  1. Part 1

    [Sheet: OCC-586 Attachment 1] $ Millions Total Asset Health | SS AGING INFRASTRUCTURE-Incremental UG Network Automation-Incremental Asset Health Subtotal Communications | Substation Communications-Incremental Emergent * | EMERGENT EQUIPMENT FAILURES - SUBSTATION-L4 Grid Ops Technology | Adaptive Protection LTC Controls Microprocessor Relays Virtual Protection DERMS Demonstration Grid Ops Technology Subtotal Planning Analytics | Advanced Analytics Platform Advanced Forecasting Tools Circuit Planning Capabilities to manage planning models Integration of Electric/Gas Planning Tools / Pilot Planning Analytics Subtotal Reliability | SMART SWITCHES PROGRAM LINE SENSORS PROGRAM-Incremental Reliability Subtotal Capacity | VOLTAGE AUTOMATION New Customer | Shared Hosting & Advancement of Renewable Energy (SHARE) * Incremental increase in proactive substation aging infrastructure investments are expected to yield a decrease in emergent equipment failure spending

As listed on the current system

Question(s) Answered 582, 585, 586 (The Connecticut Light and Power Company) Date Filed: 09/22/2026