Interrogatory responses
Answers to questions 1, 2, 3
Filed by Connecticut Light and Power Company dba Eversource Energy3 files
Part of docket 26-05-10Files3
CLF-AC-001_Final.pdf
PDF · 570 KB · 45 pagesText searchable
Download CLF-AC-001_Final.pdfRead the text of CLF-AC-001_Final.pdf
CLF-AC-002_Final.pdf
PDF · 357 KB · 17 pagesText searchable
Download CLF-AC-002_Final.pdfRead the text of CLF-AC-002_Final.pdf
CLF-AC-003_Final.pdf
PDF · 476 KB · 29 pagesText searchable
Download CLF-AC-003_Final.pdfRead the text of CLF-AC-003_Final.pdf
Search terms highlighted
Eversource rate increase is on 42 pages across 3 files of the text below, highlighted. Go to the first matchClear highlighting
Page 9 of 45
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set CLF-AC-01 Date Issued September 16, 2026 CLF-AC-001 Page 9 of 45 This means that -- even if 100% of [the future incremental capital investment was] only partially supported with CT-Bar revenues (i.e. revenue covering depreciation expense and property taxes only); and even if the Company’s future cost of service otherwise was 100% supported with rates; and even with perfect operational decision making -- the Company would still need to find $124.1 million of annual savings by Rate Year 4 in order to offset the loss of revenue associated with carrying costs on incremental investment over the term of the PBMRP, which would be necessary to commit to a stay-out term. For perspective, the total O&M expense included in the Company’s cost of service filed in this proceeding is $547.5 million. Thus, to earn its authorized ROE, all else equal, the Company would have to generate cost savings amounting to $124.1 million, or nearly 23%, of its Rate Year O&M level by Year 4, to offset the impact of the accumulating carrying costs on the incremental capital additions completed on the system after base rates are set in this case. This is nearly 34% of operating expense, excluding vegetation management and storm restoration costs, which is a very substantial proportion of the cost of service. For example, the amount of $124M is nearly two-thirds of the Company’s labor and labor-related operating expense, or 60% more than the entire vegetation management program. It simply is not possible for the Company to cut this level of O&M expense without grossly debilitating the Company’s ability to provide service to customers. In fact, it is not plausible to expect that the Company could generate even 10% in annual incremental O&M savings in the face of 2-3% annual inflation and, as a result, the Company could not agree to a stay out under circumstances where there is no recovery of the cost of capital on incremental investment over the PBMRP term. Moreover, even if the Company were somehow able to find such remarkable cost savings, the going-in revenue requirement of the subsequent multi-year rate plan would capture those cost savings. Assuming continuation of the same PBR framework and required system investment, the Company would again be in the position of having to find an additional 34% of O&M savings (i.e. more than 60% cumulatively from Rate Year 1) in order to sustain itself over the next PBR term. Clearly, a framework that does not provide revenue supporting the full cost of incremental investment over a four-year period, as well as the next four-year period, is not a plausible or lasting framework. Thus, exclusion of the cost of capital from a capital support mechanism in an environment in which significant increases in capital investments are expected all but ensures the Company has no realistic opportunity to survive the PBR term without a critical need for a rate case to realign costs and rates.Page 10 of 45
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set CLF-AC-01 Date Issued September 16, 2026 CLF-AC-001 Page 10 of 45 Consequently, the overall framework as outlined in the REO1-PFD had no practical chance of sustaining the Company financially for the four-year term, nor would the Company have been able to even agree to a stay-out. The Company fully embraces the notion of incentivizing the utility to strive for cost efficiency under a PBR framework. However, excluding the cost of the capital, which is a fundamental and necessary cost associated with the infrastructure investment necessary to achieve the objectives outlined in the PBR plan is not a tool capable of delivering that outcome. Based on its current assessment of the substantial distribution system needs, the Company expects that it would need to file rate cases every 18 months or sooner, if possible, if the CT-bar were to be implemented as contemplated in the RE01-PFD. Please refer to the Company’s response to interrogatory EOE-156 for additional discussion of the alternatives available to the Company in the absence of a viable, sustainable multi-year rate plan. Thus, this critical deficiency of CT-bar is not a design feature of a sustainable multiyear framework and as such is not included in the Company’s proposed F-Factor. 