is the primary tool available to the LDC’s to effectively and reliably perform the supplier of last resort role. 4) Firm transportation volumes other than special contracts are supplied using LDC capacity/supply for 25% of the marketer MDQ. Of this 25% of MDQ amount, one-half is long haul capacity release, and one quarter each is tariff gas storage and tariff gas peaking. Supply Strategy The forecast assumes that the Company will continue the gas supply strategy outlined in the table below: Category: Supply management: Market Actions: Commodity Pricing: Role of Storage: 365 Firm Capacity: Produced Gas (i.e. LNG): Portfolio Makeup: Contract Flexibility: New Capacity Strategy: Direct control Active Market Participation Major supply sources - diversity of capacity source/supplier Key winter supply role for reliability, diversity, balancing Well-suited for high load factor and storage injection For peaking on the coldest days of the year and operational support Balanced and comprised of flowing supply from major supply sources, storage and peaking Varying terms with unilateral rights to extend Added in advance as necessary to meet growth needs and in quantities that recognize the sporadic and uncertain nature of capacity opportunities-therefore each LDC will typically have a growth margin of 5 or more years of growth ((based upon a conservatively high case growth) in its peak day demand/supply balance to ensure capacity is available short and long term. IV-3 SENDOUT® - GAS PLANNING SYSTEM System Description Ventyx’s SENDOUT® gas supply optimization system minimizes the cost of serving demand within a single- or multiple-area distribution system for planning horizons ranging from one day to twenty years or more. The basic problem that SENDOUT® addresses is as follows: Given...     the system demand forecast, potential supplies, along with their costs and delivery capabilities, the company's reliability criteria, and the study horizon of interest, SENDOUT® determines which contracts should be used and how purchases should be scheduled from these contracts in order to meet the demand and reliability requirements in a least cost fashion. The answer to this problem is called the best cost solution since SENDOUT® determines the least cost solution within given constraints. SENDOUT® employs an algorithm that uses a full Linear Program (LP) along with network optimization to solve the gas supply planning problem. By using the linear program, a proven global optimization technique, SENDOUT® automatically takes physical limitations and contract constraints into account, and finds the minimum cost dispatch of the system for the study period. SENDOUT® looks at the complete problem at once, taking into account thousands of variables and evaluating thousands of possible solutions, in order to generate the best cost solution. When SENDOUT® is initially set up, the minimum data requirements consist of the names of the demand areas, demand classes, temperature patterns, supply contracts, storages, transportation segments and interconnects for the gas supply system. The interconnects can be considered the nodes in the SENDOUT® delivery network and typically are used to represent receipt (or delivery) points. SENDOUT® allows multiple flowing gas contracts to serve the system, with each supplying as many interconnects as are necessary (multiple receipt/delivery points). Physical and contractual constraints can be specified, such as maximum flow levels and minimum flow percentages, on a daily, monthly, seasonal, or annual basis. When a contract requires a minimum flow, SENDOUT® automatically determines when the gas should be taken in order to minimize the total system cost. SENDOUT® uses standard gas contract costs; the rates may be changed on a monthly or daily basis. In addition, supply cost and flow information may be input at a receipt/delivery point level, if desired. SENDOUT® allows multiple storage sources (either leased or company-owned, either natural or production gas) to serve the system. Storage input data include the minimum or maximum inventory levels, minimum or maximum injection and withdrawal rates, injection and withdrawal IV-4 fuel loss, to and from interconnects, and the period of activity (i.e., when the gas is available for injection or withdrawal). There is also the option to define and name volume-dependent injection and withdrawal percentage tables (ratchets) which can be applied to more than one storage. SENDOUT® uses standard storage contract costs; the rates may be changed on a monthly basis. SENDOUT® provides the means to model a pipeline/distribution system using segments and interconnects. Segments define flows, costs, and fuel loss for transportation contracts. Flow values include minimum and maximum daily quantities available for sale to gas markets or for release. Cost values include standard fixed and variable transportation rates, as well as a per unit cost generated for released capacity. Multiple demand areas can be defined in SENDOUT®, each served by as many or as few sources as is appropriate. Classes of demand can then be defined within each area. SENDOUT® may be used to compute the demand forecast for each demand class given a customer level, their usage factors, and daily temperatures. Alternatively, demand levels can be entered directly as daily or monthly forecasts by area or for the system as a whole. To solve the problem, SENDOUT® determines the supply contract takes, storage injection and withdrawal schedules, and transportation dispatch that minimize the total variable operating cost, given the physical and reliability constraints. Costs taken into account in this process include:         Supply contract commodity costs Transportation costs Storage injection costs Storage withdrawal costs Storage carrying costs Storage transportation costs Fuel costs for supplies, storages, and transportation segments Alternate fuel costs for demand classes (if defined). SENDOUT® minimizes the total system variable operating cost subject to the daily flow constraints on system segments; storage injection and withdrawal maximum rates; daily, monthly, seasonal, and annual flow constraints on supplies; and storage inventory limits. The default assumption is that all forecast demand will be served if at all possible. The priority of service may be optionally designated by demand class for economic dispatch and/or load curtailment categorization. Starting balances are defined for each storage, as well as any desired minimum or maximum inventory levels during or at the end of the optimization interval. In making the decision on how and when to inject into or withdraw from storage, SENDOUT® always obeys user-defined constraints. In the absence of constraints, the trade-off is economic. For instance, on a given day in winter, is it economically better to buy a unit of gas on the next available supply contract, leaving gas in storage to incur carrying costs (if defined) and avoiding refill costs? Or is it better to withdraw a unit of gas from storage, avoiding carrying costs, but requiring that gas be injected into storage at a later date (perhaps when supply costs are lower)? IV-5 SENDOUT® and Southern Connecticut Gas SCG feels that it is important for readers of its filing to understand the modeling methods that SCG incorporates when preparing its forecast. It should be understood that the development of this model is a continually evolving process and that the results presented in this filing represent a “snapshot” of the environment under which SCG is currently (or expects to be) operating during the current forecast period. The model reflects an up-to-date representation of SCG's current and potential supply portfolio, transportation contracts, customer demand, transportation customer activity, conservation programs, distribution system constraints, and the regulatory environment. Microsoft® is a registered trademark of Microsoft Corporation; Windowstm is a trademark of Microsoft Corporation IV-6 SUPPLY FORECAST CONCLUSIONS Peak Day SCG forecasts that given the projected end-user transportation, demand, and supply, and taking into consideration the forecast assumptions regarding the availability of supplies and transportation, there will be no deficiencies in meeting peak day requirements throughout the forecast horizon. There are no interruptible sales on the peak day. Winter Periods During the winter periods SCG forecasts sufficient supplies to meet all firm requirements, assuming the availability of supplies/capacity reflected in this forecast. As is typical in actual operations, there are supply curtailments to interruptible customers particularly during colder weather conditions. Summer Periods SCG projects that sufficient summer supplies will be available to meet customer requirements and to refill SCG's storage facilities. SCG expects to be able to fill storage with competitively priced supplies from various locations. Annually On an annual basis SCG projects that sufficient supplies will be available throughout the forecast period to meet firm customer requirements. Exhibits S-1: Seasonal Custo