Docket 07-02-11RE02ClosedJanuary 3, 2018
Application of Sugar River Power, LLC for Qualification of Lower Village Hydro as a Class I Renewable Energy Source
- Status
- Closed January 3, 2018
- First filing
- January 3, 2018
- Latest filing
- October 13, 2026
- Filings
- 38
- Documents
- On the current system (documents are copied for 2024 and later dockets)
This docket's record on the current system (opens in a new tab)
Decisions and notices
What the Authority has issued in this docket, newest first.
- January 3, 2018Decision Final Decision
Filings
38 filings.
October 2026
Compliance Filing, Order No. OneOctober 13, 2026 · William P. Short IiiJuly 2026
Compliance Filing, Order No. OneJuly 12, 2026 · William P. Short IiiFirst quarter 2026 production report for the Lower Village Hydro hydro-electric dam
May 2026
Compliance Filing, Order No. 1May 9, 2026 · William P. Short IiiFourth quarter 2025 production report for the Lower Village Hydro hydro-electric dam
- Compliance Filing, Order No. 1May 9, 2026 · William P. Short Iii
Fourth quarter 2025 production report for the Lower Village Hydro hydro-electric dam
February 2026
Compliance Filing, Order No. OneFebruary 8, 2026 · William P. Short IiiThird quarter 2025 production report for the Lower Village Hydro hydro-electric dam
October 2025
Compliance Filing, Order No. OneOctober 5, 2025 · William P. Short IiiSecond quarter 2025 production report for the Lower Village Hydro hydro-electric dam
August 2025
Compliance Filing, Order No. OneAugust 1, 2025 · William P. Short IiiFirst quarter 2025 production report for the Lower Village Hydro hydro-electric dam
April 2025
Compliance Filing, Order No. OneApril 9, 2025 · William P. Short IiiFourth quarter 2024 production report for the Lower Village Hydro hydro-electric dam
February 2025
Compliance Filing, Order No. OneFebruary 2, 2025 · William P. Short IiiThird quarter 2024 production report for the Lower Village Hydro hydro-electric dam
October 2024
Compliance Filing, Order No. OneOctober 7, 2024 · William P. Short IiiSecond quarter 2024 production report for the Lower Village Hydro hydro-electric dam
July 2024
Compliance Filing, Order No. OneJuly 5, 2024 · William P. Short IiiFirst quarter 2024 production report for the Lower Village Hydro hydro-electric dam
April 2024
Compliance Filing, Order No. OneApril 14, 2024 · William P. Short IiiFourth quarter 2023 production report for the Lower Village Hydro hydro-electric dam.
January 2024
Compliance Filing, Order No. OneJanuary 7, 2024 · William P. Short IiiThird quarter 2023 production report for the Lower Village Hydro hydro-electric dam
November 2023
Compliance Filing, Order No. OneNovember 7, 2023 · William P. Short IiiSecond quarter 2023 production report for the Lower Village Hydro hydro-electric dam
July 2023
Compliance Filing, Order No. OneJuly 13, 2023 · William P. Short IiiFirst quarter 2023 production report for the Lower Village Hydro hydro-electric dam
May 2023
Compliance Filing, Order No. OneMay 7, 2023 · William P. Short IiiFourth quarter 2022 production report for the Lower Village Hydro hydro-electric dam
January 2023
Compliance Filing, Order No. OneJanuary 29, 2023 · William P. Short IiiThird quarter 2022 production report for the Lower Village Hydro hydro-electric dam
October 2022
Compliance Filing, Order No. OneOctober 3, 2022 · William P. Short IiiSecond quarter 2022 production report for the Lower Village Hydro hydro-electric dam
July 2022
Compliance Filing, Order No. OneJuly 28, 2022 · William P. Short IiiFirst quarter 2022 production report for the Lower Village Hydro hydro-electric dam
April 2022
Compliance Filing, Order No. OneApril 4, 2022 · William P. Short IiiFourth quarter 2021 production report for the Lower Village Hydro hydro-electric dam
January 2022
Compliance Filing, Order No. OneJanuary 18, 2022 · William P. Short IiiThird quarter 2021 production report for the Lower Village Hydro hydro-electric dam
October 2021
Compliance Filing, Order No. OneOctober 11, 2021 · William P. Short IiiSecond quarter 2021 production report for the Lower Village Hydro hydro-electric dam
- Compliance Filing, Order No. OneOctober 11, 2021 · William P. Short Iii
Second quarter 2021 production report for the Lower Village Hydro hydro-electric dam
August 2021
Compliance Filing, Order No. OneAugust 6, 2021 · William P. Short IiiFirst quarter 2021 production report for the Lower Village Hydro hydro-electric facility
January 2021
Compliance Filing, Order No. OneJanuary 10, 2021 · William P. Short IiiThird quarter 2020 production report for the Lower Village Hydro hydro-electric dam
October 2020
Compliance Filing, Order No. OneOctober 11, 2020 · William P. Short IiiSecond quarter 2020 production report for the Lower Village Hydro hydro-electric facility
July 2020
Compliance Filing, Order No. OneJuly 11, 2020 · William P. Short IiiFirst quarter 2020 production report for the Lower Village Hydro hydro-electric facility
April 2020
Compliance Filing, Order No. OneApril 8, 2020 · William P. Short IiiFourth quarter 2019 production report for the Lower Village Hydro hydro-electric facility
January 2020
Compliance Filing, Order No. OneJanuary 3, 2020 · William P. Short IiiThird quarter 2019 production report for the Lower Village Hydro hydro facility
October 2019
Compliance Filing, Order No. OneOctober 13, 2019 · William P. Short IiiSecond quarter 2019 production report for the Lower Village Hydro hydro facility
July 2019
Compliance Filing, Order No. 1July 3, 2019 · William P. Short IiiFirst quarter 2019 production report for the Lower Village Hydro hydro facility
April 2019
Compliance Filing, Order No. OneApril 14, 2019 · William P. Short IiiFourth quarter 2018 production report for the Lower Village Hydro hydro facility - Sugar River Power
February 2019
Compliance Filing, Order No. OneFebruary 8, 2019 · William P. Short IiiThird quarter 2018 production report for the Lower Village Hydro hydro facility.
October 2018
Compliance Filing, Order No. OneOctober 12, 2018 · William P. Short IiiSecond quarter 2018 production report for the Lower Village Hydro hydro facility
July 2018
Compliance Filing, Order No. OneJuly 26, 2018 · William P. Short IiiFirst quarter 2018 production report for the Lower Village Hydro hydro facility
February 2018
Compliance Filing, Order No. CT070211February 15, 2018 · William P. Short Iii2017 production report for the Lower Village Hydro hydro facility
- Compliance Filing, Order No. 07-02-11RE02February 11, 2018 · William P. Short Iii
2017 production report for the Lower Village Hydro hydro facility
January 2018
DecisionJanuary 3, 2018 ·Final Decision