Skip to main content

A prototype public docket site for the Connecticut Public Utilities Regulatory Authority

Utility Dockets and Filings

Interrogatory responses

Answers to questions 8, 11

Files2

  1. Page 1

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set ICC-01 Date Issued September 08, 2026 ICC-008 Page 1 of 1 Date Filed: September 22, 2026 Witness: Warren R. Boutin and Andrew C. Belden Request from: Interconnection Customer Coalition Question: Reference ICC-5. Describe any consequences if Eversource does not meet the identified timelines. Response: Connecticut interconnection is administered under PURA-approved Guidelines, not tariffs that impose automatic penalties for EDC timeline misses. The Guidelines require the EDC to make reasonable efforts to meet the stated timeframes unless the parties agree to a different schedule. If the EDC does not meet a Guideline deadline, and the Interconnection Customer requests a status update, the EDC is to respond within three (3) business days with (a) a response to the inquiry, (b) the reason the deadline was missed, and (c) an estimated date for completing the applicable step. A missed EDC timeframe does not, by itself, advance the project to the next stage, waive screens or studies, or require issuance of an Interconnection Agreement. ISO-NE review required for projects greater than 1 MW is outside the state Guideline clocks and can extend the overall.

As listed on the current system

Question(s) Answered 8, 11 (The Connecticut Light and Power Company) Date Filed: 09/22/2026

This filing on the current system (opens in a new tab)