Written Exceptions
Filed by Connecticut Green Bank
- Type of filing
- Exception (Written Exceptions)
- Date filed
- November 10, 2026
- Filed by
- Connecticut Green Bank
- Files
- 1
As listed on the current system
Exception to Decision filed 11/10/2026 (Connecticut Green Bank) [26-08-05]
Files1
Docket No. 26-08-05 Green Bank Response to Request for Written Exceptions.pdf
PDF · 182 KB · 8 pagesText searchable
Download Docket No. 26-08-05 Green Bank Response to Request for Written Exceptions.pdfRead the text of Docket No. 26-08-05 Green Bank Response to Request for Written Exceptions.pdf
November 10th, 2026
Jeff Gaudiosi, Esquire
Public Utilities Regulatory Authority
10 Franklin Square
New Britain, CT 06051
RE:
Docket No. 26-08-05– ANNUAL ENERGY STORAGE SOLUTIONS PROGRAM
REVIEW – YEAR 6 – WRITTEN EXCEPTIONS
Dear Mr. Gaudiosi,
The Connecticut Green Bank (“Green Bank”) respectfully submits the following letter in lieu of
Written Exceptions below into the above referenced docket (“Docket”) in response to that certain
Notice of Request for Written Exceptions and the Proposed Final Decision (“PFD”) issued by the
Public Utilities Regulatory Authority (“PURA” or the “Authority”) on October 29, 2026 (the
“Notice”).
The Green Bank greatly appreciates the Authority’s extensive review and thoughtful refinement
of the Energy Storage Solutions (“ESS”) Program.
In particular, the Green Bank supports:
Adoption of the Bidirectional Charging Systems for Commercial & Industrial
(“C&I”)
o The Green Bank applauds PURA for its Proposed Final Decision to include
bidirectional charging systems in C&I projects.
Eligible Providers and Payment Beneficiaries
o As the homeowner tax credit for battery systems ends and third-party ownership
(“TPO”) becomes more prevalent, Program Administrators have received an
increasing number of inquiries regarding the recipients of performance payments.
The approval of an Eligible Provider definition and requirements as well as the
Eligible (“Institutional”) Payment Beneficiary section is very important. This
ensures that entities collecting payments on behalf of battery owners, including
lenders, contractors, and original equipment manufacturers (“OEMs”), undergo an
assessment of their experience and financial condition. This requirement protects
battery owners who assign their payments to such entities and will give battery
owners reassurance knowing they are trading their future performance incentive
payments to a reputable entity who has been assessed for experience and financial
health.
Improvements to the Enrollment Eligibility Timeframe
o Replacing multiple eligibility windows with a single requirement, which is
submission of an application within six months of approval to energize, clarifies
eligibility for battery owners and other stakeholders. This approach also reduces
the need for case-by-case determinations and minimizes disputes regarding late
applications. Eligible Contractors, Eligible Equipment, Eligible TPOs, etc., must
still be approved in the Program before Battery Energy Storage Systems
(“BESS”) are sold and installed, ensuring that customers are not marketed or sold
something that is not eligible for incentives. The risk is greater with a higher
performance incentive and differing eligibility offerings.
Operational Control
o Allowing the Program Administrators the ability to request sample telemetry files
during onboarding can help identify data issues before they affect battery
performance data reporting, performance incentive payments, clawbacks, or
benefit-cost results. The Program Administrators may present a more
substantiated penalty proposal next year as there are differences in each OEM’s
share of the Program’s BESS fleet and level of commitment to the Program, both
of which continue to evolve. The Green Bank appreciates PURA’s
acknowledgement of the probation and or suspension language that the Program
Administrators currently have in the Program if they fail to meet Program
requirements, which will be used judiciously. Suspending an OEM, BESS
Operator, etc., impacts current Program participants and puts them at risk for
clawbacks. Where a financial penalty, even a small one, allows room for growth
and better participation behavior.
Dashboard Additions
o Publishing performance payments by season, sector, and manufacturer provides
stakeholders with a comprehensive view of participant earnings and complements
the current data dashboard by enhancing transparency. This disclosure also
encourages manufacturers whose equipment underperforms to pursue continuous
improvement. Identifying dispatch events that coincide with the annual ISO-NE
system peak demonstrates whether the program is reducing demand during the
most valuable peak hour, a key driver of the benefits reflected in costeffectiveness scores.
