Written Comments
Filed by Connecticut Green Bank
- Type of filing
- Comments (Written Comments)
- Date filed
- August 28, 2026
- Filed by
- Connecticut Green Bank
- Files
- 1
As listed on the current system
Written Comments - 08/28/2026 [26-08-05] (Connecticut Green Bank)
Files1
Docket No. 26-08-05 Green Bank Response to Request for Written Comments ESS 2.pdf
PDF · 162 KB · 5 pagesText searchable
Download Docket No. 26-08-05 Green Bank Response to Request for Written Comments ESS 2.pdfRead the text of Docket No. 26-08-05 Green Bank Response to Request for Written Comments ESS 2.pdf
August 28th, 2026
Jeff Gaudiosi, Esquire
Public Utilities Regulatory Authority
10 Franklin Square
New Britain, CT 06051
RE:
Docket No. 26-08-05– ANNUAL ENERGY STORAGE SOLUTIONS PROGRAM
REVIEW – YEAR 6
Response to Request for Written Comments 2
Dear Mr. Gaudiosi,
The Connecticut Green Bank (“Green Bank”) respectfully submits Written Comments below into the
above referenced docket (“Docket”) in response to that certain Notice of Request for Written Comments
issued by the Public Utilities Regulatory Authority (“PURA”) on August 12th, 2026 (the “Notice”). The
section below is organized based on the corresponding sections in the Notice.
The Green Bank greatly appreciates the opportunity to provide Written Comments in the abovementioned docket and would like to address the following items in its response: 1. Recommended
Programmatic Changes and 2. Bidirectional Electric Vehicle (EV) Participation
CONNECTICUT GREEN BANK RESPONSE:
1)
Recommended Programmatic Changes
The Green Bank supports all of the proposed Program Administrators’ recommendations. The
recommendations incorporate lessons learned, support the transition to Construct 5, strengthen
grid and ratepayer value, expand participation opportunities, and reduce administrative and
technical barriers We address a few of these recommendations below.
Operational Control & Telemetry requirements
Reliable performance data is essential to incentive calculations, Program evaluation, and EM&V
efforts. The proposal appropriately balances flexibility in communication protocols with
telemetry standards, audits, and enforcement mechanisms. These changes advance Program
Objectives 1, 3, and 5.
Bidirectional Electric Vehicle (EV) enrollment for Medium and Heavy Duty
The Green Bank supports continued development of a bidirectional EV enrollment pathway.
Bidirectional EVs could expand dispatchable distributed resources and support Program
Objectives 1, 2, and 3. Additionally the Green Bank supports EOE’s recommendation that
Bidirectional EV charging be included in future clean energy Programs as well.1
Legacy Change Orders
The Green Bank also supports reasonable flexibility for Legacy project change orders. Changes in
system kW or kWh can occur during normal project development and should not unnecessarily
cause an otherwise viable project to lose its eligibility. At the same time, allowing PA discretion
to determine if a change is reasonable or not would be beneficial as to not have to create another
rule or wait for a determination to close a project out. This recommendation advances Program
Objectives 3 and 5.
Add-on Systems
Legacy customers should not be unnecessarily prevented from adding useful storage capacity
solely because their original systems already participate under a closed Passive Dispatch tranche.
Allowing on a case-by-case basis either repayment of the unearned upfront incentive and
conversion to the current incentive structure or, where appropriate, a blended Performance
Incentive Rate provides flexibility while preserving appropriate treatment of previously
incentivized capacity. This recommendation advances Program Objectives 2, 3, and 5 by
facilitating additional grid-capable storage deployment while maintaining an orderly incentive
framework.
Seasonal Performance Incentives & Round Rates
The Green Bank supports the proposed seasonal Performance Incentive payment structure and
clarification of seasonal incentive amounts. Given the identified DERMS limitations associated
with administering a single annual payment, two seasonal payments are what the DERMS is
accustomed to administering. Rounding the Underserved and Low-Income rates simplifies
implementation and customer communications. These changes support orderly Program
administration and continued access to enhanced incentives for priority customers and therefore
advance Program Objectives 3, 4, and 5.
The Green Bank supports all of the proposed Program Administrators’ recommendations and has
a few more considerations below.
Customers that Move
As the Program has developed, and with consideration of the upfront or potential enrollment
incentive, clear guidelines should be established for circumstances in which an Energy Storage
Solutions customer sells a home where an enrolled battery system is installed. The Program
Administrators should avoid a process that unnecessarily interrupts the battery’s participation in
1
https://www.dpuc.state.ct.us/dockcurr.nsf/4b3c728dd1c0d642852586db0069aa70/762811be4899161685258e5f
005d67ba/$FILE/26-06-04%20EOE%20Written%20Comments%20FINAL.pdf
2
the Program solely because ownership of the home has changed and the new homeowner has not
yet completed enrollment.
Under the current DERMS enrollment process, the EDCs may identify that a customer has moved
when the associated utility account number changes, including at the end of a summer or winter
performance season. A change in customer account number triggers an automatic unenrollment of
the BESS from the DERMS, and it remains unenrolled until the new homeowner affirmatively
completes a new enrollment. The Program risks losing the participation of an otherwise eligible
and operational asset. This concern is heightened because the Program’s shoulder-month
enrollment windows are limited, leaving little practical time to identify the new homeowner,
obtain updated documentation, and complete reenrollment before the next performance period.