4) “I-X” Both the RE01-PFD and the Company's proposed PBMRP include an inflationbased component within the revenue cap formula. However, the two approaches differ fundamentally with respect to both (1) the revenue base to which inflation is applied and (2) the economic purpose the inflation mechanism is intended to serve. Under the RE01-PFD, the I-Factor would be applied broadly to the utility's revenue requirement, including capital funding mechanisms. As the RE01-PFD states: [t]he Authority will apply the I-Factor to all variables within the Revenue Cap Formula, capital funding mechanisms (i.e., CT-Bar and any potential Capital Cost Trackers), PIMs, SSMs, and regulatory assets and liabilities." (PFD Appendix A, page vi). In contrast, the Company's PBMRP proposal intentionally limits application of the I-X mechanism to operating and maintenance ("O&M") costs, excluding catastrophic storm expense. The Company does so because the proposed PBMRP separately addresses capital-investment-related revenue requirements through the FFactor, which directly reflects the revenue requirement associated with incremental capital investment, including plant additions, cost of removal, depreciation, taxes, and the cost of capital.Page 11 of 45
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set CLF-AC-01 Date Issued September 16, 2026 CLF-AC-001 Page 11 of 45 This distinction reflects an important economic principle. Inflation measures are reasonably suited to address changes in operating costs such as labor, contractor services, materials, and other routine expenditures that are consumed in providing service. Capital-investment requirements, however, are not determined by general inflation. Rather, they are determined by the actual infrastructure needs of the electric distribution system, including reliability, resiliency, modernization, asset replacement, cybersecurity, and other system requirements. The revenue support necessary for those investments is further determined by the financing required to attract capital from investors in competitive capital markets. Accordingly, the Company's PBMRP separates the revenue support necessary for operating expenses from revenue support adjustment associated with capital infrastructure investment. The I-X mechanism addresses changes in operating costs while the F-Factor addresses changes in capital-related revenue requirements. Each mechanism is therefore aligned with the category of costs it is intended to support. The RE01-PFD framework did not make this distinction. Because the RE01- PFD would apply the I-Factor to revenue streams associated with capital-support mechanisms while also maintaining separate capital-recovery mechanisms such as CT-Bar, the inflation adjustment and capital-funding mechanisms become interrelated rather than functionally distinct. By contrast, the Company's proposal establishes a clearer allocation of responsibility between mechanisms: operatingcost changes are addressed through I-X, while capital-investment requirements are addressed through the F-Factor. Consistent with this approach, the Company proposes an inflation measure based on Gross Domestic Product Price Index ("GDPPI") and Employment Cost Index ("ECI"), indices that are more closely associated with the underlying drivers of utility operating costs. Because capital-investment-related revenue requirements are separately addressed through the F-Factor, there is no need for the inflation mechanism to provide additional revenue support for capital additions. The result is a more transparent and internally consistent framework in which each component of the revenue cap formula serves a distinct purpose. The I-X mechanism addresses operating-cost pressures and efficiency incentives, while the F-Factor provides revenue support for prudent capital investment necessary to maintain a safe, reliable, resilient, and modern electric distribution system.Page 12 of 45
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set CLF-AC-01 Date Issued September 16, 2026 CLF-AC-001 Page 12 of 45 5) Consumer Dividend While the Company's proposed S-Factor includes a benchmarking-based tiered approach that adjusts based on the Company's core O&M performance per customer relative to a benchmark, it does not align with the methodology described in the RE01-PFD in Docket No. 21-05-15RE01, under which highly efficient utilities would have an S-Factor of zero. Under the Company's proposal, the S-Factor has a floor of 30 basis points, meaning customers receive a 30-basis-point reduction relative to inflation even when the Company is classified in the highest performance tier. By contrast, the PFD described a framework under which highly efficient utilities would have an S-Factor of zero, resulting in no reduction relative to inflation. Further, the PFD's discussion of the S-Factor was conceptual in nature. The PFD described potential benchmarking and tiering concepts and provided illustrative examples, but it did not establish the specific benchmarks, indices, thresholds, tiers, or other parameters that would be necessary to implement such a mechanism. Accordingly, while the Company's proposal incorporates benchmarking and tiering concepts similar to those discussed in the PFD, it does not adopt the specific zerofloor approach described therein. 