Maintaining the Insurance Requirements for Eligible Contractors, TPOs, etc.
o Maintaining automobile and workers’ compensation insurance requirements for
Eligible Contractors, TPO, etc. in the Program helps ensure that accidents or
worker injuries occurring during installation are addressed through the
contractor’s or third-party owner’s insurance coverage. These requirements also
help protect customers from disruptions to project completion or ongoing service
resulting from an uninsured provider’s financial difficulties.
Removing Standing Order 2 and 7
2
o Removing Standing Order 2 and 7 is greatly appreciated as the elimination of
these two reoccurring compliance requirements will reduce the administrative
burden on the Program Administrators and allow resources to be redirected
toward program implementation, performance monitoring, and the continued
delivery of benefits to ratepayers. The Eligible Equipment is updated on the
website as the integrations are approved in both Electric Distribution Companies
(“EDC”) territories. The Energy Storage data is updated as frequently as possible
on the data dashboard1. The Green Bank supports efforts to streamline regulatory
reporting where existing program processes provide sufficient oversight and
transparency.
While the Green Bank supports the majority of PURA’s determinations, the Green Bank
respectfully submits some limited exceptions and requests for clarification in a small number of
areas below.
EXCEPTIONS AND CLARIFICATIONS
Front of the Meter (“FTM”) Working Group
The Green Bank appreciates the opportunity to administer (or co-administer) the FTM working
group and respectfully requests that PURA considers the following updates to the Order and that
doing so is consistent with CGS 16-243ee (i.e., Section 2 of Public Act 21-53, as amended).
Request for a Screening Phase
The Green Bank supports the Authority’s interest in determining whether FTM storage can
provide net benefits to Connecticut ratepayers. Green Bank respectfully requests that the
Authority establish a screening phase before directing the full FTM Storage Working Group
process. The purpose of the initial screening phase would be to determine whether the
distribution-level value available to FTM storage is sufficient to warrant a full working group
and tariff development effort.
The value stack available to a retail FTM storage tariff is narrow. As the PFD recognizes, a retail
tariff cannot compensate FTM storage for wholesale energy or ancillary service transactions, and
compensation must be structured to avoid duplicating wholesale market revenues (PFD, pp. 38–
39). It is not yet clear whether the remaining value, after meeting the Authority’s ratepayer
protection requirements, is sufficient to address the revenue gap identified by developers.
Green Bank proposes to submit an interim report to the Authority by March 1, 2027. The interim
report would include:
A preliminary assessment by the current ESS EM&V consultant of the distribution-level
value available to FTM storage2 and whether that value could support a viable tariff;
1
https://energystoragect.com/ess-performance-report/
It is the Green Bank’s understanding that the Authority is interested in evaluating FTM storage that may or may
not be additionally participating in the wholesale market.
2
3
Indicative bids for three scopes of work that together address the 11 topics identified in
the PFD: (A) technical, economic, and rate design analysis; (B) working group
facilitation and management; and (C) legal and regulatory analysis; and
A go/no-go recommendation on proceeding with the full working group scope.
Based on the interim report and indicative bids, Green Bank requests that the Authority confirm
whether Green Bank should proceed with the full working group scope, a subset of the scopes or
topics, or not proceed. Green Bank further requests that the deadline for the FTM Working
Group formation and the Storage Tariff Report be set relative to the date of the Authority’s
confirmation.
EDC Participation
Regardless of whether the Authority adopts the screening phase, Green Bank requests that the
Authority direct the EDCs to participate in the working group, rather than inviting them to
participate. The analysis required by the PFD depends on information only the EDCs hold,
including cost-of-service data, load and hosting capacity data, metering requirements and costs,
and draft rate calculations. Green Bank requests that the Authority direct the EDCs to provide
data and make relevant staff available as needed to support the working group’s analysis.
Flexibility in Determining Value
If the working group proceeds, Green Bank requests flexibility in how the value of FTM storage
is assessed. Green Bank strongly supports the Authority’s requirement that any FTM storage
tariff deliver net benefits to Connecticut ratepayers, and this request is not intended to lower that
standard or to revisit the established record on how storage delivers ratepayer value through the
ESS Program. The PFD requires that any recommended FTM tariff demonstrate a CT-RIM score
of at least 1.4, consistent with the ESS Program (PFD, p. 39).
