Interrogatory responses
Answers to questions 122, 123, 127
Filed by The Connecticut Light and Power Company3 files
Part of docket 26-05-10Files3
NECTA-122_Final.pdf
PDF · 119 KB · 2 pagesText searchable
Download NECTA-122_Final.pdfRead the text of NECTA-122_Final.pdf
NECTA-123_Final.pdf
PDF · 101 KB · 1 pageText searchable
Download NECTA-123_Final.pdfRead the text of NECTA-123_Final.pdf
NECTA-127_Final.pdf
PDF · 101 KB · 1 pageText searchable
Download NECTA-127_Final.pdfRead the text of NECTA-127_Final.pdf
The Connecticut Light and Power Company
d/b/a Eversource Energy
Docket No. 26-05-10
Set NECTA-05
Date Issued October 02, 2026
NECTA-122
Page 1 of 2
Date Filed: October 16, 2026
Witness:
David L. Gladey and Jeffrey Richard
Request from: New England Connectivity and Telecommunications Association
Question:
For all poles replaced for which Eversource is seeking amortization of non-billable O&M costs in
Exhibit CLP REVREQ-4, please
a. confirm that third-party attachers transferred their attachments to the replacement pole at their
cost;
b. discuss whether a municipal attachment can be the cause of a pole being non-compliant; and
c. provide the number of poles replaced associated with the non-billable O&M costs in Exhibit
CLP REVREQ-4 that had municipal attachments.
Response:
a.
Please refer to the Company’s response to NECTA-106 i.
b.
Please refer to the Company’s response to NECTA-107 ii subpart (a).
c.
Please refer to the Company’s response to NECTA-107 subpart (b).
Prior Referenced Response:
i
NECTA-106 Question:
For all poles replaced for which Eversource is seeking amortization of non-billable O&M costs in Exhibit CLP
REVREQ-4, please confirm that third-party attachers transferred their attachments to the replacement pole at their
cost. If not. Identify the exceptions and state who bore the transfer costs, the amounts involved, and whether any such
amounts are included in the proposed amortization.
NECTA-106 Response:
Eversource does not perform, direct, schedule, or fund the transfer of third-party attachments to replacement poles
and does not maintain records regarding costs incurred by third party attachers for such transfers. The costs reflected
in Exhibit CLP-REVREQ-r are costs incurred by Eversource and do not include costs incurred by third party attachers
to transfer their facilities.
The Connecticut Light and Power Company
d/b/a Eversource Energy
Docket No. 26-05-10
Set NECTA-05
Date Issued October 02, 2026
NECTA-122
Page 2 of 2
ii
NECTA-107 Question:
Please provide the following: (a) discuss whether a municipal attachment can cause a pole to be in violation or noncompliant with relevant pole standards, (b) provide the number of poles replaced associated with the non-billable
O&M costs in Exhibit CLP REVREQ-4 that had one or more municipal attachments before replacement.
NECTA-107 Response:
a.
Yes. A municipal attachment, like any other attachment occupying space on a utility pole, may contribute to a
pole being out of compliance with applicable clearance, loading, safety, or other pole-related standards depending
on the nature, location, and condition of the attachment. Whether a particular attachment contributed to a violation
or non-compliant condition is determined based on the specific facts and conditions present at the pole.
b.
Eversource did not track or compile information regarding the presence of municipal attachments as part of the
process used to develop Exhibit CLP-REVREQ-4. Accordingly, the Company has not determined the number of
poles associated with the non-billable O&M costs in Exhibit CLP-REVREQ-4 that had one or more municipal
attachments prior to the replacement.
As listed on the current system
Question(s) Answered 122, 123, 127 (The Connecticut Light and Power Company) Date Filed: 10/16/2026