Compliance Filing, Order No. 15
Compliance with Order No. 15
Filed by Avangrid2 files
Part of docket 26-08-05Files2
2026-07-28 UI Order No. 15 Cover Letter #26-08-05.pdf
PDF · 163 KB · 3 pagesText searchable
Download 2026-07-28 UI Order No. 15 Cover Letter #26-08-05.pdfRead the text of 2026-07-28 UI Order No. 15 Cover Letter #26-08-05.pdf
2026-07-28 UI Attachment 1 - ESS Interconnection Report #26-08-05.xlsx
Excel · 20 KBText searchable
Download 2026-07-28 UI Attachment 1 - ESS Interconnection Report #26-08-05.xlsxRead the text of 2026-07-28 UI Attachment 1 - ESS Interconnection Report #26-08-05.xlsx
July 28, 2026
Mr. Jeffrey R. Gaudiosi, Esq.
Executive Secretary
Public Utilities Regulatory Authority
10 Franklin Square
New Britain, CT 06051
Re:
Docket No. 26-08-05, Annual Energy Storage Solutions Program Review – Year 6,
Compliance with Standing Order No. 15 of the Final Decision in Docket No. 25-08-05
Dear Mr. Gaudiosi:
The United Illuminating Company (“UI” or the “Company”) submits the following report to the
Public Utilities Regulatory Authority’s (“PURA” or the “Authority”) as compliance with Standing
Order No. 15 of the Final Decision issued on December 17, 2025 in Docket No. 25-08-05 (the
“Year 5 Decision”).
Standing Order No. 15 states:
Reference Decision, Nov. 29, 2023, Docket No. 23-08-05, Order No. 26, p. 62: No later
than August 1, 2024, and annually thereafter until the ESS Program stops accepting new
enrollments, each EDC shall file as compliance an ESS Interconnection Report, as detailed
in Section IV.D., in the applicable annual review proceeding (i.e., in 2024, Docket No. 2408-05). The Report shall consist of a summary of the state of interconnection for all
commercial ESS projects and shall include, at a minimum: (1) the interconnection status
of each commercial ESS project; (2) the expected EDC interconnection approval due date
for each commercial project per EDC interconnection guidelines, as applicable; (3) the
date all required interconnection materials were submitted to the utility for each
commercial ESS project; (4) the number of days from when all required interconnection
materials were submitted to the utility for each commercial ESS project up to the
completion of the interconnection process; (5) the attrition rate for all commercial ESS
projects, based on the withdrawal of a project’s interconnection application; (6) a list of
the most common reasons for ESS interconnection delays; and (7) EDC-proposed solutions
for each of the most common reasons delaying ESS interconnections.
In compliance with Standing Order No. 15, UI provides Attachment 1 - ESS Interconnection
Report to address data requests 1 through 5:
1. The interconnection status of each commercial ESS project - addressed in Column B
2. The expected EDC interconnection approval due date for each commercial project per EDC
interconnection guidelines, as applicable – addressed in Column C
3. The date all required interconnection materials were submitted to the utility for each
commercial ESS project – addressed in Column D
4. The number of days from when all required interconnection materials were submitted to
the utility for each commercial ESS project up to the completion of the interconnection
process – addressed in Column I
5. Of the 24 applications/projects captured, 12 have been withdrawn since submitting an
interconnection application. Leading to a total attrition rate of 50%.
In compliance with Standing Order No. 15, UI provides the following information to address
requests 6 and 7 raised by the Authority:
6. Consistent with the Authority’s directives in Docket No. 25-01-27, UI has reviewed and
incorporated relevant findings and recommendations from the 100-Day Sprint Report and
the Final Decision issued on July 18, 2025.
Participants in the 100-Day Sprint identified the below common causes for delays:
• Incomplete or inaccurate applications
• Complex technical reviews
• Regulatory compliance burdens
• High application volumes
• Multi-team coordination challenges
• Metering configuration and provisioning delays
• System inefficiencies and resource constraints
7. In alignment with the Authority’s approved proposals from the 100-Day Sprint Report and
the Final Decision in Docket No. 25-01-27, UI has implemented improvements to address
the following proposals:
• Proposal 5: PowerClerk has been enhanced to add a “chess clock”, which will
assign either the EDC or customer to a task, increasing assignee transparency and
reducing incomplete or inaccurate application correction times.
• Proposal 13: A mandatory pre-submission checklist for applicants has been
established within PowerClerk to reduce application errors and improve
completeness during the initial application stage.
• Proposal 42: Multiple process improvements have been implemented across meter
procurement, programming, and installation activities. These enhancements have
streamlined internal operations and accelerated the timeline from Authority Having
Jurisdiction (AHJ) approval to permission to operate.
The implementation of these solutions continues to assist with addressing the root causes
of delays and improve the overall efficiency of the interconnection application process.
I hereby certify service of this filing upon all parties and interveners of record in this proceeding.
Respectfully,
Sincerely,
James Nitz
Manager, Regulatory Services
UIL Holdings Corporation
As Agent for The United Illuminating Company
As listed on the current system
Compliance Filings, 07/28/2026 [26-08-05] Order No.15 / Avangrid / Compliance with Order No. 15