Interrogatory responses
Answers to questions 273
Filed by Connecticut Light and Power Company dba Eversource Energy2 files
Part of docket 26-05-10Files2
EOE-273_Final.pdf
PDF · 102 KB · 2 pagesText searchable
Download EOE-273_Final.pdfRead the text of EOE-273_Final.pdf
EOE-273 Attachment 1 REDACTED.pdf
PDF · 1.9 MB · 24 pagesText searchable
Download EOE-273 Attachment 1 REDACTED.pdfRead the text of EOE-273 Attachment 1 REDACTED.pdf
The Connecticut Light and Power Company
d/b/a Eversource Energy
Docket No. 26-05-10
Set EOE-06
Date Issued September 22, 2026
EOE-273
Page 1 of 2
Date Filed: October 06, 2026
Witness:
Mark P. Baldwin, Clifford G. Williams, Leanne M. Landry and John G.
Griffin
Request from: Office of Education, Outreach, and Enforcement
Question:
(MS24F-VENDOR-LINE) Refer to Exhibit ACCT-2 CLP-6 and Confidential Exhibit ACCT-2
CLP-6A-1, pp. 23-62. The Company reported an incremental charge of $377,813 for the Asplundh
Construction Corp. Respond to the following:
a. Referring to pp. 40, 44, 47, 49, 51, 53, 55-56, and 59, explain why each of the crews were
permitted to commence billing on April 3, 2024, at either 0600 or 0630 and solely bill for
standby when the ERP declaration did not occur until 1800. As part of the response, please
identify the incremental cost for the standby billing on April 3, 2024, for the hours prior to
the 1800 ERP declaration.
b. Referring to p. 43, explain why two individuals were permitted to bill for four hours (each)
of travel for demobilization on April 5, 2024, without any details regarding the commute
or the documentation to demonstrate that there was a commute (i.e., there was no
corresponding mobilization). As part of the response, please provide documentation that
was available at the time of the review.
c. Cite the location of the vendor’s contractual Pricing Schedule Exhibit (i.e., typically
referred to as Exhibit A). The contract provided at OCC-044, Att.2 (Confidential), starting
at p. 180 includes a List of Exhibits at p. 188 which references the Pricing Schedule as
Exhibit B but was unable to locate the document. Additionally, EOE observed similar
documentation within EOE-024, Att.2 (Confidential). with a similar omission.
d. Referring to pp. 24-34, explain why the vendor billed for equipment during standby. As
part of the response, identify the total incremental charge for the equipment billed during
standby and separately identify the incremental equipment charge for the hours referenced
in subsection b.
Response:
Referring to Exhibit ACCT-2 (CLP-6)(MS24F), Outside Line Contractors, at Line 37, Asplundh
Construction Corp, in the amount of $377,813.
a. Asplundh was permitted to be on standby starting 0600-0630 because these crews were on
a 4-10 schedule. Not paying these crews standby time would have likely resulted in losing
the crews for the storm event, which the Company could not afford to do given the pending
conditions. The Company also needed the crews on standby to assist in any weather-
The Connecticut Light and Power Company
d/b/a Eversource Energy
Docket No. 26-05-10
Set EOE-06
Date Issued September 22, 2026
EOE-273
Page 2 of 2
related events that may occur prior to 1800. Without tree crews, the Company cannot
restore power or address emergencies and the Company retained the crews for that purpose.
The incremental cost for the standby billing on April 3, 2024 for the hours prior to the 1800
ERP declaration is $94,674.27.
b. These two individuals remained on system in CT. The individuals remained in Western
region to support any potential need for final support that may have been required. It was
determined they could be demobilized and they completed that process on April 5th which
included any required safety debriefs, equipment and material securement and travel
activities. The balance of their contingent traveled to another state to continue support. The
incremental cost for the standby billing for the timeframe requested on April 3 is $96,850.
c. The vendor’s contractual Pricing Schedule, identified as Exhibit B, was inadvertently
omitted from the Company’s responses to both OCC-044 and EOE-024. The Pricing
Schedule is now provided as EOE-273, Attachment 1 CONFIDENTIAL. The contractual
provisions addressing standby rates begin on page 3 of the Pricing Schedule.
d. The contractor is a Contractor of Choice (“COC”) and per the contract they are permitted
to charge for equipment. The total incremental charge for the equipment billed during
standby is $8,152. The total incremental charge for the equipment billed for the employees
mentioned in subsection b is $108.
As listed on the current system
Question(s) Answered 273 (Connecticut Light and Power Company dba Eversource Energy) Date Filed: 10/06/2026