Interrogatory responsesFiled by CL&P dba Eversource Energy
Answers to questions 1 thru 14
- Type of filing
- Response (Interrogatory responses)
- Date filed
- March 31, 2026
- Filed by
- CL&P dba Eversource Energy
- Files
- 16
As listed on the current system: Question(s) Answered 1 thru 14 (CL&P dba Eversource Energy) Date Filed: 03/31/2026
Files
RSR-001 Attachment 1.pdf
PDF · 3.0 MB · 49 pagesText searchable
Download RSR-001 Attachment 1.pdfRead the text of RSR-001 Attachment 1.pdf
RSR-005, Attachment 1.pdf
PDF · 2.0 MB · 1 pageText searchable
Download RSR-005, Attachment 1.pdfRead the text of RSR-005, Attachment 1.pdf
Text of RSR-001.pdf
Extracted from the file · 772 characters
CL&P dba Eversource Energy
Docket 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-001
Page 1 of 1
Date Filed: March 31, 2026
Witness:
Freeman, Lavelle A
Request from: Public Utilities Regulatory Authority
Question:
Provide the most up to date version of Eversource’s Distribution System Planning Guide.
Response:
The “Distribution System Planning Guide” filed in Docket No. 17-12-03RE07 in response to
Request RSR-013, included here as RSR-001, Attachment 1, remains the most current and
effective version of the document on record. Eversource has initiated a comprehensive revision of
the Distribution System Planning Guide, and the Company anticipates that the updated version
will be finalized and made available prior to the conclusion of this calendar year, 2026.
Text of RSR-001 Attachment 1.pdf
Extracted from the file · 60,000 characters (the first 60,000 are kept)
CL&P dba Eversource Energy
Docket No. 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-001, Attachment 1
Page 1 of 49
DSPG 2020
(Revision 00)
1.
Distribution System Planning Guide
Approved: September 22nd, 2020
CL&P dba Eversource Energy
Docket No. 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-001, Attachment 1
Page 2 of 49
Copyrights
Eversource Energy Copyright © 2020 All rights reserved.
Updating Standards documents
Users of this standard should be aware that these documents may be superseded at any time by the
issuance of new editions or may be amended from time to time through the issuance of amendments. The
official standard, at any point, consist of the current edition of the document together with any amendment.
In order to determine whether a given document is the current edition and whether it has been amended,
visit the standard Bookshelf Site or contact System Planning.
2
Eversource Energy Copyright © 2020 All rights reserved.
CL&P dba Eversource Energy
Docket No. 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-001, Attachment 1
Page 3 of 49
Contents
1.
Overview
4
1.1. General .......................................................................................................................................................... 4
1.2. Scope ............................................................................................................................................................. 4
2.
Planning Criteria
5
2.1. Introduction ................................................................................................................................................... 5
2.2. Thermal Loading Criteria .............................................................................................................................. 5
2.3. Substation Transformer ................................................................................................................................. 5
2.4. Voltage .......................................................................................................................................................... 7
2.5. Power Quality ................................................................................................................................................ 9
2.6. Load Density ................................................................................................................................................. 9
2.7. Reliability ...................................................................................................................................................... 9
2.8. Standard Substation Design ......................................................................................................................... 10
2.9. Substation Upgrade Criteria ........................................................................................................................ 12
2.10. Feeder Upgrade ......................................................................................................................................... 13
2.11. Battery Energy Storage System Design Criteria........................................................................................ 13
2.12. Network Criteria ........................................................................................................................................ 18
2.13. Distributed Energy Resources Criteria. ..................................................................................................... 19
3.
Rating Criteria
20
3.1. Feeder Rating .............................................................................................................................................. 20
3.2. Rating of Feeder Supplying Secondary Networks ....................................................................................... 21
3.3. Transformer Rating ..................................................................................................................................... 21
4.
Planning Methodology
24
4.1. Introduction ................................................................................................................................................. 24
4.2. Process Map ................................................................................................................................................ 24
4.3. Model Development .................................................................................................................................... 24
4.4. Gross Load Model and DER Forecast ......................................................................................................... 26
4.5. Planning Model ........................................................................................................................................... 32
4.6. Study Methodology ..................................................................................................................................... 34
4.7. Documentation of System Constraints ........................................................................................................ 37
4.8. Solution Development ................................................................................................................................. 37
4.9. Planned and Proposed Upgrades ................................................................................................................. 41
5.
References
43
6.
Definitions and acronyms
44
6.1. Definitions ................................................................................................................................................... 44
6.2. Acronyms .................................................................................................................................................... 46
7.
Annex A (informative)
47
7.1. Reference Documents .................................................................................................................................. 47
7.2. Attachment D of Capital Project Approval Process .................................................................................... 48
7.3. Distribution System Planning Substation Review Template ....................................................................... 48
3
Eversource Energy Copyright © 2020 All rights reserved.
CL&P dba Eversource Energy
Docket No. 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-001, Attachment 1
Page 4 of 49
1. Overview
This Distribution Planning Guide has been developed to provide Eversource Energy (“the Company”) with a
consistent uniform approach to designing an efficient and reliable electric distribution system to provide the quality
of service expected by our customers. The Planning Guide is aligned with applicable safety codes, regulatory
requirements, and industry standards (referenced in Section 5) and provides uniform criteria and design standards
across the Eversource Service Territory for all aspects of the System Planning Process.
The electric power industry is undergoing significant change with: increasing customer expectations for reliability
and resiliency; widespread adoption of new, often disruptive, technologies including Distributed Energy Resources
(DER), electric vehicles (EV), and smart homes; utility grid modernization initiatives; and a rapidly evolving
regulatory landscape. These changes and other advancements have not altered the basic mission of the distribution
system, but have impacted the way we way approach planning, the data sources and methods, scenarios and
simulation cases, and the range of possible solutions considered for mitigation.
The Company’s unique electric system, supplying both high density urban areas and rural areas across three states,
affords planners a great degree of flexibility in adapting the system to meet customer needs in a cost-effective
manner. However, due to the legacy standards and practices in different operating areas, there is pressing need to
harmonize standards and practices across the Company and provide clear, uniform consistent guidelines for how and
when to expand the system to meet load and DER growth. The application of these panning standards will provide
long term improvements in system performance in response to recent challenges facing the electric utility industry.
1.1. General
The basic goal of distribution planning is to provide orderly, economic expansion of equipment and facilities to meet
future system demand with acceptable system performance. The key planning objectives include:
•
•
•
•
•
Build sufficient capacity to meet instantaneous demand
Satisfy power quality/voltage requirements within applicable standards
Provide adequate availability to meet customer requirements
Deliver power with required frequency
Reach all customers wherever they exist
Since the electric utility is often the provider of last resort, planning the system is delicate balance between
performance and cost. Planning engineers must identify the goals for system performance, understand how
differences in system design and equipment will affect achievement of the goals, and find the most suitable design
solution to meet performance goals.
Balancing cost and performance to find the most suitable design solution is made more challenging by a number of
factors, including performance pressures, cost escalation, aging infrastructure, DER/EV penetration, and
state/regulatory mandates.
This Distribution Guide outlines the planning criteria, design and analysis methods and engineering rationale for
effectively expanding the distribution system to meet demand. The planning criteria builds upon existing company
standards, mainly the Distribution System Engineering Manual (DSEM) and the SYSPLAN standards, as well other
legacy standards such as NH - ED3002.
1.2. Scope
The scope of the Distribution Planning Guide is comprehensive, including traditional planning considerations for
expanding the system to avoid capacity, voltage and reliability violations as well as advanced planning concepts
related to Non-Wires Solutions (NWS), Battery Energy Storage System (BESS) and other DER application, and
integrated load/DER forecasting with EV adoption.
The foundation of the planning methodology is an advanced distribution analysis platform to enable key planning
activities. The application can import system models from GIS, integrate demand and DER data from linked sources,
and incorporate forecast and adoption models to build daily (24-hour) and yearly (8760-hour) planning scenarios.
4
Eversource Energy Copyright © 2020 All rights reserved.
CL&P dba Eversource Energy
Docket No. 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-001, Attachment 1
Page 5 of 49
2. Planning Criteria
2.1. Introduction
This guide defines the criteria Eversource uses to determine how to plan and design the system to avoid loading,
voltage, and reliability violations during normal and emergency system operation, as defined is Reference Section 5.
2.2. Thermal Loading Criteria
The topics below define the application of thermal loading criteria for substation transformers and conductors used
in the distribution system.
The methods for determining the normal and emergency rating of bulk distribution transformers is covered in
Section 3 of this document. Eversource Distribution System Engineering Manuals (refer to Section 5 references)
provide the methods for determining the normal and emergency rating for distribution lines and equipment. The
criteria below define the safe and reliable utilization of rating limits, specified by Eversource Standards, under both
normal and emergency conditions. They address the existing system design as well as future design changes planned
for the distribution system.
When analyzing system load versus Normal, Emergency, LTE, and STE ratings, it is done with respect to the
applicable seasonal ratings (e.g. winter and summer).
2.3. Substation Transformer
The design criteria noted below may be more restrictive than a transformer’s Normal rating. This does not
necessarily limit the actual operation of the transformer equipment, which may be utilized to the full extent of its
normal rating, but it provides for pre-load conditions that will maintain the equipment below acceptable LTE and
STE rating following emergency conditions.