A threshold was established for a behind-the-meter incentive program in Docket No. 17-1203RE03 which states, “the Authority directs the CGB to design upfront incentives, using the
2021 AESC, designed to deliver a RIM of 1.4 over the first three-year Program cycle.”3 The
Program Ratepayer Impact Measurement (“RIM”) is what has historically been used in ESS
rather than the Connecticut Ratepayer Impact Measurement (“CT-RIM”) though this data point
has been provided in previous annual reports as well as interrogatories as requested. The CTRIM may be a harder measurement for the Program and the FTM tariff to meet as a lot of what
storage does has regional benefits. The 1.4 Program RIM target was set for an incentive program
for customer-sited batteries, and a retail FTM tariff has a different cost structure.
A retail tariff that compensates FTM storage only for measured distribution-level benefits has a
different cost structure, and the threshold that best ensures robust ratepayer benefit may differ. It
may also be useful to identify the operating characteristics that drive ratepayer value, such as
siting behind highly loaded substations or performance during a minimum percentage of peak
hours, and design eligibility and compensation around those characteristics so that benefits are
delivered reliably. Green Bank requests that the working group be permitted to recommend an
3
https://www.dpuc.state.ct.us/2nddockcurr.nsf/8e6fc37a54110e3e852576190052b64d/6991ef77ba07bae1852587
52007994f7/$FILE/171203RE03-072821.pdf
4
appropriate valuation methodology and threshold, using the ESS Program RIM as the starting
point and ensuring the result provides ratepayer protection.
Role of the Green Bank
If the working group proceeds, Green Bank requests that the Authority clarify that Green Bank’s
role is to convene and facilitate the working group. The FTM Storage Tariff Report would
present both consensus and non-consensus positions of working group participants and should
not be construed as the position of the Green Bank. Green Bank should retain the ability to file
its own comments in any subsequent proceeding on an FTM storage tariff.
Cross-Filing
The Green Bank recommends that this report be cross-filed in the Successor Docket No. 26-0604, and any other dockets PURA deems appropriate. Given the breadth of topics the report must
address, the Green Bank recommends keeping this working group separate from other proposed
working groups in other dockets to ensure it can meet all goals established by PURA within the
specified timeframes to avoid scope creep.
Proposed Change to Docket No. 26-08-05 Standing Order 16 Regarding Clawback Fee
Waivers Submission Date
The Green Bank continues to face challenges meeting the November 1 deadline for submitting
clawback fee waiver requests under Standing Order 16 in Docket No. 26-08-05. For two
consecutive years, final performance incentive payments data compiled by the DERMS and
validated by the EDCs, has not been made available by that deadline. Reliance on estimated
performance incentive payments creates uncertainty in waiver recommendations and does not
serve customers or ratepayers, particularly because Standing Order 16 requires clawback fees to
be offset against eligible performance incentive payments before direct collection from
customers is pursued.
The Green Bank respectfully requests that the annual filing deadline under Standing Order 16 in
Docket No. 26-08-05 and any successor clawback orders in subsequent Final Decisions, be
moved from November 1 to December 1 to better align with the final performance incentive
payment timing. The schedule should provide sufficient time after payments are finalized to
reconcile project-level amounts, evaluate proposed waivers, and update the required RIM
analysis. Final payment data is necessary to determine the incentive payments available to offset
clawback fees and to assess reliably the ratepayer impacts of granting or denying waivers.
Aligning the deadline with this process would reduce reliance on estimates, minimize subsequent
corrections, and provide the Authority with a more complete and accurate consolidated
submission.
If final performance incentive payments are not provided by DERMS providers and validated by
EDCs in time to support a December 1 filing, the deadline should be extended to allow sufficient
time for reconciliation and review after their completion and before the January 15 RAM filings
are due. If that sequence is not feasible, the Green Bank respectfully requests that the deadline
under Order 5 for reporting Program Administrator costs in the RAM filings be moved to
5
February 15, allowing summer performance incentive payments and clawback totals to be
finalized before filing.
In Standing Order 16, PURA should determine whether no third-party performance incentive
payments fees are allowed on customers receiving clawbacks or if the third-party performance
incentive fee should be calculated after the clawbacks have been netted against eligible
performance payments as both of those options would ensure that recovering ratepayer’s dollars
takes precedence over fees paid to third parties. PURA could also authorize the PAs to pursue
recovery of outstanding clawback amounts from OEMs, TPOs, BESS Operators, DERMS or
other responsible third parties when the PAs determine that noncompliance resulted from failures
attributable to those entities rather than customer actions.