6) Exogenous Cost Recovery The Company provided comparison of its exogenous cost recovery proposal to the RE01-PFD in response to interrogatory OCC-430 v. In summary, the RE01-PFD’s setting of the exogenous cost recovery threshold at 0.75% is considerably higher than the thresholds established in other jurisdictions. The Company’s proposed 0.5% is more closely to those other jurisdictions, as shown in the footnote the RE01PFD references. The Company’s complete response to OCC-430 is provided here: The 0.75% materiality threshold proposed in the Docket No. 21-05-15RE01 Proposed Final Decision is unnecessarily high, and inconsistent with other jurisdictions. Although the Company supports the intention of establishing a materiality threshold as a means of balancing administrative burden with the Company’s need to cover the costs of service, including those over which it has no control, a materiality threshold set too high actually renders the mechanism increasingly ineffective, raising the likelihood that the utility cannot commit to the PBR stay-out because it will be unable to obtain a fair or reasonable level of recovery of its operating costs, also barring customers from benefitting from the efficiency gains that come from an extended stay-out.Page 13 of 45
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set CLF-AC-01 Date Issued September 16, 2026 CLF-AC-001 Page 13 of 45 In the extreme, a materiality threshold of 10%, for example, would indicate that for an event to qualify as exogenous in terms of its materiality, it must be at least $192.19 million ($1,921.9 million revenue requirement x 10%, using the Company’s cost of service filed in this proceeding). The likelihood of a single event meeting this criteria is exceedingly rare, meaning the Z-factor, in practice, would be effectively rendered moot. Additionally, PURA provided no basis for how it determined a threshold of 0.75% was appropriate. In fact, in its proposed final decision, PURA stated, “[t]he threshold [of 0.75%] better aligns with the thresholds established in other PBR jurisdictions,” and then provided the following footnote referencing those other jurisdictions, each one of which is substantially below the 0.75% it proposed: “Hawaii set thresholds equivalent to 0.2%, 0.25%, and 0.28%; Ontario set a threshold equivalent to 0.5%; Massachusetts set a threshold equivalent to 0.37%; and Alberta Utilities Commission set a threshold equivalent to 0.25%.” The Company’s proposed Z-Factor of 0.5% is more closely aligned to those other jurisdictions. (emphasis added) (c) As discussed in the Company’s response to (a) above, the Company’s proposal intentionally tracks with the developing framework outlined in the RE01-PFD, yet reflects the modifications necessary for the overall function of the plan to be a sustainable, lasting framework for the state of Connecticut, one capable of delivering on the promise of PBR. As discussed extensively in the Company’s responses above as well as in its written comments in response to the RE01-PFD, the draft framework outlined in the RE01-PFD had fatal flaws that all but guaranteed failure as a ratemaking construct for the state of Connecticut. The Company’s own extensive involvement throughout that docket, including participation in technical sessions, data requests, and analysis provided on the record, informed the conclusions stated above. Consequently, the Company did not perform additional analysis to (again) confirm that the framework outlined in the RE01PFD was deficient, without modification, as a long-term ratemaking solution and incapable of realizing the essential benefits to Connecticut and its customers that a successful PBR plan offers. Prior Referenced Responses: i OCC-423 Question:Page 14 of 45