For these reasons, PURA should require that the EDCs, through their DERMS providers, keep the
battery system enrolled under the original customer until the new homeowner is able to complete
the reenrollment process. This approach supports continuity of Program operations, allows the
battery to continue contributing to Program goals, and reduces the likelihood that a participating
system will be lost due to an administrative gap during a real estate transfer. It also recognizes
that only the EDCs have access to timely information regarding utility account changes, while the
original homeowner may have limited incentive to facilitate reenrollment if a clawback could
apply for non-performance.
Allowing the system to remain enrolled during this transition means payments could continue to
be issued to the original customer by check or other existing payment method until the new
homeowner completes enrollment. This is because ESS Performance payments are not paid
through on-bill enrollment. This interim treatment would help avoid unnecessary lag time,
prevent the loss of an available distributed energy resource, and provide a clear and
administratively workable rule for homeowner transitions. Accordingly, the Program should
establish guidance that maintains enrollment of the battery system during the transition period
and avoids interruption of participation while the new homeowner is brought into the Program.
In addition to customers moving, the Green Bank believes there may be some exceptions that
might need to be granted on clawbacks due to unforeseeable reasons such as death, foreclosure,
or other legal issues outside the control of the Program Administrators. Allowing the Program
Administrators to have discretion is needed to allow for these natural and unforeseeable issues.
Counterfactual 6
Green Bank supports use of Counterfactual 6 (CF6) for Energy Storage Solutions because CF6
better reflects the forward-looking grid conditions in which storage resources are expected to
operate. While Counterfactual 1 may be appropriate for C&LM because it excludes incremental
energy efficiency, Energy Storage Solutions is not an energy efficiency program and should be
evaluated using assumptions that reflect the broader system context storage is intended to support.
CF6 was also not available at the launch of the Energy Storage Solutions Program which is why it
was not originally proposed for use in the Program.
3
Interconnection
In addition to the annual Order 15 filings in Docket No. 25-08-05 regarding the interconnection
status of projects in the Energy Storage Solutions Program, it would be beneficial for the industry
and stakeholders to have transparent access to all initially proposed, itemized interconnection
costs quoted by the EDCs, beyond application fees, for each project that enters the
interconnection queue. Providing transparent visibility into the upgrades or additional work
deemed necessary for each project, in a format that enables comparison across projects and EDC
territories, would support greater industry understanding to some of the attrition rates the Program
is seeing.
Including final itemized cost information for all upgrades and studies at each stage of the
interconnection process to see where costs change the most during the process would also help
identify exactly where developers may have been required to abandon projects and would provide
greater transparency to support more accurate project cost estimates in the future. While this
transparency alone would not resolve interconnection delays or other challenges developers may
encounter, it would help the industry better assess instances in which costs may be unreasonable
or inequitable.
2) Bidirectional Electric Vehicle (EV) Participation
The Green Bank reiterates its support for the joint recommendations provided by the Program
Administrators in the Bidirectional EV Working Group Final Report to advance vehicle-to-grid
(“V2G”) charging opportunities for commercial fleet operators in Summer 2027.
In response to the Authority’s specific comment request on ratepayer benefits regarding bidirectional
EV participation in ESS versus managed charging, the Green Bank notes that the EDCs recently
published their Joint Annual Report – Program Cycle Year 5 in Docket No. 26-08-032. Attachment
133 associated with the Annual Report includes specific discussion of residential EV managed
charging participation data and program developments. The Green Bank encourages the Authority to
utilize the findings made available in Section V. 2025-2026 Off-Peak Managed Charging Impacts to
evaluate the potential grid resiliency benefits of managed charging participation versus theoretical,
future residential bidirectional EV participation in ESS. Doing so may require specific EM&V
analyses of the overall ratepayer benefits accrued through residential EV participation in managed
charging. In terms of evaluating average resource potential across these two distinct vehicle-toeverything technologies, the Green Bank notes that participants in the Bidirectional EV IES pilot
2
https://www.dpuc.state.ct.us/dockcurr.nsf/8e6fc37a54110e3e852576190052b64d/a9fb8a951709e89b85258e480
066e9a5/$FILE/2026-0803%20Attachment%2013%20Residential%20Managed%20Charging%20Load%20Impact%20Evaluation%20%232608-06.pdf
3
https://www.dpuc.state.ct.us/dockcurr.nsf/8e6fc37a54110e3e852576190052b64d/a9fb8a951709e89b85258e480
066e9a5/$FILE/2026-0803%20Attachment%2013%20Residential%20Managed%20Charging%20Load%20Impact%20Evaluation%20%232608-06.pdf
4
utilize 11.5 kW bidirectional chargers. The Green Bank recommends that this topic be evaluated in
the future V2G-focused docket that the Program Administrators recommended establishing in the
Bidirectional EV Working Group Final Report.
CONCLUSION
The Green Bank appreciates the opportunity to submit these Written Comments in Docket No. 26-08-05
and looks forward to continuing to work with PURA and the Program Administrators to ensure the
continued success and effective administration of the Energy Storage Solutions Program.
Respectfully submitted,
By:
Sergio Carrillo
Managing Director of Incentive Programs
Connecticut Green Bank
Phone: [phone removed]