Docket 08-01-01
DPUC Review of Peaking Generation Projects
Decisions and notices12
What the Authority has issued in this docket, newest first.
Filings757
Showing 1–50 of 222 filings of the selected types
- d
Corres. 05/31/2012 () - PSEG hereby notifies you that on May 30, 2012, it has submitted documentation to CL&P to satisfy the requirements of Section 2.6 (d) of the Agreement.
- c
Corres. 05/31/2012 () - PSEG hereby notifies you that on May 25, 2012, it has submitted documentation to CL&P to satisfy the requirements of Section 2.6 (c) of the Agreement.
- a
Corres. 05/31/2012 () - PSEG hereby notifies you that on May 23, 2012, it has submitted documentation to CL&P to satisfy the requirements of Section 2.6 (a) of the Agreement.
- PSEG
Contract for Differences Section 2.6 (h).
Confirmation from ISO-NE that interconnection service is available.
- PSEG New Haven, LLC
Project Milestone Status Report for the New Haven Peaking Project
- Holland & Knight
Force Majeure
- PSEG New Haven
Force Majeure Notification - Snow Storm on 10/29/11
- Pseg Services Corporation
In accordance with Section 2.5(a) of the Peaking Generation Cost of Service Contract for Differences between PSEG New Haven LLC (“PSEG”) and the Connecticut Light and Power Company (“CL&P”), dated August 8, 2008 (“Agreement”), PSEG hereby submits this project milestone status report.
- GenConn Energy LLC
GenConn Force Majeure Event
- Pseg Services Corporation
Project Milestone Status Report
- Northeast Utilities
Filing Concerning Commercial Operation
- GenConn Energy LLC
Affidavit of Judith Lagano in support of Motion #61 for Protective Order
- The United Illuminating
GenConn's Achievement
- PSEG Services Corp.
joint submittal of PSEG Power CT and PSEG New Haven of a request for approval from the DPUC to transfer PSEG Power CT’s Peaking Generation Cost of Service Contract for Differences with CL&P, dated 8/8/08 to PSEG New Haven.
- Levitan & Associates, Inc.
Correspondence
- Pseg Services Corporation
PSEG Power Connecticut letter of modifications to Attachment A.
Letter re: Intent of change
- Genconn Energy
GenConn Modifications to Attachment No. 2, from Final Decision in Dkt. 08-01-01
- Genconn Energy
GenConn Financial Assurance
- Genconn Energy
GenConn Informational Letter, GenConn Middletown
- PSEG Services Corp.
Mileston Status Report
- PSEG Services Corp.
Status Report
About this docket
- Docket number
- 08-01-01
- Status
- Closed again October 5, 2011
- First filing
- February 15, 2007
- Latest filing
- October 15, 2021
- Public filings
- 757
- Documents
- On the current system
Schedule
Dates for hearings, deadlines, and decisions.
- Docket schedule
Revised July 14, 2010
Search this docket
Reading a docket
- Motions ask the Authority for something; each gets a ruling.
- Interrogatories are written questions, usually from Authority staff; the answers are filed as responses.
- A draft decision comes before the final decision; participants may file exceptions to it.