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set CLF-AC-01 Date Issued September 16, 2026 CLF-AC-001 Page 14 of 45 Exhibit CLP-ELP-1 Please explain in detail why the Company believes its proposed treatment of capital expenditures under the PBMRP, including the use of forecasted capital expenditures and the F-Factor, is preferable to including capital expenditures within the Revenue Cap Formula framework as proposed in the Docket No. 21-05-15RE01 Proposed Final Decision. In your response, a. Please explain why the Company believes O&M expenses are appropriately subject to an externally indexed revenue cap, while capital expenditures require separate recovery through an F-Factor based on a fixed annual capital investment forecast. b. Please explain how the Company's proposed treatment of capital expenditures is expected to produce customer cost savings or otherwise improve customer affordability relative to including capital expenditures within a revenue cap formula. c. Please explain how the proposed F-Factor mitigates or avoids any incentive to favor capital expenditures over O&M solutions, including in circumstances where either a capital or O&M solution could be used to address the same system need. OCC-423 Response: The Company appreciates OCC’s thoughtful and analytical questions on the Company’s proposed performance based multi-year rate plan (“PBMRP”) and looks forward to further discussion on the development of a workable PBR framework for the Company’s customers. To cover the issues raised in the question, the Company’s response is organized as follows: 1. Review of relevant aspects of the Company’s PBMRP. 2. Considerations on the design of capital-driven revenue support. 3. Specific responses to parts (a), (b) and (c), above. 1. Review of the Relevant Aspects of the Company’s PBMRP Ultimately, the Company’s goal in this proceeding is to establish a sustainable, cohesive ratemaking framework that advances electric utility service in the State of Connecticut in an affordable manner for customers, over a long term. This is the Company’s goal because the CL&P system needs investment for reliability, resiliency and modernization. For this investment to be affordable for customers, a coherent ratemaking plan needs to be instituted that will consider the interests of customers over a longer term than just the next rate case. That framework needs to balance: (1) the reliability and performance requirements of the Company’s customers and the broader State of Connecticut; (2) customer rate stability and affordability; (3) incentives for cost efficiency in utility operations; and (4) implementation of a revenue support mechanism sufficient to cover the cost of delivering these objectives to customers. The Company’s PBMRP is designed to address these objectives in a holistic, balanced way. To do this, the Company started with the ratemaking framework under discussion in PURA’s PBR docket (Docket No. 21-05-15RE01), while also introducing certain new elements to remediate the flaws that would ultimately hinder PURA’s (draft) PBR model from supporting the necessary stay-out terms. For any multi-year rate plan to be successful, it needs to be grounded in the reality of the utility’s costs, while also incorporating features that innately push the utility to be more efficient. That is not to say every dollar of the utility’s costs will be (or should be) recovered. Rather, the allowed revenues need to be sufficient to afford the utility a reasonable opportunity to cover its cost of service to customers, including a reasonable rate of return on equity (“ROE”) where the utility is operating prudently and efficiently, as required by state law. A framework in which the utility has no reasonable opportunity to earn its ROE, regardless of how hard it strives for efficiency, simply becomesPage 15 of 45
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set CLF-AC-01 Date Issued September 16, 2026 CLF-AC-001 Page 15 of 45 self-defeating because the utility will exercise its statutory rights to a distribution rate proceeding, thereby muting the most powerful efficiency feature of a multi-year rate plan, which is the stay-out term. A framework that underestimates the actual cost to run the system and/or affords the utility no reasonable chance to earn its allowed ROE, year after year, also results in under-investment and a system that not only lacks innovation, but falls further and further behind at a significant – albeit potentially unseen – cost to customers. As a result, a lasting, productive framework is one that is soundly informed by – not detached from – the drivers of the utility’s real cost of service, including its cost of capital. In this context, the two most critical features of the Company’s PBMRP are as follows: • A going-in revenue requirement that reasonably reflects the Company’s actual operating expenses and cost of investment in the Rate Year, so that through effective management and prudent decision making, the Company can achieve the true efficiency gains that will be needed to stretch the approved revenue requirement over the stay-out term. Without a reasonable opportunity to maintain financial integrity over a stay-out period, as measured by the authorized ROE, the utility cannot focus on innovation and efficiency gains – and will instead file for the next rate case to make up ground. To accomplish this goal, the overall paradigm must “hang” together, making the base revenue