Docket 05-07-14PH02
DPUC Investigation of Measures to Reduce Federally Mandated Congestion Charges (Long Term Measures)
Decisions and notices12
What the Authority has issued in this docket, newest first.
Filings567
Showing 301–350 of 567 filings
- Pullman & Comley
- Prospero LLC
Qualifications for Proposal for Suffield Power Project
- NRG Energy, Inc.
Qualifications for Proposal for Devon Power for Repowered Generation
- NRG Energy, Inc.
Qualifications for Proposal – Montville
- NRG Energy, Inc.
Qualifications for Proposal – Middletown
- NRG Energy, Inc.
Qualifications for NRG Devon Generation Project
- Northeast Utilities
Qualification Package and Proposal
- NE Energy Services
Qualifications for Proposal – 1: One Combustion Turbine and Upgrade to Shepaug Hydro Turbine
- NE Energy Inc.
Qualifications for Proposal – 2: Two combustion turbines and upgrade to Shepaug hydro turbine
- Mill River Power (Harbert Power)
Qualifications for Proposal for Evergreen Power Project – Part 2 of 2
- Mill River Power (Harbert Power)
Qualifications for Proposal for Evergreen Power Project – Part 1 of 2
- Maxim Power
Qualifications for Proposal – Entire Filing Submitted under Protective Order
- Maxim Power Corp.
Qualifications for Proposal – Entire Filing Submitted Under Protective Order
- Lake Road Generating Company--B
Qualification Proposal to reduce the Impact of FMCCS – Option B
- Lake Road Generating Company--A
Qualification Proposal Option A to reduce the Impact of FMCCs
- GE Financial Services
Qualifications for Proposal
- EMCOR Energy Services
Qualifications for Proposal
- Consumer Powerline
Qualifications for Proposal to reduce the Impact of FMCCs
- Comverge
Qualifications for Proposal – Entire Filing Submitted Under Protective Order
- CMEEC
Qualifications for Proposal
- Bridgeport Energy
Qualification Submission for Bridgeport Energy
- Boston Power Supplies
RFP Qualifications
- Ameresco
Qualifications for Proposal – Program 1
- Ameresco
Qualifications for Ameresco Program 2
- Ameresco Program 3
Qualifications for Ameresco Program 3
- GE
Written Exceptions
- RE
withdrawal from 2006 RFP program
- United Illuminating
Written Exceptions
- Rubin and Rudman LLP
Written Exceptions
- Rubin and Rudman LLP
Written Exceptions
- NRG Energy
Written Exceptions
- Kleen Energy Systems
Written Exceptions
- Connecticut Municipal Electric Energy Cooperative
Written Exceptions
- CL&P
Written Exceptions
- RE
regarding dates for extension
Ruling: Other
Draft Decision
- Waterside Power
Request for Exension of Proposed Schedule for RFP
- Pullman & Comley, LLC
Written Comments
- Murtha Cullina
NRG Post-Bidders' Conference Comments
- United Illuminating
Written Comments
- RE
Written Comments
- DPUC
Ruling: Denied
- DPUC
Ruling: Granted
- DPUC
Ruling: Denied
- RE
commetns solicited at pre-bid conference
- RE
Written Comments
- RE
bidder registration - generation
Transcript: Prebid Conference
- Rubin & Rudman
Written Comments
About this docket
- Docket number
- 05-07-14PH02
- Status
- Closed May 3, 2007
- First filing
- October 14, 2005
- Latest filing
- June 17, 2022
- Public filings
- 567
- Documents
- On the current system
Schedule
Dates for hearings, deadlines, and decisions.
- Docket schedule
Revised July 25, 2007
Search this docket
Reading a docket
- Motions ask the Authority for something; each gets a ruling.
- Interrogatories are written questions, usually from Authority staff; the answers are filed as responses.
- A draft decision comes before the final decision; participants may file exceptions to it.