Bulk Distribution Transformer loading is evaluated on a winding basis, that is the load carried by each individual
winding is evaluated against that winding’s rating(s). Bulk Distribution Transformer windings shall have ratings
determined per the requirements of Eversource Procedure SYSPLAN 008, refer to Section 3.3, and shall be applied
in the following manner.
Bulk Transformers, Normal Operation – CT/MA
Loading Up To 75% of The Normal Rating:
Bulk transformer winding loads (expressed in Amperes or MVA), should not exceed 75% of the normal rating,
under normal (scheduled) operating conditions/configurations.
Notes:
•
When determining LTE and STE ratings of a transformer winding, a 75% pre-load condition is assumed.
Therefore, to protect the integrity of the emergency ratings, normal loads should be limited to 75% of the
normal rating 1.
•
Loading up to 100% of normal ratings can be used for single transformer substations, when that transformer
is not relied upon to provide secondary supply to another bulk distribution supply bus.
Loading Between 75% of The Normal Rating and the Long-Term Emergency (LTE) Rating:
Bulk transformer winding loads above the normal rating, but below the LTE rating are allowed for one Event (24hour load cycle). Transformer winding loads within this range result from contingency events in the distribution
1
Applies to transformers that provide contingency (N-1) supply to load normally served by other transformers. Utilization at this level balances the
maximization of the contingency STE rating with that of base capacity, ensuring that a substation has sufficient capacity to maintain continuity of
service for customers in the event of loss of a transformer.
5
Eversource Energy Copyright © 2020 All rights reserved.
CL&P dba Eversource Energy
Docket No. 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-001, Attachment 1
Page 6 of 49
system or within substations (loads in this range may result from ABR operations).
Note:
Load transfers (within the distribution system) or installation of a mobile transformer should be available to lower
winding loads to the normal rating (or below) for subsequent load cycles following the contingency, or until the
system can be returned to normal conditions.
Loading Between the Long-Term Emergency (LTE) Rating and the Short- Term Emergency (STE)/ Drastic
Action Limit (DAL) Rating:
Bulk transformer winding loads above the LTE rating, but below STE/DAL rating must be lowered to below the
LTE rating within 30 minutes.
Loading Above the Short-Term Emergency (STE)/Drastic Action Limit (DAL) Rating:
Loading transformer windings above the STE/DAL rating is not acceptable under planning criteria for any duration.
This is intended as an emergency operational practice only. Automatic protection schemes shall be applied when
needed to prevent loading bulk substation transformer above the STE rating.
Note:
Operating a transformer, for any duration, at loading levels above the STE rating can result in loss of life or in
extreme cases, increased risk of catastrophic internal failure of the transformer.
Bulk Transformers, Normal Operation – NH
For all transformers in New Hampshire, loading shall not exceed 95% of the Normal rating. Maintaining transformer
loading at a higher threshold under normal (N-0) system conditions increases the risk of equipment failures and
exposure to customer reliability interruptions under N-1 contingency conditions. This variation in design criteria,
from the standard 75%, is to allow maximum utilization of the existing population of 34.5kV transformer that do not
exhibit a significant reduction on STE rating when applying a 95% preload. For those transformers where STE
performance impacts the ability to restore customers automatically (as per Section 2.8) the standard 75% preload
should be maintained.
Non-Bulk, Normal Operation (N-0)
For all non-bulk transformers on the Eversource system, planned loading shall not exceed 100% of the Normal
rating.
Non-Bulk, Contingency Operation (N-1)
With available load transfers, the loading on a transformer shall be reduced to below the LTE rating. Load levels can
only be sustained above the Normal rating for one load cycle.
2.3.1. Loading Limits for Conductors used in the Distribution System:
The topics below define the application of thermal loading criteria for conductors used in the distribution system,
calculated values for cable and wires thermal loading limits in Amps is provided in the DSEM Section 08.00 by
conductor type.
Cables and Wires supplying underground and Overhead Areas:
Normal Operation (N-0)
During normal system conditions, load levels shall not exceed the Normal rating. The normal rating is the maximum
loading without incurring loss of life above the design-loading limit.
6
Eversource Energy Copyright © 2020 All rights reserved.
CL&P dba Eversource Energy
Docket No. 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-001, Attachment 1
Page 7 of 49
Contingent Operation (N-1)
Cables
During contingent system conditions of the electric system, load levels may not exceed Normal Ratings for Cables 2.
System changes shall be developed when cable limits are expected to exceed 100% of Normal rating during
contingency operations. Operating above the Normal rating may involve loss of life or loss of tensile strength for
conductors, loading must be reduced after one load cycle (24-hour period)
Wires
During contingency system conditions of the electric system, load levels may not exceed the following criteria:
• NH – Wires shall not exceed emergency rating, as per Distribution System Planning and Design Criteria
Guidelines (ED-3002)
• CT/MA – Wires shall not exceed normal rating 3
2.3.2. Load Balance
Distribution feeders shall be arranged in order to give the best possible load balance on the system. In Distribution
feeders where load imbalance exceeds 50 amps between phases, necessary improvements should be considered to
reduce imbalance to less than 50 amps.
2.3.3. Feeders Supplying Underground Network System:
All network feeders are designed to operate within their normal rating at all times of the year. In addition, the
feeders are designed to operate within their normal ratings in the event of the loss of any one (N-1) feeder in the
grid. This is done in order to provide some level of protection against a double contingency. The feeders should also
be designed to operate within their LTE rating in the event of a double (N-2) contingency.
2.3.4. Distribution Supply System (DSS) Lines
Under normal configuration the loads of all lines (in service) in the line group will be below the normal ratings at all
times.
During a single contingency (N-1) condition, where one of the lines is out of service, the load on any one of the
remaining lines should not exceed its long-term emergency (LTE) rating.
2.4. Voltage
Operating voltage limits allowed on Eversource Energy Distribution circuits, principally for residential or
commercial services, are covered in the DSEM (refer to Sections 5 and 7). These voltage limits are also used as a
reference when analyzing customer voltage problems and designing distribution circuits.
Upper and Lower Voltage Limits
State
CT
MA
Voltage Limits
Connecticut upper and lower voltage limits are those prescribed in Section 16−11−115,
Voltage Variations, of the Regulations of Connecticut State Agencies. Voltage excursions
above the upper limit shall not exceed one minute. American National Standards Institute
(ANSI) C84.1−2016 shall be used to determine the lowest temporary voltage excursions
permissible.
Massachusetts limits are based on voltage guidelines in ANSI C84.1−2016.
2
In compliance with the Department’s guidance in Docket Number 17-12-03, PURA Investigation into Distribution System Planning of the Electrical Distribution
Company
3
In compliance with the Department’s guidance in Docket Number 17-12-03, PURA Investigation into Distribution System Planning of the Electrical Distribution
Company
7
Eversource Energy Copyright © 2020 All rights reserved.
CL&P dba Eversource Energy
Docket No. 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-001, Attachment 1
Page 8 of 49
State
NH
Voltage Limits
New Hampshire limits are based on New Hampshire Code of Administrative Rules, Rule 304,
Quality of Electric Service. These limits are based on voltage guidelines in ANSI C84.1.
Table 1- Upper and Lower Voltage Limits
Contingency Voltage Limits
CT, MA, and NH state regulations allow for temporary voltage excursions outside the normal range at the customer
service entrance during contingency operating conditions. Some examples of temporary contingency conditions are
listed below. For CT, temporary voltage below the lower limit should not exceed 24 hours where practical. Voltage
excursions above the upper limit are not identified by magnitude but shall not exceed one minute. For WMA and
NH, voltages above and below normal limits are based on ANSI C84.1 guideline and shall be limited in extent,
frequency, and duration. When they occur, corrective measures shall be undertaken within a reasonable time to
improve voltages to meet normal voltage range requirements.
Contingency operating conditions, when temporary voltage excursions are allowable, include (but are not limited to)
the following:
• Autoloops when a circuit, or part of a circuit, is being supplied through a tie recloser
• Automatic transfer schemes when fed by the backup feeder
• Contingent, manually switched supply to load in response to an interruption of normal supply routes or as
needed for line construction, not exceeding 24 hours in expected duration
• Secondary networks with one or more supply feeders out of service
• Secondary networks with one or more network transformers out of service
• Forced outages of bulk power transformers
• Forced outages of transmission lines
Additional information on voltage variation among phases and calculation of voltage unbalance is included in the
Distribution System Engineering Manual Section 05.131 to 05.135 (refer to Section 7),
High and Low Normal and Contingency Limits Summary
The Tables below list the high and low normal and contingency service voltage limits for all three states in the
Eversource system:
Nominal
Voltage
120
Normal
High Limit
123.6
208
214.2
197.6
190.7
240
247.2
228.0
220.0
277
285.3
263.2
253.9
480
494.4
456.0
440.0
618.0
570.0
550.0
600
Normal Low
Limit
114.0
Contingency Low
Limit
110.0
Table 2- Connecticut Service Voltage Limits (Volts)
Nominal
Voltage
120
Normal High
Limit
126
Contingency
High Limit
127
Normal Low
Limit
114
Contingency
Low Limit
110
208
218
220
197
191
240
252
254
228
220
277
291
293
263
254
480
504
508
456
440
8
Eversource Energy Copyright © 2020 All rights reserved.
