Docket 13-07-19ClosedOctober 30, 2013
Application of FirstLight Hydro Generating Company for Qualification of Bulls Bridge Units 1-6 as a Class 1 Renewable Energy Resource
- Status
- Closed October 30, 2013
- First filing
- July 31, 2013
- Latest filing
- October 16, 2026
- Filings
- 62
- Documents
- On the current system (documents are copied for 2024 and later dockets)
This docket's record on the current system (opens in a new tab)
Decisions and notices
What the Authority has issued in this docket, newest first.
- October 30, 2013Decision Final Decision
- October 28, 2013Draft decision Draft Decision
Filings
Showing 1–50 of 62 filings.
October 2026
Compliance Filing, Order No. COM05168October 16, 2026 · FirstLight PowerJuly 2026
Compliance Filing, Order No. COM05168July 23, 2026 · FirstLight PowerBULLS BRIDGE UNITS 1-6 HYDRO QTR 2, 2026
April 2026
Compliance Filing, Order No. COM05168April 23, 2026 · FirstLight PowerBULLS BRIDGE UNITS 1-6 HYDRO QTR 1, 2026
January 2026
Compliance Filing, Order No. COM05168January 22, 2026 · FirstLight PowerBULLS BRIDGE UNITS 1-6 HYDRO QTR 4, 2025
October 2025
Compliance Filing, Order No. COM05168October 28, 2025 · FirstLight PowerBULLS BRIDGE UNITS 1-6 HYDRO QTR 3, 2025
- Compliance Filing, Order No. COM05168October 28, 2025 · FirstLight Power
BULLS BRIDGE UNITS 1-6 HYDRO QTR 3, 2025
July 2025
Compliance Filing, Order No. COM05168July 28, 2025 · FirstLight PowerBULLS BRIDGE UNITS 1-6 HYDRO QTR 2, 2025
April 2025
Compliance Filing, Order No. COM05168April 21, 2025 · FirstLight PowerBULLS BRIDGE UNITS 1-6 HYDRO QTR 1, 2025
January 2025
Compliance Filing, Order No. COM05168January 16, 2025 · FirstLight PowerBULLS BRIDGE UNITS 1-6 HYDRO QTR 4, 2024
October 2024
Compliance Filing, Order No. COM05168October 28, 2024 · FirstLight PowerFIRSTLIGHT BULLS BRIDGE UNITS 1-6 HYDRO QTR 3, 2024
July 2024
Compliance Filing, Order No. COM05168July 26, 2024 · Firstlight PowerFIRSTLIGHT BULLS BRIDGE UNITS 1-6 HYDRO QTR 2, 2024
April 2024
Compliance Filing, Order No. COM05168April 26, 2024 · Firstlight PowerFIRSTLIGHT BULLS BRIDGE UNITS 1-6 HYDRO QTR 1, 2024
January 2024
Compliance Filing, Order No. COM05168January 25, 2024 · Firstlight PowerFIRSTLIGHT BULLS BRIDGE UNITS 1-6 HYDRO QTR 4, 2023
October 2023
Compliance Filing, Order No. COM05168October 24, 2023 · Firstlight PowerFIRSTLIGHT BULLS BRIDGE UNITS 1-6 HYDRO QTR 3, 2023
July 2023
Compliance Filing, Order No. COM06168July 18, 2023 · Firstlight PowerFIRSTLIGHT BULLS BRIDGE UNITS 1-6 HYDRO QTR 2, 2023
April 2023
Compliance Filing, Order No. COM06168April 24, 2023 · Firstlight PowerFIRSTLIGHT BULLS BRIDGE UNITS 1-6 HYDRO QTR 1, 2023
January 2023
Compliance Filing, Order No. COM05168January 26, 2023 · Firstlight PowerBULLS BRIDGE UNITS 1-6 HYDRO QTR 4 - 2022
October 2022
Compliance Filing, Order No. COM05168October 25, 2022 · Firstlight PowerFIRSTLIGHT BULLS BRIDGE UNITS 1-6 HYDRO QTR 3, 2022
July 2022
Compliance Filing, Order No. COM05168July 28, 2022 · Firstlight PowerFIRSTLIGHT BULLS BRIDGE UNITS 1-6 HYDRO QTR 2, 2022
April 2022
Compliance Filing, Order No. COM05168April 21, 2022 · Firstlight PowerBULLS BRIDGE UNITS 1-6 HYDRO QTR 1, 2022
January 2022
Compliance Filing, Order No. COM05168January 27, 2022 · Firstlight PowerFirstlight Bulls Bridge Units 1-6 Hydro Qtr 4, 2021
- Compliance Filing, Order No. COM05168January 6, 2022 · Firstlight Power