requirement a pivotal element. The many components of a PBR plan, including going-in rates, as well as the subsequent rate adjustments, must work in concert with performance objectives and the capital investment requirements expected of the Company – for the benefit of customers, i.e., the entire framework must work to the benefit of customers, not only in relation to the price they will pay, but also in relation to supporting the level of service that they need and expect. • Revenue support for incremental capital investment to support long-term system goals. The Company operates in a capital-intensive industry and has a substantial need to acquire cash on a systematic basis to operate its business. As annual capital investments regularly exceed net cash from operations (i.e. cash receipts from customers net of operating cash outflows), the Company must look to other capital sources to fund those investments. Those sources are the debt and equity investors supplying the cash to capital markets. This means the Company must compete with all other entities participating in those markets to attract capital. It is simply not possible for the Company to go to those markets and demand cash for free, or at belowmarket rates relative to the investor’s risk when other entities participating in the same capital markets offer compensation for the use of funds over time. The Company provided extensive analysis and discussion on the cost of capital throughout Docket No. 2105-15RE01, including specifically as it relates to CT-Bar. PURA’s treatment with respect to going-in revenue requirements as well as any ongoing capital-driven revenue support mechanism, such as CT-Bar, is paramount to whether the Company, with effective management and sound decision-making, can responsibly cede its right to file for a rate amendment, whereas that is otherwise the only tool the utility has to align its revenues and costs and have a reasonable chance at earning its authorized ROE, which, over time, is necessary in order to attract the capital necessary to meet the standards of service expected of the Company’s customers. The lack of a valid revenue requirement component within the CT-Bar that would allow recovery of the cost of capital associated with incremental capital investment over the term of the PBMRP is a non-starter from a policy perspective, creating an obstacle that would block a utility from giving up its right to file for rate modifications over the multi-year period in question. This is particularly accurate in the present environment in which significant increases in the level of necessary system investments are expected (and planned). Simply put, the CT-Bar, as previously envisioned in PURA’s draft PBR decision, fully prevented thePage 16 of 45
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set CLF-AC-01 Date Issued September 16, 2026 CLF-AC-001 Page 16 of 45 Company from having any practical chance at staying out of a rate case, and therefore, would never work to create a reasonable PBR framework. The Company’s proposed PBMRP in this docket is designed to track the design of the CT-Bar as closely as possible, given that this was PURA’s developing framework. However, the Company’s PBMRP addresses the two primary faults in PURA’s RE01 framework that would prevent the implementation of a workable PBR framework, which are (1) the deviations from ratemaking fundamentals that grossly understate the “going in” revenue requirement; and (2) modification of the CT-Bar to reflect the revenue requirement applicable to capital investment, which would include recovery of the cost of capital and the cost of removal over the course of the PBMRP term. The Company’s F-Factor also corrects for the mechanical error of deducting depreciation expense from new plant additions, rather than from rate base. In particular, the Company’s proposed F-Factor is designed to recover no more than the revenue necessary to support a discrete amount of ongoing system investment, recognizing that the cost of capital is a lawful and factual cost of service that must be incorporated into the revenue requirement calculation for the Company, as it is for any utility. 2. Considerations on the Design of Capital Driven Revenue Support CT-Bar, as defined in PURA’s Proposed Final Decision, issued in Docket No. 21-05-15RE01, on July 14, 2025 (the “RE01-PFD”), had several sensible qualities that the Company supported. However, those “sensible” qualities were overcome by certain critically flawed concepts that would need to be modified or eliminated in order for the Company to consider committing to a stay-out. The positive and negative CT-Bar qualities are outlined briefly here and discussed in greater detail below, including with respect to similarities or differences to the Company’s proposed F-Factor. Summary of constructive features of PURA’s RE01-PFD: 1) Acknowledgement that current revenue support for ongoing investment is essential; 2) No category of capital investment was summarily or preemptively excluded from CT-Bar; 3) CT-Bar takes effect with Rate Year 1; and 4) CT-Bar aligns capital revenue support with the capital investments of the DSP. Summary of unworkable features of PURA’s RE01-PFD: 1) Exclusion of the recognition in the CT-Bar of the cost of capital between rate cases. 