CL&P dba Eversource Energy
Docket No. 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-001, Attachment 1
Page 9 of 49
Nominal
Voltage
600
Normal High
Limit
630
Contingency
High Limit
635
Normal Low
Limit
570
Contingency
Low Limit
550
Table 3- Massachusetts & New Hampshire Service Voltage Limits (Volts)
2.5. Power Quality
System Planning follows the latest approved version of the “Eversource DER Information and Technical
Requirements for the Interconnection of the Distributed Energy Resources (DER)” to complete analysis of:
• Steady-state Thermal and Voltage Criteria
• DER Impact on Voltage Regulating Equipment
• Transformer Reverse Power Capability
• Rapid Voltage Change and Voltage Flicker
• 3V0 Assessment 4
System Planning also follows the transient overvoltage curve in IEEE Std. 1547−2018, clause 7.4.2. limiting the
transient overvoltage to less than 1.2pu. This is a critical section due to potential load rejection overvoltage (LROV)
by the inverters, which can potentially cause damage to utility equipment, and/or nearby customer equipment.
2.6. Load Density
One important metric utilized by Planning Organizations, to determine the substation design and reliability criteria
required to supply specific geographic areas is load density. This is defined by Distribution System Planning as
MWh Energy Demand for a whole year over the Supply Area in square miles:
• High Load Density areas are those greater than 750MWh/square miles or comparable to Downton
Boston, MA.
• Medium Load Density areas are those between 250MWh/sq-mi and 750MWh/sq-mi or comparable to
Stamford, CT and Somerville Area, MA.
• Low Load Density areas are those less than 250MWh/sq-mi or comparable to Plymouth, SEMA.
MWh Energy Demand is calculated by using a sampling rate of 1 hour and actual MWh readings for an entire year
(8760 hours) from all the distribution stations supplying the targeted geographic area. The Supply Area (square
miles) is the geographic boundary of all the distribution circuits that normally supply load via the targeted stations.
The distribution circuit boundary extends up to the last distribution or non-bulk transformer supplied by the targeted
Substation and does not cover the length of additional tie lines to other stations. The geographic boundary includes
all habitable land, including small parks and recreational areas, but not the areas covered by large green areas or
water bodies (state forest, large parks, ocean, lake, ponds, and/or wetlands).
Based on the above definition:
• Area Work Centers (AWC) in the CT and NH service territory currently fall within the Low to Medium
Load Density Criteria
• Somerville and Mass Ave AWC fall within Medium to High Load Density Criteria
• Metro Boston Network area falls within the High Load Density Criteria
• Other MA service territory (except for Somerville, Mass Ave and Metro Boston) currently fall within
the Low to Medium Load Density Criteria.
2.7. Reliability
2.7.1. Bulk Distribution Substations:
4
Eversource requires ground fault (zero sequence) overvoltage (“3V0”) protective relaying package to be installed on the transformer high-voltage side to
detect the ground fault overvoltage when the upstream transformer connection is delta and the DER is about 50% of minimum load.
9
Eversource Energy Copyright © 2020 All rights reserved.
CL&P dba Eversource Energy
Docket No. 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-001, Attachment 1
Page 10 of 49
Within its service territory, Eversource supplies a range rural and urban areas which often differ in electric supply
characteristics and requirements. Electric distribution substations are scaled in size and redundancy as a proportion
of the mix between rural and urban areas. To maintain adequate levels of reserve capacity, power quality, and
reliability, that meet or exceed our Customer’s increased expectations, Bulk Distribution Substations shall be
designed to sustain any Single Contingency (N-1) with no Load Loss.
Transmission System Considerations:
Upholding the Bulk Distribution Substation N-1criteria starts at the transmission level, by observing the following:
• The transmission system supplying distribution bulk substations shall be designed so that the outcome of
any single contingency event at the transmission side does not result in a condition greater than a Single
Contingency (N-1) at the distribution bulk substation.
Distribution System Considerations:
Upholding the N-1 design standard also applies to the distribution system by observing the following:
• The distribution system shall be designed so that any feeder outage does not result in thermal or voltage
violation above design criteria, as defined Sections 2.2 and 2.4.
2.7.2. Distribution System Reliability
Distribution Feeder design is intended to provide safe, reliable service within allowed voltage limits at a reasonable
cost. Reliability generally addresses interruptions of service exceeding the targets specified by state regulators.
Eversource uses three reliability measures adopted by the utility industry: SAIDI, SAFI and CAIDI, refer to DSEM
02.11. There are limits as to what degree of reliability is practical or achievable, depending on the investment cost
and rates permitted by regulatory authorities. To evaluate the effectiveness of reliability projects and determine the
most cost-effective solution Eversource follows DSEM 03.30.
To maintain approved regulatory reliability indices, the following solutions can be implemented in areas of the
distribution system that required reliability improvement:
• Add automatic sectionalizing devices to limit exposure to 500 customers or less per switchable zone. Refer
to DSEM 02.30, DSEM 06.51, and DSEM 10.42.
• Eliminate or reconfigure triple circuit pole lines to minimize customer exposure for single emergency events
that result in more than 1000 customers out of service
• Reconfigure double circuit pole lines where both the normal and alternate source supply the same group of
customers resulting in more than 1000 customers out of service.
2.8. Standard Substation Design
While it may not be possible to design, build, and operate substation facilities that are completely resilient to any
event which could result in customer outages, there are economic designs and technologies that minimize the
occurrence and/or impact of substation-based events to improve reliability. At the distribution level, it is
Eversource’s goal to have customer’s electric service automatically restored upon loss of supply to Bulk Distribution
Supply Buses.
In areas of High Load Density, a higher degree of reliability is required by maintaining supply, without the loss of
power, to Bulk Distribution Buses following an N-1 Contingency Condition.
To accomplish this, certain technologies/designs are considered:
• Each distribution bus providing service to high load density areas shall have at least two means of supply
connected in a parallel. In this context, the preferred primary supply is provided by connection to the
secondary winding of a Bulk Distribution Transformer, and secondary supply is provided by connecting to
a normally closed bus tie breaker that connects to another bus supplied by the secondary winding of a
different Bulk Distribution Transformer.
• Each distribution bus providing service in low to medium load density areas, shall have at least two means
of supply (primary and secondary). In this context, the preferred primary supply is provided by connection
to the secondary winding of a Bulk Distribution Transformer.
o Secondary supply for distribution buses is provided by a connection to bus tie breakers (either
10
Eversource Energy Copyright © 2020 All rights reserved.
CL&P dba Eversource Energy
Docket No. 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-001, Attachment 1
Page 11 of 49
normally open or normally closed) that connects to another bus that is supplied by the secondary
winding of a different Bulk Distribution Transformer within the same substation.
For all Standard Substations, Automatic bus restoral schemes (ABR), on the transformer secondary side, are
designed/intended to restore supply to distribution buses after loss of supply due to transmission and/or substation
events that results in loss of the transformer that normally supplies that distribution bus. These schemes
automatically isolate the secondary breaker of the primary transformer supply to the bus and then close a normally
open tie breaker to another bus/transformer, restoring supply to the affected customers.
Secondary bus arrangement for Standard Bulk Substations shall consist of two or more standard size transformers
connected at the secondary side via a Ring Bus or Double Bus Switchgear configuration, refer to Figure below:
Figure 1 - Standard Substation Design
The preferred secondary bus arrangement design for new substations or substation upgrades shall be driven by the
expected load density, based on long-term forecast of the area to be supplied. Low to Medium Load-Density areas
shall be planned as Double Bus Switchgear configuration, and for areas with Medium to High Load-Density future
substations shall be planned as a Ring Bus Configuration. In both substations arrangements, the system shall be
design so that a bus fault does not result in loss load. In the Double Bus Switchgear this is accomplished by
transferring the load to the non-faulted bus, in a Ring Bus Configuration the distribution system is designed to
account for a bus fault.
Standard Bulk Distribution Substation shall be designed to meet the following criteria:
• Available short circuit currents shall not exceed the protection equipment’s interrupting capabilities, both
inside the substation and the distribution system:
• Short circuit currents that exceed protection equipment interrupting capability can result in equipment
damage, widespread outage events, and concerns in maintaining personnel and/or public safety near such
equipment. To minimize the risk, impact, and possibility of such events, simulations shall be conducted to
evaluate the maximum short circuit current in a substation against the protection equipment’s capability of
interrupting it.
• The System Protection and Control department is responsible for this determination.
• Bulk Distribution Substations shall be designed such that the limiting element is the Substation
Transformer(s).
• Capability to ensure Bulk Distribution Transformer winding loads can be maintained within the applicable
rating during both normal and post-contingency conditions as per Section 2.2.
• Sufficient VAR support to maintain scheduled bus voltage values during normal and post-contingency (N1) conditions.
• Capability and proper load balance between secondary buses to ensure:
o Secondary bus loading is not exceeded during normal and post-contingency (N-1) emergency
conditions.
o Substation equipment and getaway cable loading is not exceeded during normal and postcontingency (N-1) emergency conditions.
11
Eversource Energy Copyright © 2020 All rights reserved.
