Interrogatory responses
Answers to questions 95, 98, 108
Filed by The Connecticut Light and Power Company3 files
Part of docket 26-05-10Files3
ALLCO-095_Final.pdf
PDF · 155 KB · 3 pagesText searchable
Download ALLCO-095_Final.pdfRead the text of ALLCO-095_Final.pdf
ALLCO-098_Final.pdf
PDF · 109 KB · 1 pageText searchable
Download ALLCO-098_Final.pdfRead the text of ALLCO-098_Final.pdf
ALLCO-108_Final.pdf
PDF · 155 KB · 3 pagesText searchable
Download ALLCO-108_Final.pdfRead the text of ALLCO-108_Final.pdf
The Connecticut Light and Power Company
d/b/a Eversource Energy
Docket No. 26-05-10
Set ALLCO-09
Date Issued September 21, 2026
ALLCO-095
Page 1 of 3
Date Filed: October 05, 2026
Witness:
Andrew C. Belden, Warren R. Boutin and Justin Pelkowski
Request from: ALLCO
Question:
The Company’s responses to ALLCO-040 and ALLCO-041 state that treating distributionconnected resources under five megawatts as unregistered load reducers “produces benefits for
customers by reducing wholesale load obligations” and “reduce[s] the load and capacity supply
obligations of all load serving entities.” For each calendar year 2020 through 2025:
(a) describe how the Company’s retail load settlement process allocates the output of a host
customer’s behind-the-meter generation to the load-serving entity serving that customer —
i.e., confirm that when the host customer is served by a licensed third-party supplier, the
resulting reduction in settled load accrues to that supplier’s wholesale position rather than
to the Company’s standard service load; (b) state the number of net-metered, virtually netmetered, and other load-reducer host customers served by third-party suppliers versus
taking standard service or supplier-of-last-resort service, by year, and the associated
behind-the-meter output in MWh for each group (or the best available estimate, identifying
the estimation method); and (c) state the aggregate MWh by which load-reducer output
reduced the settled Real-Time Load Obligation of the Company and of third-party
suppliers, respectively, by year, in native format.
Response:
PURA’s June 2, 2026, Notice of Proceeding in Docket No. 26-05-10 states that, upon a receipt of
a completed application from Eversource to amend the Company’s existing rate schedules, PURA
will conduct a contested proceeding to review Eversource’s application. Eversource objects to
Allco’s effort to litigate an issue that is outside the scope of this rate case proceeding. Considering
the statutory 350-day timeframe to issue a final decision on the Company’s application and the
number of interrogatories issued in this proceeding to-date, the litigation of issues irrelevant to the
Company’s application threatens to adversely impact the orderly conduct of this proceeding. 1
Without waiving said objection, the Company states as follows:
Allco previously litigated renewable energy projects as load reducers in the Company’s Docket
No. 24-01-03 Revenue Adjustment Mechanism proceeding. See, Docket No. 24-01-03,
Eversource responses to ALLCO-04 and ALLCO-027. Eversource objected to both of these
questions.
1
The Connecticut Light and Power Company
d/b/a Eversource Energy
Docket No. 26-05-10
Set ALLCO-09
Date Issued September 21, 2026
ALLCO-095
Page 2 of 3
a. For the purposes of ISO-NE load settlement within the wholesale power markets, electric
distribution utilities report load data to ISO-NE for each “Load Asset,” which is the
specific collection of customer load represented in the ISO-NE market settlement system
for a particular load-serving entity (“LSE”). The Company reports hourly load data to
ISO-NE consistent with the applicable tariff provisions and rules of ISO-NE. Customer
hourly loads are determined based on either actual hourly interval data or estimated data
developed from load profiles. Non-large commercial and industrial customers generally
do not have interval metering, and their load data is reported to ISO-NE based on load
profiles. Large commercial and industrial customers have interval metering and their
load data is reported to ISO-NE based on that hourly metered data. When interval data
is not available, the load data for those customers is reported to ISO-NE based on load
profiles. If a customer has a behind-the-meter load reducer, then for generation that is not
in excess of the their consumption that load reducer lowers both that customer’s billed sales
and the wholesale load associated with the load asset assigned to their LSE. If a wholesale
supplier’s load is reduced, the expense billed from ISO-NE to the wholesale supplier is
reduced. For generation that is in excess of their consumption, that excess amount is
credited to the customer in the manner described in ALLCO-043. The excess wholesale
generation is distributed amongst all LSEs in the load zone.
b.
