Answers to questions 780, 781, 783, 787

Files11

The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-19 Date Issued September 21, 2026 OCC-780 Page 1 of 2 Date Filed: October 05, 2026 Witness: David L. Gladey, Leanne M. Landry and Jeffrey D. Turano Request from: Office of Consumer Counsel Question: Exhibit CLP-ADDITIONS-12 shows a 2023 Connecticut Distribution plan of $466.4 million (PDF p. 121) against 2023 actual expenditures of $557.9 million (PDF p. 145). Explain each driver of the $91.5 million variance in dollar terms, identify each project or program added to the 2023 plan after the plan was set, and provide the 2023 capital variance analysis presented to Company management and to the Board of Trustees. Response: CLP-ADDITIONS-12 provides the annual capital investment plan from 2017 through 2025 at the CT Electric Operations organizational level. The table provides a list of projects added to the 2023 plan (over $500,000). The two largest projects added to the 2023 capital investment plan for CL&P were the trip-saver program and circuit patrol fixes. Trip savers are installed to reduce the number of outages caused by transient type events (tree, animal, lightning, etc.). A trip saver is a self-powered, electronically controlled, single-phase, cutout-mounted vacuum interrupter recloser. It is designed to eliminate the sustained interruption that occurs when a lateral fuse cutout operates in response to a transient fault. This device saves outages, improves restoration time to customers and reduces truck rolls. It also eliminates momentary circuit interruptions that occur when a substation circuit breaker or source-side line recloser would trip to prevent a lateral fuse cutout from operating in response to a transient fault. Additionally, the Company addressed circuit-patrol deficiencies identified by a third party. Distribution circuits patrolled by the third party documented deficiencies that were required to address asset and system improvements. The identified upgrades were completed to maintain a reliability of service to customers. The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set OCC-19 Date Issued September 21, 2026 OCC-780 Page 2 of 2 CD02197:2023 Trip Saver Program CD02169:TRC Circuit Patrol Fixes STRM22CP:CL&P MAJOR STORMS 2022 CD02133:Rentschler Field - New Service CS00675:Falls Village 9A Replace XFMR CD02275:Western Lateral Contributors to CEM CD01866:2023 ROW Priority 3 Poles CD02296:Eversource CT Hot Line Clamp Repl. CS00663:Stevenson 12A Install Mobile CD02270:Eastern CEMI-Lateral Reconductoring CD02030:6A7 Overload CD02334:Great Pond, Windsor NS CD02162:RECOMMENDATION FOR I-95 CD02121:11R50 PILC Cable Replacement CD02004:Canton 5R6 – Contingency Overload CD01852:ROW 030 Priority Structures CD02279:1B12 PILC Cable Replacement CD02045:48C7 Overload Project CD01559:11W47 PILC Cable Replacement 2023 Actual $ 21,972,108 $ 20,016,591 $ 4,096,195 $ 3,963,530 $ 3,159,632 $ 1,869,115 $ 1,644,692 $ 1,226,920 $ 1,154,330 $ 1,150,698 $ 1,096,932 $ 1,092,976 $ 1,089,367 $ 997,460 $ 733,499 $ 687,618 $ 659,215 $ 568,537 $ 561,296 Please refer to OCC-780, Attachment 1, for the December 2023 CT Electric Operations Budget Results, which includes the 2023 capital variance analysis that was presented to Company management. Please refer to OCC-780, Attachment 2 CONFIDENTIAL, for the February 5, 2024 CL&P Board of Directors letter, which includes a 2023 variance analysis for capital expenditures.

Text of OCC-781 Attachment 1.pdf

Extracted from the file · 6 pages · 17,148 characters

Text of OCC-781 Attachment 2.pdf

Extracted from the file

Text of OCC-781 Attachment 2.xlsx

Extracted from the file

Text of OCC-783_Final.pdf

Extracted from the file

Text of OCC-787_Final.pdf

Extracted from the file

Text of OCC-787 Attachment 1.pdf

Extracted from the file

Text of OCC-787 Attachment 1.xlsx

Extracted from the file

As listed on the current system

Question(s) Answered 780, 781, 783, 787 (The Connecticut Light and Power Company) Date Filed: 10/05/2026