CL&P dba Eversource Energy
Docket No. 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-001, Attachment 1
Page 12 of 49
2.9. Substation Upgrade Criteria
Bulk Distribution Substation designs should be in accordance with the design criteria specified in the Section 2.8
When existing substation designs do not conform to these criteria or future potential non-conformances are
identified, as part of the Solution Development Process in Section 4.8, plans shall be developed to address identified
violations. This section outlines the process for prioritizing needed upgrades required to mitigate capacity, power
quality, and reliability violations.
To maximize the benefit of available funds and resources, the Eversource distribution bulk substations system
improvement objective is to prioritize upgrades addressing violations based on the following priorities, in order:
1 - Highest to lowest overloads under normal and contingency (N-1) conditions
2 - Load loss under first contingency (N-1) conditions
3 - Highest to lowest number of customers impacted during contingency conditions
4 - Associated risk evaluation of substation based on individual components (Asset Condition).
a - This Asset Condition criteria does not include equipment with asset conditions deemed a safety
hazard, those should be prioritized and resolved under emergency conditions.
This objective ensures that violations addressing distribution substation overloads, both bulk and non-bulk, are
prioritized due to the risk that equipment failure can pose to the public and employee safety. Moreover, violations
that impact the reliability of the electric service we provide to our customers is also prioritized by addressing
violations that result in a Single Contingency Load Loss. A reliable electric grid brings a host of benefits beyond
reduced outage time to those affected by power outages (e.g., by providing greater assurance to businesses and
emergency personnel that their activities will not be inconvenienced by electric outages). Lastly, by prioritizing
reliability driven replacement of substation transformer and/or equipment as a factor of the load density, the number
of customers affected by equipment failure is reduced (e.g., replacement of transformers that are over their useful
life and are supplying high load density areas shall be prioritized when compared to similar transformers supplying
low load density areas).
After the yearly distribution substation assessment process, Distribution System Planning shall identify all violations
per individual substations and rank them by state based on the priority given in Table below.
Priority
Number
1.
2.
3.
4.
5.
6.
7.
Violation
Type
Capacity
Capacity
Reliability
Reliability
Power Quality
Description
Bulk Distribution Substation Overloads
Non-Bulk Distribution Substation Overload
Single Contingency (N-1) load loss
Substations with higher risk of equipment failure, due to
asset condition or power quality violations, supplying
High Load Density Areas
Reliability
Substations with higher risk of equipment failure, due to
Power Quality
asset condition or power quality violations, supplying
Low Load Density Areas
Power Quality
Power quality Violations such as Harmonics, TOV, ROI
Reliability
Non-Standard Substation Design
Table 4 - System Violation Ranking
Single Contingency Load Loss (SCLL)
SCLL is identified as complete or partial interruption of load served by a Substation for a sustained period due to the
absence of automatic throw-over schemes on the transmission end or load swap schemes on the distribution end,
(e.g. load supplied from radially fed circuits with no ties.)
Eversource System Operating Procedure (ESOP-28) - Single Contingency Load Loss for the respective state.
supports the identification of events which result in customers being fed by a single transmission path, a loss of
which would lead to complete or partial interruption of load served by a Substation for greater than 90 minutes due
12
Eversource Energy Copyright © 2020 All rights reserved.
CL&P dba Eversource Energy
Docket No. 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-001, Attachment 1
Page 13 of 49
to the absence of automatic throw-over schemes on the transmission end or load swap schemes on the distribution
end. Eversource has an established process to identify, review, and notify stakeholders of these SCLL situation to
manage the risk of having these types of event occur. This process is specified in the ESOP-28 and applies to
Eversource CT, MA, and NH electric transmission and distribution organizations. The process ensures involvement
of stakeholders and management in reviewing, preparing for, and issuing any needed notification for outage work
that creates a SCLL condition. Completion of the SCLL process in advance of the scheduled outage ensures that
plans are in place to minimize risk exposure and mitigate customer load interruption.
Distribution System Planning should identify SCLL conditions due to substation transformer or switchgear outages
that result in exposures exceeding the conditions cited in ESOP-28. When developing preferred and alternate
solutions that will be implemented in the 5-year capital plan, as part of the solution development process in Section
4.8, Distribution System Planning will assess the severity of potential SCLL conditions and document these findings
as part of the Solution Selection Form (SSF). Where SCLL risks are deemed to be severe, such risks would be
considered in the design of the applicable solution.
For events that could potentially exceed the ESOP-28 criteria, the following information should be documented as
part of the preferred solution:
• The next event (transformer or switchgear outage) that will result in the greater number of customers out of
service.
• Identify transformer or switchgear equipment age and/or known asset conditions.
2.10.Feeder Upgrade
Feeder upgrades are required when one or more of the following design criteria is violated to ensure that any feeder
cable/wire will not exceed Normal or Emergency Ratings, as per Section 3.1.
Cables and Wires Supplying Underground and Overhead Areas:
System modifications shall be developed and proposed when conductor limits are expected to exceed the following:
•
80% of normal feeder rating for cables
•
90% of normal feeder rating or emergency for wires
Feeder Supplying Underground Network Systems
System modifications shall be developed and proposed when conductor limits are expected to exceed the following:
•
80% of normal feeder rating
Distribution Supply System (DSS) Lines
System modifications shall be developed and proposed when DSS Lines are expected to exceed the following:
•
80% of normal or emergency rating for cables
•
90% of normal or emergency rating for wires
2.11.Battery Energy Storage System Design Criteria
Eversource defines the deployment of energy storage as a distribution grid solution, and the process for
identifying scenarios where battery energy storage solutions would be most beneficial. Energy storage can
be classified as a Non-Wires Solution (NWS) option or as a standalone technology that can be deployed at
various scales.
Energy storage systems are uniquely capable of a variety of applications and uses. Like other NWS,
energy storage can be used to defer distribution system upgrades and provide peak shaving benefits. In addition, can
also provide demand charge reductions, and backup power in behind the meter applications.
Energy storage solutions can provide benefits to the distribution system in numerous ways, by providing multiple
functions at different times of the day:
Active Power Functionality
13
Eversource Energy Copyright © 2020 All rights reserved.
CL&P dba Eversource Energy
Docket No. 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-001, Attachment 1
Page 14 of 49
Peak shaving - may be used to reduce exceptionally high load flows that likely occur only a handful of times per
year and threaten to exceed thermal limits of lines or transformers either under all facilities in (N-0) or Contingency
outage (N-1) conditions, as well as address voltage issues that might be caused at feeder ends.
Load Flattening Peak Shaving - may refer to the regular dispatch of energy during relative (typically daily)
Substation of feeder load peaks. Operating the BESS in this way can:
Reduce the range of loading on a given feeder
Absorb energy during light-load periods
System Services – may be used to strategically dispatch the BESS to address (sub) transmission system needs
Provide energy and power when they are more valuable,
Limit ramp rates associated with the evening decrease of PV generation
provide frequency control services
Reactive Power Functionality
It could be beneficial year-round (management or peak shaving should still be set as priority) to regulate substation
power factor to help minimize losses as well as reduce the amount of reactive power to be sourced or absorbed by
transmission. With modern inverter technology, reactive power support can be provided even while active power
functionality is idling.
• BESS’s method of dispatching reactive power aid in system voltage regulation by absorbing or injecting
reactive power or idling as necessary.
• The ability of control voltage can help mitigate issues caused by the high penetration of DER, such as light
load voltage rise depending on the location of the storage asset.
• The ability of the BESS to control voltage can mitigate post-contingency high voltage issues on the
Transmission system that may be identified by ISO-NE.
• The ability of the BESS to control power factor may permit more improved compliance with ISO-NE
Operating Procedure #17(Annual Load Power survey)
Operational Responsibility
One of the chief potential values of energy storage is its ability to provide timely energy on demand to the grid. This
requires the eligibility of Eversource Energy to own and operate energy storage as a flexible source of power. It is
necessary to own and operate energy storage to provide distribution grid management services, such as discharging
the storage to offset peak load on a circuit or to manage voltage on a circuit. It is the responsibility of Eversource to
have the ability to control the energy storage under defined conditions or time periods—and that the energy storage
be available (i.e., sufficiently charged) to meet the grid performance need.
Processes for Identifying BESS Opportunities
Through analysis and assessments, specific distribution grid needs/constraints can be identified and be considered
and addressed by a BESS option. Distribution System planning can include a variety of analysis such as:
•
•
•
•
•
•
Forecasting of load growth analysis
o Seasonal peak loads at substation distribution transformers
o Spot loads
Distribution feeder loading analysis
Distribution system modeling and scenarios simulations
Reliability assessments
o Worst performing circuit analysis
Utilization of traditional reliability indices
Equipment/asset loading analysis
A traditional solution must be identified to be compared with the BESS option.
The BESS will be implemented if it meets the “least cost” solution for a grid need. If applied as a capacity deferral,
14
Eversource Energy Copyright © 2020 All rights reserved.
CL&P dba Eversource Energy
Docket No. 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-001, Attachment 1
Page 15 of 49
the transformer/line remaining life time expectancy must be greater than 10 years. A preliminary BESS gross
estimate can be calculated by using the latest version of the National Renewable Energy Laboratory (NREL) U.S.