Green Bank Access to All Battery and EV Interconnection Applications and Managed
Charging Enrollments
Following the Application Working Group’s report, the Program Administrators reduced some
application requirements as the data was anticipated to be included in the interconnection
application for each project. For example, the Green Bank needs to confirm that an
interconnection application is open at the time of incentive reservation approval. At this time, the
need for expanded access to PowerClerk interconnection data to support the enrollment process
is being requested by the Green Bank. Limited access to PowerClerk data creates enrollment
challenges, strains relationships with customers and applicants, and generates additional
unnecessary work for customers, applicants, Program Administrators, and the EDCs’
interconnection teams. To address these issues, the Green Bank proposes the EDCs provide,
through established secure channels, all PowerClerk interconnection records for battery storage,
bidirectional electric vehicle supply equipment, and managed charging enrollment data by
January 1st, 2027 to ensure a better application experience for ESS participants.
With the allowance of commercial bidirectional charging systems in Energy Storage Solutions,
the Green Bank also needs access to Managed Charging Program enrollment data to cross-check
participation and prevent dual enrollment in managed charging and Energy Storage Solutions.
Providing access to managed charging enrollment data will also be needed to support any future
program expansion efforts to expand bidirectional charging eligibility to residential use cases.
The Green Bank supports the Authority’s determination that dual enrollment in the ESS and
managed charging programs is “not an immediate priority.” Given the significantly higher
incentive potential under ESS, the Green Bank anticipates that managed charging participants
may be interested in switching their enrollment to ESS if residential bidirectional charging
system eligibility is approved in the future. The Green Bank recommends evaluating this topic
during the Docket No. 27-08-05 cycle and following the August 1, 2027, compliance filing
focused on residential bidirectional charging system enrollment eligibility in ESS.
The Green Bank also notes that enrollment in the EDCs’ managed charging programs has slowed
significantly in 2026 since eligibility for their respective home EV charging and wiring rebates
was limited to income-qualified participants. Delivering this rebate has previously provided the
6
EDCs with a smooth way to enroll customers at-scale in their managed charging programs. The
Green Bank encourages the Authority to keep these managed charging customer enrollment
trends in mind as it considers how to best leverage bidirectional charging systems for long-term
grid resilience.
Together, access to interconnection records and managed charging enrollment data would help
identify eligible projects earlier, reduce duplicative information requests, and prevent enrollment
issues caused by unavailable data.
Self-Enrollment
The Green Bank has identified a gap in the Program’s enrollment requirements that allows
projects to enroll without an Eligible Contractor (described in the current Program Manual as
“Self-Enrollment”4). This gap is inconsistent with PURA’s determination that all Eligible
Contractors must meet insurance requirements. This gap also would allow contractors to operate
and enroll customers in the Program without any oversight of their business practices. To address
this issue, the Green Bank proposes revising the Program Manual to remove the Self-Enrollment
option and require an Eligible Provider for all enrollment pathways.
For context, the Self-Enrollment pathway was approved by PURA in 20225 to allow certain
Tesla customers to access Active-Only enrollment. At the time, Tesla opted not to participate in
ESS as an Eligible Contractor or Eligible Equipment, as Tesla opposed the Passive Dispatch
design. With the launch of “Construct 5” in April 2026, Tesla fully joined ESS and this pathway
is no longer utilized by new customers.
Revised Avoided Energy Supply Cost Study (“AESC Study”) Issuance
The Evaluation Measurement and Verification (“EM&V”) provider for Energy Storage Solutions
has indicated that the revised AESC Study has not yet been released and is expected in 2027.
Depending on its release date and the scope of the revisions, the study may affect the delivery of
the Program’s three-year and annual reports. Because the changes to the AESC Study remain
unknown, it is not yet possible to determine the extent of any required updates to the BCA
calculator or whether those updates can be completed in time to meet the June 15 deadline.
Accordingly, if the revised AESC Study is released before May 2027, it is proposed that the
deadline under Order 4 be extended to August 1 to align with the deadline under Order 3.
4
5
Energy Storage Solutions Program Manual, Sec. 3. May 19, 2026
Docket No. 22-08-05 Decision (ESS Year 2 Review). December 21, 2022
7
The Green Bank greatly appreciates the opportunity to contribute and the Authority’s
consideration of the above Written Exceptions.
Respectfully submitted,
By: Sergio Carrillo
Sergio Carrillo
Managing Director of Incentive Programs
Connecticut Green Bank
Phone: [phone removed]
[email removed]
8