2) Exclusion of cost of removal in the CT-Bar. 3) Application of depreciation expense as a reduction to plant additions rather than rate base. Constructive features of PURA’s RE01-PFD: 1) Positive #1: Acknowledgement that current revenue support for ongoing investment is essential to the integrity of the PBR framework. First, that the CT-Bar even existed in PURA’s RE01-PFD is genuine acknowledgement that some form of revenue support for rate year investment is essential to support a PBR framework. As discussed at length in that docket, the Company anticipates significant system investment over the next five years to advance the state’s clean energy and reliability goals. Revenue support for ongoing system investment is crucial for any multi-year rate plan, whether in the form of the Company’s proposed PBMRP, step increases, or any other ratemaking framework. CT-Bar’s inclusion in RE01-PFD is a clear indication that incremental revenue support for ongoing system investments is a necessity.Page 17 of 45
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set CLF-AC-01 Date Issued September 16, 2026 CLF-AC-001 Page 17 of 45 2) Positive #2: No category of capital investment was summarily or preemptively excluded from CT-Bar. Second, the RE01-PFD did not exclude particular categories of capital investment. For example, capital investments in facilities, fleet and information technology are viewed as permissible categories for revenue support in the CT-Bar framework. This is consistent with the Company’s proposed F-Factor in this proceeding. 3) Positive #3: CT-Bar takes effect as of Month 1 of Rate Year 1. The Company provided extensive discussion and analysis throughout Docket No. 21-05-15RE01 technical sessions and data responses regarding the “going-in” revenue requirement and the detrimental financial consequences of limiting capital investments to a period of time removed from the rate year. Ignoring for a moment the CT-Bar’s deficiencies, having the mechanism take effect Month 1 of Rate Year 1 minimizes or eliminates those detrimental timing consequences, particularly in light of the fact that PURA has in recent years moved away from its prior practice of implementing future-test years in base rate proceedings, instead favoring a strict historical test year practice as it relates to plant additions. Revenue decoupling is a factor to consider here because the revenue decoupling mechanism (“RDM”) subsumes all sales growth to the extent that it is occurring, funneling incremental sales revenues back to customers. RDM is supported by valid policy reasons; however, the fact is that there are capital costs associated with adding new customers. Historically, when consistent and steady levels in the range of ~3$ per year of annual growth in sales and revenues was available to a utility to help offset the cost of incremental capital additions between rate cases, the pressing need for incremental revenue support was mitigated. Without the ability to capture that sales growth, and combined with the absence of an ongoing revenue support mechanism such as an F Factor taking effect on Month 1 of Rate Year 1, the Company would not be in a position to commit to a stay-out of any duration. This is because the Company would never be in a position to cover its cost of service (inclusive of its authorized cost of capital) because its rates would be set on a historical level of plant additions, despite the fact that its capital expenditures are higher than historical levels of depreciation, and because revenue decoupling ensures that even if load growth exists (and even if such load growth is enabled by the Company’s increased level of capital expenditures) the Company is unable to retain additional revenues contributed by new customers, or new load. 4) Positive #4: CT-Bar was designed to align capital revenue support with the DSP. Ignoring its deficiencies, the CT-Bar’s connection to the Distribution System Plan (“DSP”) constituted an essential link between ongoing system investments necessary to meet the objectives of the DSP with the revenues necessary to support those investments. Throughout Docket No. 21-05-15RE01, the Company advocated strongly for clearly defined linkages across all three tracks (RE01, RE02 and RE03), including proposing what would be the final technical session touching upon revenue requirements, in which those linkages were discussed. The Company’s F-Factor is similarly aligned with the capital investment forecast provided in this proceeding for the DSP. The Company’s capital investment forecast serves as the basis for a cap on the level of investment for the F-Factor. Unworkable Features of PURA’s RE01-PFD: 1) Negative #1: No recovery of cost of capital in the revenue requirement for capital investment between rate cases.Page 18 of 45