Utility-Scale Photovoltaics-Plus-Energy Storage System Cost Benchmark. Refer to most recent table of US UtilityScale Lithium-ion Standalone Storage Cost for Durations of 0.5-4 hours. To the selected $/kWh value, the feeder
position installation cost (if applicable), must be added. To this total cost the ES Indirect Costs and the AFUDC
must also be applied. Contact the respective Cost Estimating Department to get these costs
Distribution Battery Energy Storage Suitability
Eversource owned Energy Storage can be used to meet System Planning Standards for normal and contingency
operations. When the BESS is applied inside or in the substation vicinity, consideration should be given to future
substations expansions. The BESS should not restrict expected long-term substation upgrades.
Eversource uses the following suitability criteria to identify
opportunities for storage Implementation:
Criteria
Potential Elements Addressed
Project Type Suitability
Project types include Capacity, Power Quality, and/or
Resiliency.
Storage is the least cost solution compared with
traditional option
BESS
2-3 years Lead Time for small projects
3-5 years Lead Time for large projects
Time-Horizon Suitability
Demand
Suitability
BESS Minimum Life
5-12 years
BESS Cycle Duration at
nameplate power
1-4 hours
Asset Condition (being relieved)
Remaining Life Expectancy
> 5-12 year
Large Project
3-20 MW
Small Project
1-2.5 MW
Table 5 - Opportunities for Storage Implementation Criteria
Note - For grid forming BESS applications short circuit ratio (short circuit of electric system at point of
interconnection divided by size of BESS) should be greater than 1 at the minimum, optimal design is greater than 2.
For grid following BESS applications short circuit ratio should be greater than 2, optimal design is greater than 3.
BESS size solutions for Eversource areas with Low/Medium DER saturation and/or low peak shaving:
2.5MW/10MWh and 3.5MW/14MWh.
BESS distribution applications will consider utility system benefits such as:
15
Eversource Energy Copyright © 2020 All rights reserved.
CL&P dba Eversource Energy
Docket No. 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-001, Attachment 1
Page 16 of 49
•
•
•
Avoided/Deferred distribution investments costs
o Deferred distribution investment costs will be considered on a net present value basis
Avoided energy and transmission costs
o Yearly Capacity Peaks Reduction (Forward Capacity Market (FCM) costs
o Monthly Regional and Local Network Services (RNS/LNS) Peak Reductions
Clean Peaks Standards Certificates (MA only)
MA Only - Constructability of the BESS solution compared to the avoided conventional T&D upgrade.
If the BESS requires a substation expansion with extension of the fence line (which is an intensification of use), the
BESS itself may trigger MDPU Chapter 40A review, whereas the conventional Substation upgrade (replacement of
transformers in-kind with Larger banks) may not. This may be a factor that makes the conventional upgrade
superior to the BESS implementation notwithstanding other apparent benefits.
Other components we need to consider for the Evaluation of a storage site vs. traditional upgrade.
• Aside from CapEx cost, BESS have significantly higher OpEx, so we should include expected maintenance
and upkeep for the BESS over the study horizon as a net present value stream
• BESS energy losses, not sure where we account for those, but a 10MWh system that cycles once a day with
an 80% roundtrip efficiency has a total annual energy consumption of 730 MWH. That needs to be paid for
an accounted somehow
• Decommission and recycling. If it’s not already baked into the upfront project contract that can be a major
cost factor.
Inverters Functions Applied to Eversource Options:
A three-phase inverter transforms the dc input into three-phase ac output. Inverters rely on their internal control logic
to achieve the targeted functions and to support the grid stability. Inverters equipped with advanced functionality can
provide grid support services such as frequency/voltage regulation (Volt-var, Volt-watt, Fixed power factor (wattvar), hertz-watt, etc.)
Reactive power applications including Volt/VAR, independent reactive power (Q) dispatched output, and PF control
• The goal is to use inverters as a resource in distribution circuit voltage profile management, power quality,
and power factor management
• Both autonomous and centrally controlled applications are of interest
• Implementations may include an inverter Q response to a local and/or remote measurement
• With modern inverters and dependent on the control option, Q response is not limited to times of active
power activity.
Islanding
•
•
•
•
The goal is to provide enhanced resiliency to customers by providing a back-up power supply during a loss
of the normal electrical service
Near-term anticipated islanding use cases have the following characteristics:
o The ESS will island a 3-phase portion of a distribution circuit
o Phase imbalance may be significant
o The ESS inverter is required to provide grid-forming functions including voltage and frequency
regulation
o The island will not include other sources of generation, load control, or a central microgrid
controller
o The ESS will coordinate with circuit management devices such as reclosers and with a distribution
control center
o May be implemented as seamless transfer, or may require picking up cold load
Future islanding applications, in addition to the above, have the following characteristics:
o Require coordination with central microgrid controller
o Require coordination with diverse other resources including solar, cogeneration facilities, diesel
generators, flexible load
o May involve significant phase imbalance of load and other generation resources
Frequency response
o The goal is to explore ability of inverters to participate in autonomous frequency response
16
Eversource Energy Copyright © 2020 All rights reserved.
CL&P dba Eversource Energy
Docket No. 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-001, Attachment 1
Page 17 of 49
•
Inverter should have an autonomous response to locally measured frequency Phase Balancing operation
o 3 phase inverters are typically set up as three single phase inverters with a joint DC bank allowing
theoretical, and practical control of each phase individually.
o Charging and discharging of active power to balance phases
o Generation or consumption of reactive power to balance power factor and support individual phase
voltages
•
Eversource-owned utility scale BESS can also:
• Participate in ISO-NE System Blackstart
• Participate in other ISO-NE markets such as frequency regulation.
Distribution System Potential Benefits from the BESS/Smart Inverter
•
•
•
•
•
•
•
•
•
•
•
Capacity Deferral—Storage can help delay a capacity investment to reduce expected present value costs or
gather additional information and preserve options regarding the timing, nature, and scale of the required
investment.
Backup Supply—Storage can enable a Customer or group of Customers to maintain some or all electric
service when power is not available from the grid.
Remote Loads—Storage can be deployed in locations where significant investment would be required to
provide service to the Customer and/or meet reliability requirements. This may include support for various
remote EV charging scenarios (e.g., fast charging, fleet charging, transit charging) to smooth spikes in
demand.
Buffering—Storage can continuously and automatically offset and smooth changes in real power demand
and supply from other DERs.
CVO—Storage can assist in actively controlling distribution voltage, in most circumstances, to achieve
energy and demand savings/reductions.
Island—In an Island mode, zones, or circuits are capable of operating autonomously or collaboratively to
optimize their operation based on system conditions. Storage can help balance demand and supply in a
specific zone/circuit when disconnected from other portions of the grid system.
Power Quality—Storage can help maintain the wave form in an alternating current (AC) power system that
is necessary to ensure reliable and efficient operation of the grid and Customer equipment.
Congestion Relief—Storage can help mitigate distribution congestion and enable more efficient power
transfer by increasing demand upstream of a constraint or by supplying energy downstream of a constraint.
Ramping—Storage can help address rapid changes in supply and/or demand over various time periods, from
several dispatch intervals to several hours.
System Efficiency—Storage can make load factor improvements by shifting demand from peak to off-peak
periods.
Topology Optimization—Storage can provide power or reserves such that the system can be reconfigured
while continuing to meet reliability requirements.
System
Capacity
Grid/Ancillary Services
Reliability
Distribution System
Capacity Deferral
Backup Supply
Remote Loads
Buffering
CVO
Congestion Relief
Topology Optimization
Backup Supply
Power Quality
System Efficiency
Island
Bulk System
Capacity Deferral
Buffering
Congestion Relief
Backup Supply
Power Quality
System Efficiency
Ramping
17
Eversource Energy Copyright © 2020 All rights reserved.
CL&P dba Eversource Energy
Docket No. 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-001, Attachment 1
Page 18 of 49
2.12.Network Criteria
Downton areas of large cities are characterized by high power demands and increased customer density.
Additionally, since most of the financial and commercial businesses are typically located in downtown areas, there
are often strict requirements for uninterruptable power supply and power quality.
Full Secondary Network load areas, which are typically High Load Density, are defined as those in which both the
low voltage secondary grid and customer spot networks installations are supplied by distribution underground
network feeders that are connected to network bulk distribution substations. By this definition, both the supply
feeders and the substations are designed and operated to meet the Reliability Requirements of the Secondary
Network System.
Partial Secondary Network load areas are defined as those in which the low voltage secondary grid and individual
customers spot networks installations are supplied by a combination of underground and overhead network feeders,
but both the feeders and/or the substations are not designed to meet the reliability requirements of the Secondary
Network System. Low and Medium load density areas are typically supplied via Partial Secondary Network systems.
Full Secondary Network System Reliability Requirements:
The objective of a secondary network is to interconnect feeders and transformers to form a consistent and welldiversified intermesh through the impedance of the low-voltage grid of mains and transformers. Feeders are
connected to network transformers whose low voltage cables connect to a low-voltage secondary grid via network
protector devices. The Eversource Full Secondary Network Systems is designed for N-1 Contingency Criteria at the
substation level. The system is designed so that the loss of one distribution feeder does not result in customer
interruptions, unsatisfactory customer voltages, or secondary cable overloads.
