Skip to main content

A prototype public docket site for the Connecticut Public Utilities Regulatory Authority

Utility Dockets and Filings

Interrogatory responses

Answers to questions 45, 60

ResponseFiled by Connecticut Light and Power Company dba Eversource Energy21 files
Part of docket 26-05-10Open
  • Electric
Application of The Connecticut Light and Power Company d/b/a Eversource Energy to Amend its Rate Schedules

Files21

Text of EOE-060 Attachment 13.pdf

Extracted from the file · 2 pages · 4,641 characters

Text of EOE-060 Attachment 12.pdf

Extracted from the file · 3 pages · 7,241 characters

Text of EOE-060 Attachment 11.pdf

Extracted from the file · 9 pages · 20,240 characters

Text of EOE-060 Attachment 10.pdf

Extracted from the file · 2 pages · 5,855 characters

Text of EOE-060 Attachment 9.pdf

Extracted from the file · 2 pages · 3,951 characters

Text of EOE-060 Attachment 8.pdf

Extracted from the file · 3 pages · 5,695 characters

Text of EOE-060 Attachment 7.pdf

Extracted from the file · 3 pages · 4,974 characters

Text of EOE-060 Attachment 6.pdf

Extracted from the file · 3 pages · 6,774 characters

Text of EOE-060 Attachment 5.pdf

Extracted from the file · 2 pages · 4,531 characters

Text of EOE-060 Attachment 4.pdf

Extracted from the file · 2 pages · 3,669 characters

Text of EOE-060 Attachment 3.pdf

Extracted from the file · 6 pages · 16,249 characters

Text of EOE-060 Attachment 2.pdf

Extracted from the file · 4 pages · 11,766 characters

Text of EOE-060 Attachment 1f.pdf

Extracted from the file · 1 page · 780 characters

  1. Page 1 of 12

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-01 Date Issued July 31, 2026 EOE-060 Attachment 1e Page 1 of 12 Template for Capital Project Review and Approval by a Subsidiary Board [Sponsoring Operating Unit or Corporate and Shared Services Group] [Project Title] Capital Project Review and Approval [Name of Subsidiary] Board of Directors [Sponsoring Officer] [Date of Submission] This information is intended for the use of internal management only and should not be discussed with or distributed to external parties.
  2. Page 2 of 12

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-01 Date Issued July 31, 2026 EOE-060 Attachment 1e Page 2 of 12 Subsidiary Board Project Authorization Contents ➢ Executive Summary Project Justification Project Solution & Benefits Project Alternatives ➢ Project Timeline ➢ Financial Evaluation ➢ Risk Assessment ➢ Authorization Criteria for IT Projects (if Applicable) Appendix ➢ Approval History 1
  3. Page 3 of 12

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-01 Date Issued July 31, 2026 EOE-060 Attachment 1e Page 3 of 12 Subsidiary Board Project Authorization Executive Summary Scope: ➢ Summary of project scope and description Estimated Project Costs by year ($ in millions): Prior 20XX 20XX 20XX Total In-Service Date Capital(1) $X.X $XX.X $XX.X $XX.X $XX.X O&M $X.X $XX.X $XX.X $XX.X $XX.X Total $X.X $XX.X $XX.X $XX.X $XX.X Month/Year (1) Direct and Indirect Capital Costs • Is project capital part of Original [20XX] Operating Plan • Is project O&M part of Original [20XX] Operating Plan Issues: Any project issues or risks should be included here for the subsidiary board’s consideration of funding approval (i.e., challenging or unusual permitting and siting requirements, new technology, coordination with other utilities) How cost variances to the Original [20XX] Operating Plan will be addressed (if applicable) Regulatory Approvals: (if applicable) Funding Request: ➢ Name of Subsidiary Board approval of $XX.XM for [business unit/shared services] to [restate project purpose] 2
  4. Page 4 of 12

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-01 Date Issued July 31, 2026 EOE-060 Attachment 1e Page 4 of 12 Subsidiary Board Project Authorization Project Justification ▪ Include the problem statement, project objectives, project scope, risk being mitigated 3
  5. Page 5 of 12

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-01 Date Issued July 31, 2026 EOE-060 Attachment 1e Page 5 of 12 Subsidiary Board Project Authorization Project Solution & Benefits ▪ Detailed description of the project including pictures and maps, as appropriate, and rationale as to why project provides the solution to the project need discussed on the prior page(s) ▪ Discuss impact of this project on other Eversource projects/initiatives (if any) ▪ Discuss use of or applicability of solution to other Eversource Companies (if applicable) ▪ Describe the benefits of the project, both qualitative and quantitative 4
  6. Page 6 of 12

