Question:
Reconcile the Company’s responses to EOE-164, and EOE-166. EOE-166, describes contractexecution controls in Ariba, automated purchase-order logic in Ariba and Maximo linking every
purchase order over $50,000 to an active contract, sole-source justification, or approved exception,
dual sign-offs, and year-to-date compliance metrics tracked by the procurement group. EOE-164,
states that milestone payments “are not maintained as a separately reportable procurement
attribute.” State: (a) whether milestone or advance payment terms are recorded in the Ariba
contract records or payment schedules for the contracts they govern; (b) whether the Ariba and
Maximo systems can be queried or reported on by payment-term attributes, and if not, what
payment-term data those systems store; and (c) produce the listing EOE-164, declined to provide
— each procurement since January 1, 2020 that included milestone or advance payments, with the
vendor, contract amount, milestone payment amounts and schedule, and the amount paid in
advance of work performed or costs incurred — deriving it from the systems described in EOE166; or, if the Company maintains that this cannot be done, explain how a compliance assertion of
“no policy violations” across 50,323 purchase orders can be validated by systems from which basic
payment-term attributes cannot be reported.
Response:
As it relates to the controls identified in the Company’s response to EOE-166 i, those controls are
related to purchase-order compliance with the competitive bidding requirement for transactions
valued at greater than $50,000 and the approval of Ariba contracts.
When a purchase order is released, systemic logic evaluates whether the purchase order is linked
to an active Ariba contract or an approved Maximo sole-source justification. If neither linkage is
present and the purchase order exceeds $50,000, the purchasing agent must then select an approved
exception or identify the transaction as a policy violation before the purchase order can proceed.
The Maximo purchase-order control therefore evaluates whether a purchase order subject to the
release logic is associated with: (1) an active Ariba contract; (2) an approved Maximo sole-source
justification; (3) an approved exception to the competitive-bidding requirement; or (4) a policyviolation designation. The applicable pathway requires sign-off by the purchasing agent and the
agent’s supervisor.
The Connecticut Light and Power Company
d/b/a Eversource Energy
Docket No. 26-05-10
Set ALLCO-09
Date Issued September 21, 2026
ALLCO-090
Page 2 of 6
The statement in EOE-166 that there were no policy violations among 50,323 released purchase
orders means that none of those purchase orders were released with a policy-violation designation
based on the specific system logic and fields evaluated by the control. The metric separately
identified 294 approved exceptions at the purchase-order level. The statement was not intended
to represent that each of the 50,323 purchase orders was reviewed for compliance with every
procurement-policy, contractual or payment requirement.
This control is only one component of the Company's broader procurement compliance and
oversight framework. Separately, prior to execution of an Ariba contract, purchasing agents and
designated approvers are required to upload or verify supporting documentation to validate
compliance with applicable competitive-bidding requirements. That contract-level review
confirms the applicable procurement pathway and supporting documentation without requiring
milestone or advance payment provisions to be captured as separately reportable system attributes.
The Maximo purchase order release control does not evaluate contract-specific payment structures,
including milestone or advance payment provisions, and does not depend on those provisions
being maintained as separately reportable system attributes. Accordingly, there is no inconsistency
between the EOE-166 description of the purchase-order release control and the EOE-164 ii
statement that milestone-payment provisions are not maintained as a separately reportable
procurement attribute.
a. Milestone payment schedules may be included in the underlying contract documentation,
which may take the form of an Ariba Contract or a Maximo Purchase Order. Advance
payment provisions may be recorded in the same types of governing or supporting
documents. The location and format of the applicable provision may vary based on the
structure of the transaction and its governing documents.
Milestone or advance-payment information is not maintained as a separately reportable or
trackable data field within Ariba or Maximo because this type of information is most
common to larger materials purchases or to engineering work pertaining to custom
materials. As a result, this type of information is not generally applicable to the bulk of
the Company’s contracts. For efficiency and effectiveness, Ariba and Maximo store
payment-term information as necessary to support procurement and accounts payable
processes.
b. The standard payment term, referring to the field that generally establishes how long after
invoice receipt a payment should be made, is maintained within the Company's
procurement system. It is generally established at the vendor level, although it may be
modified at the purchase-order or contract level in limited circumstances where
appropriate.
A standard payment term generally establishes when payment is scheduled following
invoice receipt. By contrast, a milestone or advance-payment provision may establish the
The Connecticut Light and Power Company
d/b/a Eversource Energy
Docket No. 26-05-10
Set ALLCO-09
Date Issued September 21, 2026
ALLCO-090
Page 3 of 6
contractual events or conditions governing when an invoice may be submitted or payment
becomes due. These provisions are generally contained in contract documentation rather
than a discrete data field in Ariba or Maximo.
Where milestone or advance payments are contemplated, invoice processing would
generally be supported through business-approval workflows conducted in accordance
with the applicable contract and Delegation of Authority requirements. These payments
require approval by the appropriate invoice approver and, where applicable, additional
approvers based on the relevant thresholds. The review relies on the approver’s
understanding of the contract terms and confirmation that the applicable conditions have
been satisfied.
Accordingly, the Company’s systems maintain payment terms as necessary for transaction
processing, which the business uses. The Company’s systems are not designed to create
an all-encompassing inventory of procurement transactions containing milestone or
advance-payment provisions that is not necessary for the business.
c. Compilation of the requested listing would require a manual review of the relevant
contracts, purchase orders, statements of work, amendments, payment schedules, invoices,
and supporting documentation, which is not an analysis that the Company needs or utilizes
for its own purposes. The existence of an Ariba contract or Maximo purchase order does
not necessarily indicate that the transaction contains such a provision or its associated
amount and schedule.