To maintain this level of reliability, the following design practices are implemented in Secondary Network load
areas:
• At the secondary low voltage grid level, it is necessary to install a diversified intermesh with proper
number, size, and capacity of transformers and secondary mains. This ensures that secondary equipment
load levels remain under the required normal and emergency threshold for any combination of N-1
contingency.
• At the feeder level, it is necessary to use proper diversity when supply network transformers so that a single
contingency N-1 event or transformer outage will have the minimum impact on secondary mains and
nearby transformer loading.
• At the network level, to maintain proper feeder diversity only a certain number and combination of feeders
are installed in the same conduit system and allowed to supply the same local areas or spot network
installations. This prevents a single manhole or conduit section failure to result in secondary main
overloads, transformer overloads, and/or customer outages.
• At the substation level, to maintain proper bus diversity feeder bus arrangement in network stations should
be designed so that a bus section outage will have minimum impact on feeder loading. When designing or
arranging distribution network feeders, it is recommended to connect unrelated feeders to each bus sections.
This ensures that feeders supplying the same local areas a supplied from different bus sections.
Network Substation Supplying Full Secondary Network Load Areas:
Distribution Bulk Substation supplying network areas shall be designed so that each distribution bus has a minimum
of two means of supply that are always connected in a parallel. In this context, the primary supply is provided by
connection to the secondary winding of a bulk distribution transformer, and secondary supply is provided by
connecting to a normally closed bus tie breaker that connects to another bus supplied by the secondary winding of a
different Bulk Distribution Transformer.
For a Standard Substation Ring Bus configuration, each distribution bus has three means of supply that are always
connected in parallel. The primary supply is provided by connection to the secondary winding of a bulk distribution
18
Eversource Energy Copyright © 2020 All rights reserved.
CL&P dba Eversource Energy
Docket No. 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-001, Attachment 1
Page 19 of 49
transformer, and secondary supply is provided by connecting to normally closed bus tie breaker that connects to
another bus supplied by the secondary winding of a different bulk distribution transformer.
Substations supplying Full Secondary Networks are operate with all tra
Text of RSR-002.pdf
Extracted from the file · 4,476 characters
CL&P dba Eversource Energy
Docket 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-002
Page 1 of 2
Date Filed: March 31, 2026
Witness:
Soderman, Angela M, Freeman, Lavelle A
Request from: Public Utilities Regulatory Authority
Question:
Describe the methodologies the Company uses to analyze remainder-of-life and asset health for
station transformers (e.g., dissolved gas analysis). Provide any documents describing Eversource’s
internal methodologies, standards and procedures for testing and evaluating transformer asset
health, disseminating test results to the Company’s planning staff, and triggering an infrastructure
replacement project.
Response:
Eversource evaluates the remainder-of-life and overall health of station transformers through a
condition-based asset management approach that integrates diagnostic testing, inspection results,
operational experience, engineering evaluation, and system planning considerations. Transformer
replacement decisions are not driven by age alone and are not based on any single test or metric.
Asset age is considered as one contextual factor within a broader assessment of condition,
performance, and system risk.
Station transformers are designed with an expected service life of approximately 40 years;
however, actual longevity varies depending on loading history, maintenance practices,
environmental conditions, and operating stresses. As a result, Eversource emphasizes observed
condition and performance trends, with age used to help inform relative risk and prioritization
rather than to establish prescriptive replacement timing.
Transformer condition is monitored throughout the asset’s service life through routine inspections,
maintenance activities, and diagnostic testing. Information from these activities is reviewed
collectively to identify degrading conditions, adverse trends, or potential reliability concerns that
may warrant further engineering evaluation.
A primary diagnostic method used is dissolved gas analysis (DGA) and oil quality testing. Oil
samples are periodically obtained from substation transformers, including main tanks and load tap
changers, and are analyzed in accordance with applicable ASTM and IEC standards. Results are
evaluated and trended over time to identify indicators of abnormal thermal, electrical, mechanical,
or oil-related conditions. Engineering personnel review these results and determine appropriate
actions, which may include maintenance activities, enhanced monitoring, or additional technical
evaluation.
CL&P dba Eversource Energy
Docket 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-002
Page 2 of 2
Eversource utilizes industry-supported analytical tools, including the Electric Power Research
Institute (EPRI) Power Transformer Expert System (PTX), to support consistent transformer
condition assessment across the fleet. PTX considers multiple factors when developing qualitative
health indices, including; normal degradation, abnormal thermal conditions, abnormal electrical
conditions, abnormal core conditions, oil quality, and age.
These factors are evaluated collectively to provide insight into overall asset condition and relative
risk. PTX outputs are used as decision-support information and do not serve as automatic
replacement criteria. Engineering judgment and operational experience remain central to
evaluating results and identifying appropriate actions.
When assessments indicate declining condition or increased risk, transformers may be identified
for additional consideration. Potential refurbishment or replacement actions are informed through
coordination among Asset Management, System Planning, Substation Engineering, Substation
Technical Engineering, and Substation Operations, using the available condition information,
operational knowledge, and planning input to determine appropriate next steps.
In parallel, System Planning evaluates station transformers relative to current and forecasted
system capacity needs. Where projected system needs exceed existing capability, planning
considerations are evaluated alongside transformer condition, age, and operational risk to identify
suitable solutions.
Through this integrated process—combining condition monitoring, diagnostic testing, qualitative
health indicators, age as a supplemental factor, engineering judgment, and planning coordination—
Eversource manages the health of its station transformer fleet while avoiding prescriptive,
age-based replacement practices.
Text of RSR-003.pdf
Extracted from the file · 1,871 characters
CL&P dba Eversource Energy
Docket 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-003
Page 1 of 1
Date Filed: March 31, 2026
Witness:
Freeman, Lavelle A
Request from: Public Utilities Regulatory Authority
Question:
Att. 5, System Data Requirement No. 9 (Confidential). For each substation identified by
Eversource as having load within 90-100% of the normal rating or exceeding the normal rating,
provide the following information:
a. A description of any planned or in-progress capital projects at these substations and the
status of these projects;
b. The Firm Capacity of the substation;
c. The Load Carrying Capacity (LCC) of the substation;
d. The Distribution System Switching Capacity of the substation;
e. The date on which Eversource first identified the grid need;
f. A copy of the initial funding request forms;
g. If available, a copy of the solution selection forms;
h. If available, a copy of the project authorization forms.
Response:
RSR-003 Attachment 1 CONFIDENTIAL includes a table identifying substations operating at
90–100% of their Load Carrying Capability (LCC) and provides all requested data items (a
through h). Please note that the loading percentage categories referenced in “System Data
Requirement No. 9 (Confidential)” are based on each substation’s LCC, rather than its normal
rating, as described in the response to PMEV-017 in Docket No. 25-08-08, Non-Wires Solutions
Process Cycle 1.
For substations with initiated capacity projects supported by approved documentation, the
corresponding files have been included and are referenced within the summary table.
In accordance with Exhibit A of the Final Decision in Docket No. 24-08-08, Non-Wires Solutions
Process Initiation Phase, this response containing details regarding System Data Requirement No.
9 (Confidential) is provided confidentially as approved by PURA in that decision.
Text of RSR-004.pdf
Extracted from the file · 836 characters
CL&P dba Eversource Energy
Docket 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-004
Page 1 of 1
Date Filed: March 31, 2026
Witness:
GLADEY, DAVID L
Request from: Public Utilities Regulatory Authority
Question:
Att. 16, pp. 3-5. Provide the following information for Project CD02440:
a.
b.
c.
d.
The date on which Eversource first identified the grid need;
A copy of the initial funding request form;
A copy of the solution selection form; and
A copy of the project authorization form.
Response:
A. The initial funding request was created on March 13, 2024.
B. See Q-RSR-004 Attachment 1 for a copy of the initial funding request form.
C. See Q-RSR-004 Attachment 2, Section 4 “Alternatives Considered” for information related
to the solution selection.
D. See Q-RSR-004 Attachment 2 for a copy of the project authorization form.
Text of RSR-005.pdf
Extracted from the file · 555 characters
CL&P dba Eversource Energy
Docket 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-005
Page 1 of 1
Date Filed: March 31, 2026
Witness:
GLADEY, DAVID L
Request from: Public Utilities Regulatory Authority
Question:
Att. 16, pp. 3-5. Provide a map of the 14R31 Right-of-Way (ROW) and circuit which labels each
substation and feeder. Highlight in the map the circuit segments which the company plans to
rebuild.
Response:
Please refer to RSR-005, Attachment 1 which contains a map of the labeled 14R31 ROW and
circuit with the project segments highlighted.