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-01 Date Issued July 31, 2026 EOE-060 Attachment 1e Page 6 of 12 Subsidiary Board Project Authorization Project Timeline ➢ Include timeline of major project milestones ➢ Show the expected timing of capital expenditures along the timeline 5
  7. Page 7 of 12

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-01 Date Issued July 31, 2026 EOE-060 Attachment 1e Page 7 of 12 Subsidiary Board Project Authorization Financial Evaluation ▪ Insert a table which provides main components of direct and indirect capital costs. Provide information by year in detail or in an appendix as appropriate Main Component Time Period – by year and in total Direct: Labor Outside Services Materials Other (include contingency amounts) Indirect: Benefits Loaders Capitalized Interest or AFUDC if applicable Other (include contingency amounts) Total ➢ ➢ Provide estimated future costs that will result from the project and if they are included in the current Operating Plan Describe financial benefits resulting from the project including whether or not they are in the approved Operating Plan 6
  8. Page 8 of 12

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-01 Date Issued July 31, 2026 EOE-060 Attachment 1e Page 8 of 12 Subsidiary Board Project Authorization Financial Evaluation Financial metrics may include the following at the discretion of the project’s management and financial evaluation representative(s) Shareholder Metrics Detailed Capital Expenditures Detailed Capital Expenditure timing (by year) Expected Return on Equity (ROE) and Equity Percentage Net Present Value (NPV) and Internal Rate of Return (IRR) (using appropriate discount rate by company) Earning Per Share Contribution Customer Metrics Detailed Rate impacts Detailed Revenue Requirements analysis Present Value of Revenue Requirements Revenue Requirements Break-even year Project Specific Metrics Sensitivities +/- Capital Spend +/- O&M Spend Impact of timing delays Impacts to ROEs, NPVs, Earnings Payback period Other project-specific metrics (describe) Other Identification of alternative project options Financial metrics may be presented graphically if considered appropriate to assist in review and approval 7
  9. Page 9 of 12

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-01 Date Issued July 31, 2026 EOE-060 Attachment 1e Page 9 of 12 Subsidiary Board Project Authorization Risk Assessment Include a table which quantifies the identified risks to project implementation, calculates an estimated expected value of each such risk resulting in a total expected value risk exposure, and describes risk mitigation plans. Compare the contingency assumed in the total cost estimate to the total estimated expected value risk exposure. (Provided by Enterprise Risk Management following required risk assessment process) Risk Event Risk Horizon Risk 1 1Q-3Q 20XX Risk 2 April 20XXJuly 20XX Risk 3, etc. 20XX-20XX Total Identified Risk Likelihood of Occurrence Expected Value Cost Exposure ($M) % likelihood 0-100% Cost Exposure x Likelihood of Occurrence Risk Mitigation Mitigation Plan Cumulative Expected Value of Cost Exposure ➢ The Capital Cost Estimate includes a contingency of $______M compared to the total expected value cost exposure of $______M 8
  10. Page 10 of 12

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-01 Date Issued July 31, 2026 EOE-060 Attachment 1e Page 10 of 12 Subsidiary Board Project Authorization Authorization Criteria for IT Projects (if Applicable) ➢ Describe the applications that are impacted and include information regarding the interfaces and interdependencies related to this IT project ➢ Assess the fit of this IT project with the overall IT strategy ➢ Describe control matters, such as the processes for data migration, change management plan including impacts to business processes, data maintenance controls, whether or not this IT project will be or impacts a Sarbanes-Oxley critical application, and the business continuity plan 9

Text of EOE-060 Attachment 1d.pdf

Extracted from the file · 3 pages · 3,207 characters

Text of EOE-060 Attachment 1c.pdf

Extracted from the file · 5 pages · 7,956 characters

Text of EOE-060 Attachment 1b.pdf

Extracted from the file · 5 pages · 5,670 characters

Text of EOE-060 Attachment 1a.pdf

Extracted from the file · 16 pages · 34,194 characters

As listed on the current system

Question(s) Answered 45, 60 (Connecticut Light and Power Company dba Eversource Energy) Date Filed: 08/14/2026

This filing on the current system (opens in a new tab)