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set CLF-AC-01 Date Issued September 16, 2026 CLF-AC-001 Page 18 of 45 The single-most problematic feature of the CT-Bar was its intentional exclusion of the cost of capital associated with completing capital plant additions to the benefit of customers. Costs of capital are real costs of providing electric distribution service to customers in the State of Connecticut (or anywhere) and are recognized in statute. Although the cost of capital may be a more challenging cost to conceptualize, it is nonetheless as real as vegetation management, insurance, customer service, or any other cost of service. Cash is not free, a fact arising from its scarcity. Fundamentally, capital markets are where people, banks, corporations and other institutions provide their surplus of cash -- which is limited, to those entities that have cash needs -- which are generally unlimited. Consequently, and unsurprisingly, those entities providing the cash for some period of time expect to be compensated for providing it, thus establishing real cost to acquire capital. The Company, operating in the capital-intensive industry of regulated utilities, is one of those entities that needs to acquire cash to operate its business. As annual capital investments regularly exceed its net cash from operations (i.e. cash from customers), the Company must look to other sources to fund those investments. Those sources are the debt and equity investors supplying the cash to capital markets. This means the Company must compete with ALL other entities participating in those markets. It is simply not possible for the Company to go to those markets and demand cash for free (or for below-market rates, relative to market expectations of risk and reward) when other entities participating in those capital markets offer adequate compensation for the use of funds over time. Therefore, there is a real and tangible cost to acquiring that capital. Please refer to the Company’s pre-filed cost of capital testimony for in-depth discussion of the cost of capital. The Company provided extensive analysis and discussion on the cost of capital throughout Docket No. 21-05-15RE01, including specifically as it relates to CT-Bar. PURA’s treatment with respect to goingin revenue requirements as well as any ongoing capital revenue support mechanism, such as CT-Bar, is paramount to whether the Company, with effective management and sound decision-making, has the opportunity, but not a guarantee, to cover its cost of service to customers, and to earn its allowed return. The absence of the cost of capital from the CT-Bar, particularly in the present environment where significant increases in the level of necessary system investments are expected, prevents the Company from having any practical opportunity to commit to a stay-out to avoid the next rate case. As discussed in the Company’s response to OCC-435, based on the Company’s current assessment of system investment needs in the near future, the revenue requirement associated exclusively with the cost of capital pertaining to future capital additions (excluding GET and Uncollectible) would amount to an incremental $15.6 million for Rate Year 1; an incremental $32.8 million for Rate Year 2; an incremental $36.4 million for Rate Year 3; and an incremental $39.5 million for Rate Year 4, or $124.1 million in total. This means that -- even if 100% of those future plant additions were only partially supported with CTBar revenues (i.e. revenue covering depreciation expense and property taxes only); and even if the Company’s future cost of service otherwise was 100% supported with rates; and even with perfect operational decision making -- the Company would still need to find $124.1 million of annual savings by Rate Year 4 in order to offset the loss of revenue associated with carrying costs on incremental investment over the term of the PBMRP, which would be necessary to commit to a stay-out term. For perspective, the total O&M expense included in the Company’s cost of service filed in this proceeding is $547.5 million. Thus, to earn its authorized ROE, all else equal, the Company would have to generate cost savings amounting to $124.1 million, or nearly 23%, of its Rate Year O&M level by Year 4, to offset the impact of the accumulating carrying costs on the incremental capital additions completed on the
As listed on the current system
Question(s) Answered 1, 2, 3 (Connecticut Light and Power Company dba Eversource Energy) Date Filed: 10/07/2026