Text of RSR-005, Attachment 1.pdf
Extracted from the file · 695 characters
CL&P dba Eversource Energy
Docket No. 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-005, Attachment 1
Page 1 of 1
Project Stop
Interrogatory 26-08-08 14R31 Map
Project CD02440
WEST_GOSHEN
33M
7-15-2024 Overload Event
9-12-2013 Overload Event
9-12-2013 Overload Event
Bulk Substation
Distribution Substation
Primary Overhead Conductor
NORTH_LITCHFIELD
42J
7-15-2024
Overload
Event
Circuit 14R31
CORNWALL
37J
SHARON
CORNWALL
WINCHESTER
BARKHAMSTED
GOSHEN
WEST_GOSHEN
33M
TORRINGTON
Project Stop
NORTH_LITCHFIELD
42J
NEW
HARTFORD
HARWINTON
LITCHFIELD
Project Start
KENT
CAMPVILLE
14R
WARREN
Project Start
MORRIS
WASHINGTON
THOMASTON
14R31 ROW
Project Start & Stop Points
Text of RSR-006.pdf
Extracted from the file · 761 characters
CL&P dba Eversource Energy
Docket 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-006
Page 1 of 1
Date Filed: March 31, 2026
Witness:
GLADEY, DAVID L
Request from: Public Utilities Regulatory Authority
Question:
Att. 16, pp. 3-5. Provide the number of customers served by the 14R31 circuit and any connected
feeders broken out by customer class (commercial, industrial, residential).
Response:
The table below provides the number of customers served by the 14R31 circuit by customer class
and includes the number of customers served by any connected feeders, by customer class.
Circuit
14R31
33M1
33M2
37J1
42J1
Grand Total
Residential
0
695
275
900
1027
2897
Customer Type
Commercial Industrial Total
2
0
2
42
0
737
2
0
277
85
0
985
105
0
1132
236
0
3133
Text of RSR-007.pdf
Extracted from the file · 3,321 characters
CL&P dba Eversource Energy
Docket 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-007
Page 1 of 2
Date Filed: March 31, 2026
Witness:
GLADEY, DAVID L
Request from: Public Utilities Regulatory Authority
Question:
Att. 16, pp. 3-5. For the three instances where the Company’s conductor was ‘burnt down’:
a. Describe the N-1 event that triggered the switching (i.e. what component of the distribution
system failed). If possible indicate the location of the failure on the map referenced in RSR5;
b. Provide the dates and times of the failures and subsequent overloads;
c. Provide the loading conditions on each feeder before and after the failure (i.e, for each
feeder, the load on the feeder and the ratio of that load to the feeder’s peak load);
d. Provide the duration of the overload conditions which necessitated switching;
e. Explain why the Company did not reconductor the ROW with higher capacity conductors
after the first time the conductor was burnt down.
Response:
There were two events that caused conductor failure due to overload within the 14R31 right of
way (“ROW”).
A. The location of failure for Line 14R31 was a primary insulator that melted resulting in a
pole fire. This insulator failure coincides with an increase in loads on the Campville 14R31
and 14R32 lines from the Bulls Bridge Substation 11M. The Bulls Bridge Substation was
de-loaded on September 12th, 2013 to facilitate the installation of a mobile transformer
position.
The event which occurred on July 15, 2024 was due to a tree that fell on a double circuit
pole line containing both the 11M3 and 11M62 circuits. Following the tree event, the fault
locations were isolated for both 11M3 and 11M62 circuits and customers were restored via
the 14R31 circuit. The conductor failure on 14R31 resulted after the increase in load from
customer restoration. See attachment (CD02440 – 14R31 Project Map) in RSR-5 for the
location of the conductor failure.
CL&P dba Eversource Energy
Docket 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-007
Page 2 of 2
B. The first event occurred on September 12, 2013 at 12:30 and the second event occurred on
July 15, 2024 at 19:42.
C.
14R31 Load Conditions
Load prior to receiving additional load (amps)
Load prior to conductor failure (amps)
Summer peak load (amps)
Ratio of load prior to failure versus summer peak
load
9/12/2013 7/15/2024
90
127
342
312
161
155
212%
201%
D. The duration of the condition for the September 12, 2013 event was 7 hours in which 3 of
the 7 hours created an overload condition.
The duration of the condition for the July 15, 2024 event was 52 minutes in which the
conductor failed due to overload 7 minutes after the switching occurred.
E. The overload event from September 12, 2013 was to facilitate the installation of a mobile
position at Bulls Bridge 11M which required the entire substation to be de-energized.
Going forward, with the mobile position installed, the load supplied from Bulls Bridge
11M would be transferred to the mobile transformer via the newly installed mobile position
as opposed to transferring the load to the Campville 14R feeders. Therefore, this overload
condition would not occur on the 14R31 as a result of the substation being de-energized
and there was no longer a need at that time to reconductor the 14R31 overhead conductor.
Text of RSR-008.pdf
Extracted from the file · 1,765 characters
CL&P dba Eversource Energy
Docket 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-008
Page 1 of 2
Date Filed: March 31, 2026
Witness:
GLADEY, DAVID L
Request from: Public Utilities Regulatory Authority
Question:
Att. 16, pp. 3-5. For each of the eight reliability related outages on the 14R31 ROW in the last
fifteen years, provide the following information:
a. The number of customers that experienced an outage broken out by customer class
(residential, commercial, industrial);
b. The total number of outage minutes broken out by customer class;
c. An estimate of the lost load broken out by customer class.
Response:
a.
Event
Number
Date
1443420 7/22/2010
1823854 10/29/2011
2312364 9/12/2013
3811036 11/22/2018
4327552 8/29/2020
4559922
7/7/2021
5018299 3/14/2023
5453436 7/15/2024
Total
Residential Commercial Industrial Customers
Affected
615
N/A*
2,205
2,831
1,200
1,008
432
2,913
179
N/A*
165
234
125
104
7
234
0
0
0
0
0
0
0
0
794
3,279
2,370
3,065
1,325
1,112
439
3,147
* Customer type distinctions are not available in for the 10/29/2011, winter storm Alfred event.
CL&P dba Eversource Energy
Docket 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-008
Page 2 of 2
b.
Event
Number
Date
1443420 7/22/2010
1823854 10/29/2011
2312364 9/12/2013
3811036 11/22/2018
4327552 8/29/2020
4559922
7/7/2021
5018299 3/14/2023
5453436 7/15/2024
Residential Commercial Total Cust
Cust Mins Cust Mins
Mins
44,310
N/A*
559,998
127,006
4,864
79,632
177,120
115,862
12,880
57,190
N/A* 11,696,193
40,874
600,872
9,662
136,668
1,007
5,871
8,216
87,848
2,870
179,990
9,174
125,036
* Customer type distinctions are not available in for the 10/29/2011, winter storm Alfred event.
c. The estimated load lost by customer class is not available at this level.
Text of RSR-009.pdf
Extracted from the file · 580 characters
CL&P dba Eversource Energy
Docket 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-009
Page 1 of 1
Date Filed: March 31, 2026
Witness:
GLADEY, DAVID L
Request from: Public Utilities Regulatory Authority
Question:
Att. 16, pp. 3-5. Confirm that the Company analyzed the alternative battery storage solution
assuming it would only reduce the load on the circuit during peak load conditions, not provide
outage support to customers.
Response:
The alternative battery solution was analyzed to mitigate the contingent overload on the 14R31
while supporting the 11M62 and 11M3 loads.
Text of RSR-010.pdf
Extracted from the file · 2,465 characters
CL&P dba Eversource Energy
Docket 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-010
Page 1 of 2
Date Filed: March 31, 2026
Witness:
GLADEY, DAVID L
Request from: Public Utilities Regulatory Authority
Question:
Att. 16, pp. 3-5. Justify the Company’s 22.5 MWh sizing of the battery storage solution to the
Campville14R31 ROW grid need by providing:
a. A narrative description of how the Company arrived at the value of 22.5 MWh as the
minimum required size of the battery storage solution;
b. The peak load profiles demonstrating that a minimum of 6.25 MVA for four hours is
required to eliminate overload conditions;
c. An explanation of why the Company assumed a 10-year growth rate of 1.43% and any
historical data and forecast information to support this assumption.
Response:
The Campville 14R31 ROW project has been updated to reflect the completion of CD02350
which was placed in service in 2025. The project revisions reflect a reduction in the overload
magnitude on the 14R31 circuit and include updated 2025 summer peak load data within the
project load sheet. The overall scope of the project has not changed, the NWS battery size has
been reduced in Option 5 from 22.5 MWh to 7.5 MWh. In order to evaluate all the options
equally, aging infrastructure replacements in the ROW were included within the NWS option
as the overall scope of the project addresses both overload and aging infrastructure.
a. The minimum required battery capacity was determined by forecasting the identified
contingency overload over a ten-year planning period, resulting in a projected overload of
1.5 MVA. This capacity was then multiplied by a five-hour outage duration of overload,
yielding an estimated battery energy storage requirement of approximately 7.5 MWh.
b. The peak load profile demonstrates that a minimum of 1.5 MVA for five hours is required
to eliminate overload conditions. The 1.5 MVA is based on 1.3 MW, a 90% power factor
and anticipated 10-year load growth.
14R31-61R Load profile (Amps at 27.6 kV) while supporting the 11M62 and 11M3 load
CL&P dba Eversource Energy
Docket 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-010
Page 2 of 2
c. The Company forecasts that load on the Campville 14R Substation will grow by
approximately 0.43% annually over the ten-year planning period. This forecast is derived
from a ten-year compound annual growth rate (CAGR) analysis specific to the Campville
14R Substation.
