Interrogatory responses
Answers to questions 25
Filed by The Connecticut Light and Power Company3 files
Part of docket 26-05-10Files3
BETP-025_Final.pdf
PDF · 143 KB · 4 pagesText searchable
Download BETP-025_Final.pdfRead the text of BETP-025_Final.pdf
BETP-025 Attachment 1 .pdf
PDF · 196 KB · 2 pagesText searchable
Download BETP-025 Attachment 1 .pdfRead the text of BETP-025 Attachment 1 .pdf
BETP-025 Attachment 1 .xlsx
Excel · 38 KBText searchable
Download BETP-025 Attachment 1 .xlsxRead the text of BETP-025 Attachment 1 .xlsx
The Connecticut Light and Power Company
d/b/a Eversource Energy
Docket No. 26-05-10
Set DEEP-01
Date Issued October 06, 2026
BETP-025
Page 1 of 4
Date Filed: October 27, 2026
Witness:
David L. Gladey, Lavelle Freeman, John P. Dipaola-Tromba, Jennifer A.
Schilling and Elli Ntakou
Request from: Department of Energy and Environmental Protection
Question:
Refer to Exhibit CLP-TSP-3. For each proposed substation or distribution-capacity project
identified, please briefly identify the principal alternatives considered, including:
a.
b.
c.
d.
e.
f.
g.
load transfers;
equipment uprating;
storage
demand response;
flexible interconnection;
or other non-wires alternatives.
Please provide the estimated cost, implementation timeline, and principal reason each
alternative was rejected or not selected. If no alternatives analysis was performed, explain why.
Response:
The substation capacity projects identified in the workbooks are in various stages of the projectapproval process. None of the projects have reached a stage that would have received a detailed
NWA analysis to date. As these projects proceed through the solution selection and engineering
stages, NWA and other alternatives will be vetted. The results will be submitted during the annual
grid needs filing as part of the NWS docket. For additional project details, please refer to the
Company’s response to OCC-599 i, identifying current project status, estimated budget, and any
alternatives identified at this time.
The line capacity projects identified currently exceed the planning criteria based on metered data
and NWS solutions were analyzed as alternatives to traditional line projects. Demand response
and flexible interconnections were not evaluated as alternatives due to the lack of both a DERMS
system and AMI. The Company submitted all capital projects to the process monitor as part of
Docket No. 25-08-08 and the ongoing Docket No. 26-08-08.
Please refer to BETP-025, Attachment 1, identifying alternatives reviewed for distribution line
projects. Please note that the PAF reflects only alternatives that were evaluated and determined to
be feasible. As an example, load transfer options that were found to be infeasible were not included
among the listed alternatives.
The Connecticut Light and Power Company
d/b/a Eversource Energy
Docket No. 26-05-10
Set DEEP-01
Date Issued October 06, 2026
BETP-025
Page 2 of 4
Prior Referenced Response:
i
OCC-599 Question:
Refer to Exhibit CLP-TSP-3 at 22–24.
a. Provide the data underlying the headroom and constrained-area presentations on pages 22–24. For each
substation identified as constrained, provide its normal and emergency rating, five-year historical load and
peak load data, available headroom, forecast first year of violation, and proposed project cost.
b. For each constrained substation identified, provide the existing analysis of temporary and permanent load
transfers. Identify the receiving substation or feeder, available transfer capacity, MW that could be
transferred, required enabling work, estimated cost, and reason any transfer was rejected. Please confirm if
no transfer analysis was performed.
c. Provide a summary of each actual substation capacity violation and stranded-load event experienced from
2016 through the present. Identify the substation, date, maximum loading, applicable rating, duration,
contingency, customers at risk, customers interrupted, and whether load transfer prevented or reduced an
outage.
OCC-599 Response:
a.