BULLS BRIDGE QTR 3, 2021
July 2021
Compliance Filing, Order No. COM05168July 27, 2021 · Firstlight PowerFirstlight Bulls Bridge Units 1-6 Hydro Qtr 2, 2021
April 2021
Compliance Filing, Order No. COM05168April 23, 2021 · Firstlight PowerFirstlight Bulls Bridge Units 1-6 Hydro Qtr 1, 2021
January 2021
Compliance Filing, Order No. COM05168January 27, 2021 · Firstlight PowerBulls Bridge Units 1-6 Hydro
October 2020
Compliance Filing, Order No. COM05168October 27, 2020 · Firstlight PowerFirstLigt Bulls Bridge Units 1-6 Hydro Class 1 Renewable Energy Source Data 3rd Qrt., 2020
July 2020
Compliance Filing, Order No. COM05168July 22, 2020 · Firstlight PowerCom05168 Bulls Bridge Qtr. 2
April 2020
Compliance Filing, Order No. COM05168April 27, 2020 · Firstlight PowerBulls Bridge Units 1-6 Hydro
February 2020
Compliance Filing, Order No. 1February 4, 2020 · Firstlight PowerCom05168 Bulls Bridge Qtr. 4
October 2019
Compliance Filing, Order No. 1October 24, 2019 · Firstlight PowerCOM05168
July 2019
Compliance Filing, Order No. 1July 24, 2019 · Firstlight Power Resources Services, LlcCOM05168 Bulls Bridge Qtr 2-2019
April 2019
Compliance Filing, Order No. 1April 23, 2019 · Firstlight Power Resources Services, Llc1st Qtr 2019 Filing - FirstLight Bulls Bridge Units 1-6
January 2019
Compliance Filing, Order No. 1January 16, 2019 · Firstlight Power Resources Services, Llc4th Qtr 2018 Filing
October 2018
Compliance Filing, Order No. 1October 24, 2018 · Firstlight Power Resources Services, Llc3rd Qtr 2018 Filing
July 2018
Compliance Filing, Order No. 1July 23, 2018 · Firstlight Power Resources Services, Llc2nd Qtr 2018 Filing
June 2018
Compliance Filing, Order No. 1June 20, 2018 · Firstlight Power Resources Services Llc1st Qtr 2018 Filing
January 2018
Compliance filingJanuary 22, 2018 · Firstlight Power Resources Services LlcCompliance Filing, Order No. 13-07-19
October 2017
Compliance filingOctober 12, 2017 · Firstlight Power Resources Services LlcCompliance Filing, Order No. 13-07-19
July 2017
Compliance Filing, Order No. 13-07-19July 6, 2017 · Firstlight Power Resources Services LlcUnit 1 thru 6 Hydro
April 2017
Compliance filingApril 6, 2017 · Firstlight Power Resources Services LlcCompliance Filing, Order No. 13-07-19
January 2017
Compliance filingJanuary 24, 2017 · Firstlight Power Resources Services LlcCompliance Filing, Order No. 13-07-19
- Compliance filingJanuary 24, 2017 · Firstlight Power Resources Services Llc
Compliance Filing, Order No. 13-07-19
October 2016
Compliance filingOctober 31, 2016 · Firstlight Power Resources Services LlcCompliance Filing, Order No. 13-07-19
July 2016
Compliance filingJuly 21, 2016 · Firstlight Power Resources Services LlcCompliance Filing, Order No. 13-07-19
April 2016
Compliance filingApril 27, 2016 · Firstlight Power Resources Services LlcCompliance Filing, Order No. 13-07-19
January 2016
Compliance filingJanuary 22, 2016 · Firstlight Power Resources Services LlcCompliance Filing
October 2015
CorrespondenceOctober 22, 2015 ·3rd Qtr. 2015 Class 1 Renewable Energy Source Data.
August 2015
Compliance filingAugust 6, 2015 ·Compliance Filing, Order No. 1
May 2015
Compliance filingMay 7, 2015 · Firstlight Power Resources Services LlcCompliance Filing, Order No. 1
- Compliance filingMay 7, 2015 · Firstlight Power Resources Services Llc
Compliance Filing, Order No. 1