CAGR Analysis for Campville 14R
Text of RSR-011.pdf
Extracted from the file · 2,320 characters
CL&P dba Eversource Energy
Docket 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-011
Page 1 of 2
Date Filed: March 31, 2026
Witness:
GLADEY, DAVID L, Freeman, Lavelle A
Request from: Public Utilities Regulatory Authority
Question:
Att. 16, pp. 3-5. Regarding the Company’s estimate of $2 million per MWh of energy storage
system capacity:
a. Provide a copy of the Request for Proposal (RFP) the Company issued to obtain the
referenced contractor bids;
b. Describe how the Company advertised the RFP for the energy storage system including
where the RFP was posted and the duration of the solicitation process;
c. Provide a copy of the proposals received by the Company from the bidding vendors (i.e.,
a copy of the vendor bids);
d. Provide the itemized cost breakdowns provided by the bidding vendors.
Response:
The Company rounded these estimates to $2 million per MWh for estimation purposes.
a. RSR-011 Attachment 1 CONFIDENTIAL contains the technical/commercial documents
submitted to the supplier participants in this Request For Information (RFI), to obtain
indicative non-binding pricing and not intended to result in a contract award. The file
structure is as follows:
CT BESS RFI to Suppliers
- Appendix A-DD
o One lines and sketch of proposed layout
- Appendix A-DS
o Conduit and Trench Engineering/Construction Standards
o Equipment & Material Engineering/Construction Standards
o Grounding & Bonding Engineering/Construction Standards
o Precast Foundations Engineering/Construction Standards
o Switching & Tagging Engineering/Construction Standards
o Testing Engineering/Construction Standards
o Misc Design Data/ Engineering/Construction Standards
o Siting and Development Engineering/Construction Standards
- Instructions to Bidders
- Schedule of Values (Pricing Form)
CL&P dba Eversource Energy
Docket 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-011
Page 2 of 2
-
RFI/Question Log
Technical Specification
b. The RFI was issued through Eversource’s sourcing tool, Ariba and was posted from
3/12/24 to 4/4/24.
c. Summaries of the Supplier responses for Frybrook (RSR-011 Attachment 2
CONFIDENTIAL) and Campville (RSR-011 Attachment 3 CONFIDENTIAL) are
included with this response.
d. See the attachments referenced in Part c. for the itemized cost breakdown provided by the
bidding vendors.
Text of RSR-012.pdf
Extracted from the file · 2,550 characters
CL&P dba Eversource Energy
Docket 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-012
Page 1 of 2
Date Filed: March 31, 2026
Witness:
Soderman, Angela M
Request from: Public Utilities Regulatory Authority
Question:
Att. 17. Provide the following for Project CS00606:
a. Explain why the Company is replacing the existing transformer at the substation;
b. Describe whether the transformer the Company is replacing has fully depreciated;
c. Provide the age of the transformer and the results of any internal assessment the Company
has undertaken to evaluate the health and remainder-of-life of the transformer;
d. Identify the date on which the Company first identified the grid need;
e. Provide a copy of the initial funding request form;
f. Provide a copy of the solution selection form; and
g. Provide a copy of the project authorization form.
Response:
a. The company is replacing the transformer because the Glenbrook 1K-2X transformer was
installed in 1964 (62 years old) and has surpassed the 40-year timeframe customarily
regarded as the useful life of a transformer and the health index indicates it is near its endof-life.
In addition to solving asset condition issues at Glenbrook 1K, replacing the 46.7MVA 1K2X transformer with a new Eversource standard 62.5MVA transformer will increase the
substation capacity and better allow Glenbrook 1K to meet the increased load demands
which are forecasted to exceed 100% of its Load Carrying Capacity (LCC) by the summer
of 2026.
b. Yes, the Glenbrook 1K-2X transformer is over 40 yrs old and is fully depreciated.
c. The transformer is currently 62 years old. Additionally, per the Electric Power Research
Institute (EPRI) Power Transformer Expert (PTX) tool the health index indicates it’s near
its end-of-life based on this equipment’s short and long-term health indices of 0.29 and
0.60, respectively, as of April 2025. The health index is measured in the range of 0 to 1,
with 0 meaning healthy and 1 needing immediate replacement. A value greater than .5 is
considered poor health. The long-term health index, as well as its age surpassing the 40-
CL&P dba Eversource Energy
Docket 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-012
Page 2 of 2
year timeframe customarily regarded as a transformer’s useful life, dictates the need for
replacement.
d. This need to replace the Glenbrook 1K-2X was approved with an initial funding request on
08/24/22.
e. Reference RSR-012, Attachment 1
f. Reference RSR-012, Attachment 2a and RSR-012, Attachment 2b
g. Reference RSR-012, Attachment 3
Text of RSR-013.pdf
Extracted from the file · 3,121 characters
CL&P dba Eversource Energy
Docket 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-013
Page 1 of 2
Date Filed: March 31, 2026
Witness:
Soderman, Angela M
Request from: Public Utilities Regulatory Authority
Question:
Att. 17. Provide the following for Project CS00503:
a.
Explain why the Company is replacing the existing transformers at the substation;
b.
Describe whether the transformers the Company is replacing have fully depreciated;
c.
Provide the age of the transformers and the results of any internal assessment the Company
has undertaken to evaluate the health and remainder-of-life of the transformers;
d.
Identify the date on which the Company first identified the grid need;
e.
Provide a copy of the initial funding request form;
f.
Provide a copy of the solution selection form; and
g.
Provide a copy of the project authorization form.
Response:
a.
This project is not replacing a transformer, but it is replacing the 13.8kV switchgear with
associated circuit breakers (CBs), protection relays, conduits, cabling, and foundations.
The 13.8kV switchgear was installed in the mid-1970s. In the past years, the foundation has begun
to sink unevenly, causing the switchgear to come out of alignment cand causes difficulty when
racking circuit breakers in and of the cubicles. Correcting the alignment issues requires outages
and partial disassembly of the switchgear to realign it. The foundation continues to settle, and
realignment is becoming regularly required. Substation Engineering, System Planning, and Asset
Management have determined the need to replace the 13.8kV switchgear and associated equipment
at East Meriden 21P SS to improve customer and system reliability due to asset conditions and
obsolescence of the existing switchgear.
The Transformers 21P-1X and 21P-2X are not being replaced but have been identified for LTC
receiver upgrades. The existing radio-controlled Transformer LTC Voltage Reduction System
with new DSCADA controlled LTC Voltage Reduction Systems that have the capability to
remotely reduce the system voltage by 5% during contingencies to help stabilize the system and
provide LTC control to System Operations Control (SOC). Existing tap changer controllers/radio
receivers will be replaced with new Beckwith 2001D tap changer controllers. This project will
incorporate those upgrades and connect the LTC controls to the DSCADA system in the new
switchgear.
Performing this work when the switchgear is replaced will allow for cost savings by performing
engineering and outages for both scopes of work concurrently.
CL&P dba Eversource Energy
Docket 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-013
Page 2 of 2
b.
Yes, the switchgear is over 40 yrs old and is fully depreciated.
c.
The switchgear is from the mid – 1970s and is at least 46 years.
d.
This East Meriden 21P Switchgear Replacement was approved with an intital funding
request on 07/22/2021.
e.
Reference RSR-013, Attachment 1 Confidential CEII
f.
Reference RSR-013 Attachment 2a Confidential CEII and RSR-013, Attachment 2b
Confidential CEII
g.
Reference RSR-013, Attachment 3 Confidential CEII
Text of RSR-014.pdf
Extracted from the file · 2,000 characters
CL&P dba Eversource Energy
Docket 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-014
Page 1 of 2
Date Filed: March 31, 2026
Witness:
GLADEY, DAVID L
Request from: Public Utilities Regulatory Authority
Question:
Att. 15. Provide the following for Projects CD02654 and CD02618:
a. Provide the margin of contingent overload and the number of hours during the year that
this overload is forecasted to occur under a 90/10 planning scenario; and
b. Provide the number of customers in each class served by the relevant feeder
Response:
CD02654
a. Option 2 – NWS: The 9 MWh battery size was estimated based on the 1.5 MVA needed
to bring the load on the 11Y2 overloaded conductors below 100% rating during
contingency with the 11Y8-71S zone. This reduction would be required during the 6hour peak load period of 2PM and 8PM for this area. This comes at a cost of $18M for
the 9 MWh battery. NWS estimates were calculated at $2M per MWh based on the two
lowest of three contractor bids received in Connecticut. The 90/10 planning scenario
is not done at the circuit level; it is done only at the substation level.
b. 11Y2: 2,969 customers
• 2,681 Residential
• 281 Commercial
• 7 Industrial
CD02618
c. Option 3 offers a Non-Wires Solution by installing a 12.38 MWh battery. The battery
needs to support 76A (3.03 MW) of load to lower the 120% contingency to 100% at
the 15L69-80M. The expected duration of the battery is 4 hours. The expected growth
rate is 2.2% over a ten-year period. NWS estimate was calculated at $2M per MWh
based on the two lowest of three contractor bids received in Connecticut. This results
in a total cost of $24.75M. The 90/10 planning scenario is not done at the circuit level;
it is done only at the substation level.
a. 15L69: 2,315 customers
• 2,139 Residential
• 171 Commercial
• 5 Industrial
CL&P dba Eversource Energy
Docket 26-08-08
Set Pura-01
Date Issued March 10, 2026
RSR-014
Page 2 of 2
11C14: 3,073 customers
• 2,919 Residential
• 146 Commercial
• 8 Industrial