The graphic depicted in CLP-TSP-3, at 22, is derived from headroom data for substations with actual values, time
series data, and ratings shown on our public maps using the Eversource CT Grid Connection Navigator. Loads
are based on our most recent summer peak year, 2025. Please refer to OCC-599, Attachment 1 CONFIDENTIAL,
for project forecast violation year and the 5-year historical peak load data for each respective project. The table
contains the LCC rating of each substation which is the planning criteria identified within the DSPG, please refer
CLF-SC-023, Attachment 1. The following substations have projects initiated and have obtained at a minimum a
conceptual level estimate:
Substation
West Brookfield 14H
Beacon Falls 11N
Franklin Drive 1B
Southington 4C
Berlin 6A_13.8kV
Westside 7A
Hopewell 22R
Estimated Project Cost
$16,900,000
$12,632,000
$17,986,000
$9,772,600
$23,199,000
$18,399,000
$17,518,000
All other substations within the attachment have not had a comprehensive evaluation to identify possible solutions
and the costs associated with those solutions. The table below depicts a high-level tabletop analysis for possible
projected cost of a substation solution. These costs will be refined as these projects progress through the funding
process and receive full engineering analysis for solutions and conceptual level estimates.
The Connecticut Light and Power Company
d/b/a Eversource Energy
Docket No. 26-05-10
Set DEEP-01
Date Issued October 06, 2026
BETP-025
Page 3 of 4
b.
Substations
High Level
Estimate
Project Status
Waterside 22M
Flax Hill 24A
Rocky Hill 12Y
$600,000
$500,000
Less than $250,000
Investigating Project Need
Investigating Project Need
Investigating Project Need – Anticipating Permanent
Load Transfer from West Brookfield 14H with settings
changes only
Triangle 11A
Middle River
28M
$4,800,000
$500,000
Initial Funding Approved
Investigating Project Need
Rockville 14W
Campville 14R
Baldwin 13F
Tracy 14M
Frybrook 13B
Brooklyn 30Y
$10,000,000
$52,300,000
$20,250,000
$9,900,000
$20,000,000
Less than $250,000
Initial Funding Approved
Partial Funding
Initial Funding Submitted
Initial Funding Approved
Initial Funding Approved
Investigating Project Need – Anticipating Permanent
Load Transfer from Tracy 14M or Frybrook 13B with
settings changes only
Prior to initiating a funding project, permanent load transfers are, in many cases, a preferred solution if the
conditions at the constrained substation and the adjacent area support this as these are typically substantially lower
cost than substation investments and have a much more rapid deployment timeline. Historically these load
transfers were not explicitly tracked, and the Company does not possess historical data as it pertains to deferrals
by means of permanent load transfer. As of 2024 the Company identified this opportunity to begin having a
detailed record of load transfers, partly in response to increasingly constrained regional capacity. The Company
is now prepared to track these transfers in the Step Load Tracker as a load transfer on the receiving substation
and a negative load transfer to the originally constrained station. This tracker will not only allow the forecasted
load transfer to be visible but will also allow for historical reporting of deferred major capital upgrades through
completed load transfers.
The newly identified projects are in early stages of development and have not yet completed the solution selection
process yet. Therefore, these projects would not yet have any tracked load transfers or analyses completed to date.
Following initial funding of these projects, all available solutions including permanent load transfers, non-wires
solutions, and traditional solutions are identified and evaluated for suitability and for viability. No potential
solutions have been rejected at this time from these newly identified projects. Temporary transfers are reserved
for substations anticipating overload during a current planned peak event, planned or unplanned outages, or other
transient system events. Temporary solutions place the system in an abnormal condition which can impact
operations, protections and controls, and automations within the system and are not used as a long-term solution
except where necessary to address real-time operational needs that do not have a permanent solution placed into
service.
c.
All substation forecasted violations are mitigated by using pre-contingent load transfers to adjacent substations
with remaining capacity. In accordance with planning criteria in the Distribution System Planning Guide (CLFSC-023, Attachment 1), the Company plans and designs its system to avoid overload of major substation assets
such as transformers during an N-1 event. During real-time operation, these overload scenarios are avoided
The Connecticut Light and Power Company
d/b/a Eversource Energy
Docket No. 26-05-10
Set DEEP-01
Date Issued October 06, 2026
BETP-025
Page 4 of 4
through the use of monitoring technology and planned mitigation measures. However, the Company’s substation
planning group recreates a normalized substation load to aid in the process of forecasting for future years.
As listed on the current system
Question(s) Answered 25 (The Connecticut Light and Power Company) Date Filed: 10/27/2026