In most instances, advance- or milestone-related payments are intended to support supplier
costs associated with engineering, materials, or other contractually required investments in
Company projects. A contract may also provide for a payment or payment commitment to
secure production capacity, long lead materials, or manufacturing slots.
The amount of “paid in advance of work performed or costs incurred” therefore cannot
necessarily be determined from a payment schedule alone. That determination requires a
transaction-specific comparison of contract terms, invoices, payment records, supporting
documentation, and the status of supplier performance or costs at the time of payment.
The Company's response to EOE-166 does not rely upon the identification or reporting of
milestone-payment provisions, advance-payment arrangements, or other contract-specific
payment structures. Rather, the compliance metric referenced in EOE-166, relates to a
control designed to verify that purchase orders exceeding $50,000 are supported by are
processed through (1) an Ariba contract, (2) an approved Maximo sole-source justification,
or (3) an approved exception to the competitive-bidding requirement or (4) identification
as a policy violation. The separate Ariba contract execution process requires the upload or
verification of supporting procurement documentation; however, that requirement does not
The Connecticut Light and Power Company
d/b/a Eversource Energy
Docket No. 26-05-10
Set ALLCO-09
Date Issued September 21, 2026
ALLCO-090
Page 4 of 6
create a separately reportable field identifying milestone- or advance-payment provisions,
as this information is not necessary for the business.
The EOE-166 metric can therefore be validated through the system fields, workflow
statuses and approvals evaluated by the purchase-order release control. That validation
does not depend on milestone or advance payment provisions being separately reportable.
Conversely, the control is not intended to evaluate compliance with those contract-specific
payment provisions.
Accordingly, the Company’s statement that there were no policy violations means that no
purchase orders were released with a policy-violation designation based on the defined
release-control logic. It does not speak to compliance with milestone payments, advance
payments, or other requirements outside the control’s scope or that are monitored by the
Company through other processes.
Prior Referenced Response:
i
EOE-166 Question:
(COMPETITIVE BID ASSESSMENTS) Respond to the following:
a.
b.
Explain how the Company ensures that each purchase order or contract is subject to a competitive bid
assessment, sole source justification, or an approved exception. As part of the response, please discuss
whether there are any systemic controls, including the use of Ariba, that ensure adherence to these
requirements and, if applicable, provide an example of the referenced controls.
Explain how the Company ensures adherence to the Company’s competitive bid requirements for situations
where multiple purchase orders or contracts could be used in lieu of the referenced controls discussed in
subsection a.
EOE-166 Response:
a.
The Company enforces adherence to competitive bid assessments, sole source justifications, and approved
exceptions through integrated governance policies and automated controls within Ariba and Maximo:
•
Contract Execution Controls: Prior to executing an Ariba Contract, purchasing agents and designated
approvers are required to upload or verify appropriate supporting documentation into the system to validate
compliance.
Automated Purchase Order (PO) Systemic Logic: When a PO is released, system logic automatically verifies
that it is linked to either an active Ariba Contract or an approved Maximo Sole Source Justification. If neither
control is present and the PO is valued at more than $50,000, the system prevents processing until the agent
selects an approved exception or flags the record as a policy violation.
•
Both pathways require formal dual sign-off from the agent and their supervisor. For exceptions a standardized
comment nomenclature is expected.
The Connecticut Light and Power Company
d/b/a Eversource Energy
Docket No. 26-05-10
Set ALLCO-09
Date Issued September 21, 2026
ALLCO-090
Page 5 of 6
The image below, details the year-to-date metrics tracked by the procurement group on exceptions and violations
across the procurement organization, including records supporting CL&P and other affiliates. To date, out of 50,323
Purchase Orders released by the Procurement Team, there were no policy violations and 294 represented exceptions
taken at the PO level.
b.
ii
The Company actively prevents purchase order "stringing" which is the practice of splitting orders to bypass
competitive bidding thresholds, where the practice is inappropriate. In some cases, purchase orders may be
used to accommodate valid operational requirements (such as distinct delivery sites, scopes of work, or
material types):
•
Agent Oversight & Pattern Detection: Procurement agents evaluate non-contracted POs during the
approval workflow. Agents monitor indicators of stringing by cross-referencing requisitions with similar
service descriptions, identical supplier selections, and matching accounting strings across multiple
orders.
•
Centralized Spend Coverage: Over 90% of Company spend is governed by master Ariba Contracts.
Establishing spend under Ariba Contracts naturally mitigates the risk of PO-level stringing, as individual
POs draw down from existing contracts that were approved to DOA systematically.
EOE-164 Question:
(MILESTONE PAYMENTS) Refer to Response to EOE-056. The Company’s response stated that the “Company
does not generally support milestone payments prior to work being performed or costs being incurred by the
Company’s vendor…” Provide a listing of all procurements that included milestone payments, along with the rationale
for why the payments were permitted. As part of the response, please identify the vendor, the contractual amount, and
the payment amount that would be at risk.
EOE-164 Response:
Milestone payments are not maintained as a separately reportable procurement attribute. Milestone payment terms,
where applicable, are permitted on a case-by-case basis as described in the Company’s response to EOE-056i.
The Connecticut Light and Power Company
d/b/a Eversource Energy
Docket No. 26-05-10
Set ALLCO-09
Date Issued September 21, 2026
ALLCO-090
Page 6 of 6
Milestone payments may be permitted where appropriate, based on the nature of the goods or services being procured
and the applicable commercial terms. Any characterization of an amount that would be “at risk” would depend upon
the specific contractual provisions, milestone that was completed, and other facts applicable to the individual