Showing 101–150 of 237 filings
- Department Of Energy And Environmental Protection
- Pullman & Comley, Llc
Correspondence re addition to service list
- NuPower Bridgeport FC LLC
Request for Clarification
- Pullman & Comley, LLC
NuPower Updated Interconnection Cost Estimate and Cost Recovery Proposal
- Uil Holdings Corporation
UI Final Facilities Study Report
- PURA
Ruling: Granted
- Pullman & Comley, LLC
Update on Status of Interconnection
- Uil Holdings Corporation
UI Monthly Interconnection Process Status Update
- UI
UI Motion for an extension of time to submit Order No. 2 - Final Facility Study.
- Uil Holdings Corporation
UI Monthly Interconnection Process Status Update
- Pullman & Comley, Llc
Update of Interconnection with UI
- Uil Holdings Corporation
UI Monthly Interconnection Process Status Report
- Pullman & Comley, LLC
Interconection Status Report
- Uil Holdings Corporation
UI Monthly Interconnection Process Update
- Uil Holdings Corporation
UI Monthly Status Update of Interconnection Process
- Pullman & Comley, Llc
Status of NuPower's Interconnection with UI
- PURA
Ruling: Granted in part - Denied in part
- Uil Holdings Corp.
UI / Monthly Interconnection Process Status Update
- Pullman & Comley, LLC
Interconection Status Report
- Pullman & Comley, LLC
Response type: Objection
- UI
UI submits a Motion to stay additional compliance filings relative to Order No. 2 of the Decision dated October 2, 2019.
- PURA
PURA's response to UI's November 7, 2019 compliance filing
- Uil Holdings Corporation
UI's Monthly Update on the Status of Interconnection Process
- Pullman & Comley, Llc
Compliance filing re interconnection with UI
- Uil Holdings Corporation
UI Revised PPA with Modifications
- UI
UI Motion for Extension to file Revised PPA
- Uil Holdings Corporation
UI Monthly Update on Status of Interconnection Process
- Uil Holdings Corporation
UI Status of Revised PPA
- Pullman & Comley, Llc
Interconnection Status Report
- Representative Tom Delnicki
Comments
Final Decision
- Representative Tom Delnicki
Comments
- Representatives: Gresko, Arconti, Stafstrom, Steinberg & Ali-Brennan - Senators: Formica, Bradley & Duff
Comments
Posted in Error, see Docket 98-06-17
- International District Energy Association
Comments
- UI
Written Exceptions
- Office of Consumer Counsel
Written Exceptions
- NuPower Bridgeport FC
Written Exceptions
- DEEP - BETP
Written Exceptions
- NuPower Bridgeport FC
Filed in Error by Filer. Request to Expedite Issuance of Draft Decision
Draft Decision
- Vic Mulaire, President & Founder of Nest Arts Factory
Comment
About this docket
- Docket number
- 18-08-14
- Status
- Closed October 2, 2019
- First filing
- August 16, 2018
- Latest filing
- November 12, 2026
- Public filings
- 237
- Documents
- On the current system
Schedule
Dates for hearings, deadlines, and decisions.
- Docket schedule
Revised September 12, 2024
Search this docket
Reading a docket
- Motions ask the Authority for something; each gets a ruling.
- Interrogatories are written questions, usually from Authority staff; the answers are filed as responses.
- A draft decision comes before the final decision; participants may file exceptions to it.