The volume of distributed generation facilities enrolled in Connecticut clean energy
programs and tariffs is reported by the EDCs and other program administrators on an
annual basis, most recently in Docket No. 25-08-01. The total number and capacity of
reported facilities in Eversource service territory for each year is as follows:
Year
DG facility count
2020
2021
2022
2023
2024
2025
31,997
35,481 41,448 56,327
67,591 75,727
Total MW
314.5
360.7
414.0
539.3
658.8
742.5
_
The Company does not track the number of customers enrolled in clean energy programs
and tariffs served by third-party suppliers versus taking standard service or supplier-oflast-resort service.
c. The company does not track or estimate the aggregate MWh by which load-reducer output
reduced the settled Real-Time Load Obligations.
The Connecticut Light and Power Company
d/b/a Eversource Energy
Docket No. 26-05-10
Set ALLCO-09
Date Issued September 21, 2026
ALLCO-095
Page 3 of 3
Prior Referenced Response:
_______________________
i
ALLCO-043 Question:
Describe how amounts associated with net metering and virtual net metering are calculated and recovered from other
customers through the NBFMCC (including the "avoided bill" methodology described by Company witnesses in
Docket No. 20-01-01), and state whether the amounts so charged to customers are reduced or offset by the
corresponding reductions in regional transmission charges (RNS, LNS, TAC), capacity obligations, and standard
service procurement quantities attributable to the same behind-the-meter generation; if no such offset is made, explain
why not, and quantify the annual amount charged to customers through the NBFMCC for net metering for each year
2020 through 2025 without any such offset.
ALLCO-043 Response:
PURA’s June 2, 2026, Notice of Proceeding in Docket No. 26-05-10 states that, upon a receipt of a completed
application from Eversource to amend the Company’s existing rate schedules, PURA will conduct a contested
proceeding to review Eversource’s application. Eversource objects to ALLCO’s effort to litigate an issue that is outside
the scope of this rate case proceeding. Considering the statutory 350-day timeframe to issue a final decision on the
Company’s application and the number of interrogatories issued in this proceeding to-date, the litigation of issues
irrelevant to the Company’s application threatens to adversely impact the orderly conduct of this proceeding.1
Without waiving said objection, net metering and virtual net metering amounts included in the NBFMCC are
calculated and recorded for inclusion in the NBFMCC, as part of each customer’s monthly bill, in accordance with
the tariff rider under which each customer is enrolled. Monthly net metering amounts for the net metering rider
involving banked kWh (e.g., Rider N) are calculated by multiplying the portion of a customer’s net metering facility’s
energy produced and not used, but that is netted against the energy delivered to that customer from the distribution
system by the customer’s prevailing per kWh rates. Any excess monthly energy production not so netted over the
course of 12 months is multiplied by the annual average LMP rate to determine a residual amount included in the
NBFMCC. For net metering facilities that do not involve kWh banking (e.g., RRES), the amount included in the
NBFMCC for each month is calculated by multiplying total energy produced and not used by the customer by the rate
set forth pursuant to the net metering tariff rider under which they are enrolled. For virtual net metering (“VNM”), net
metering amounts included in the NBFMCC are determined by multiplying the monthly energy production by the
prevailing general service rates under which the customer receives electric service, calculated on a per kWh basis,
pursuant to the VNM rider
Allco previously litigated renewable energy projects as load reducers in the Company’s Docket No. 24-01-03
Revenue Adjustment Mechanism proceeding. See, Docket No. 24-01-03, Eversource responses to ALLCO-04 and
ALLCO-027. Eversource objected to both of these questions.
1
As listed on the current system
Question(s) Answered 95, 98, 108 (The Connecticut Light and Power Company) Date Filed: 10/05/2026