Skip to main content

A prototype public docket site for the Connecticut Public Utilities Regulatory Authority

Utility Dockets and Filings

Interrogatory responses

Answers to questions 1, 2, 4, 10, 18, 20

ResponseFiled by Connecticut Light and Power Company dba Eversource Energy13 files
Part of docket 26-05-10Open
  • Electric
Application of The Connecticut Light and Power Company d/b/a Eversource Energy to Amend its Rate Schedules

Files13

Text of ICC-001 Attachment 3.pdf

Extracted from the file · 34 pages · 76,972 characters

Text of ICC-001 Attachment 4.pdf

Extracted from the file · 34 pages · 72,650 characters

Text of ICC-001 Attachment 5.pdf

Extracted from the file · 67 pages · 136,480 characters

Text of ICC-002_Final.pdf

Extracted from the file · 2 pages · 2,788 characters

Text of ICC-002 Attachment 1.pdf

Extracted from the file · 29 pages · 46,015 characters

  1. Page 1 of 74

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 08, 2026 ICC-002 Attachment 2 Page 1 of 74 Eversource Energy The United Illuminating Company Docket No. 03-01-15 RE04 Compliance Order No. 1 April 8, 2019 EVERSOURCE ENERGY THE UNITED ILLUMINATING COMPANY Guidelines for Generator Interconnection Fast Track and Study Processes April 8, 2019 Excluding Inverter Based Projects 20 kW and Less
  2. Page 2 of 74

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 08, 2026 ICC-002 Attachment 2 Page 2 of 74 Table of Contents Section 1 Introduction and Executive Summary 1 Section 2 Pre Application 6 Section 3 Application 7 Section 4 Fast Track Process 12 Section 5 Study Process 17 Section 6 Provisions That Apply to All Interconnections and Associated Applications 22 Attachment I Interconnection Request I-1 Attachment II Application Acknowledgement Form II-1 Attachment III Information Request Form III-1 Attachment IV Feasibility Study Agreement IV-1 Attachment V Distribution System Impact Study Agreement V-1 Attachment VI Facility Study Agreement VI-1 Attachment VII Contingent Approval to Interconnect VII-1 Attachment VIII Approval to Energize VIII-1 Attachment IX Certification of Small Generator Equipment Packages IX-1 Attachment X Codes and Standards X-1 Attachment X I Glossary XI-1 Exhibit A Interconnection Agreement (Separate Document) Exhibit B Technical Requirements (Separate Document) i
  3. Page 3 of 74

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 08, 2026 ICC-002 Attachment 2 Page 3 of 74 SECTION 1 1. 0 Introduction and Executive Summary 1.1 Introduction W elcome! These Guidelines have been prepared by the Electric Distribution Companies, The Connecticut Light & Power Company (“CL&P”) and The United Illuminating Company (“UI”) (collectively, the “EDCs”), to assist power-generating customers wishing to interconnect with the Electric Power System (the “EPS”). Capitalized terms used herein shall have the meanings specified in Attachment XI or the body of these Guidelines. The EDCs are responsible for the distribution of electric power throughout most of the State of Connecticut. In order to carry out their responsibilities to all customers, each EDC must assure that all Interconnections are made according to certain protocols and procedures, which are described in more detail in these Guidelines. These revised Guidelines have been simplified as follows: (i) the application process has been streamlined; and (ii) these Guidelines are harmonized with ISO-NE, Schedule 23, requirements based on FERC’s Small Generator Order-2006. These Guidelines do not apply to inverter-based Generating Facilities of 20 kW and less. Separate guidelines, entitled “Guidelines for the Interconnection of Residential Single Phase Certified Inverter- Based Generating Facilities, 20 kW (ac) or Less,” were created for such Generating Facilities. These Guidelines contemplate that a Generator and an EDC will work together toward the common goal of a successful Interconnection, and the EDCs may consider case specific exemptions to the Guidelines (e.g., advances in technology). In the unlikely event that a Generator and an EDC cannot reach agreement on a specific Interconnection matter, such dispute will be resolved via formal dispute resolution procedures set forth in these Guidelines. Generators intending to make an Interconnection are advised to (i) refer to the Technical Requirements, attached hereto as Exhibit B, for guidance in the design of the Generating Facility and the Interconnection Facility; (ii) consult with the appropriate EDC prior to purchase of equipment in connection with the proposed Interconnection; and (iii) contact the appropriate EDC Facilitator to determine where and how to apply. 1
  4. Page 4 of 74

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 08, 2026 ICC-002 Attachment 2 Page 4 of 74 SECTION 1 The Connecticut Light & Power Company and The United Illuminating Company look forward to working with Generators to facilitate a safe, reliable and successful Interconnection in accordance with these Guidelines. 1.2 Executive Summary Interconnection Process for Generators smaller than 20 MW: These Interconnection Guidelines provide general guidance for interconnections of Generating Facilities that are smaller than 20 MW. Generating Facilities interconnections vary significantly in complexity depending on the generator size, location, and customer requirements; consequently, it is not practical to expect that these Guidelines should be rigidly observed for all interconnections and at all times. The Electric Distribution Company’s (EDC’s) Facilitator will work closely with the Generator to help achieve a successful interconnection. This Executive Summary and the flow chart shown in Figure 1 provide a quick overview of the Interconnection process and are not meant to replace the more detailed description of requirements contained in the remainder of these Interconnection Guidelines. The first step of the Interconnection process is to identify under which jurisdiction an Interconnection falls; the Federal Energy Regulatory Commission (FERC) or State of Connecticut (DPUC). Generators that intend to interconnect to the EPS and sell power or ancillary services to a third party or in the wholesale market may under certain circumstances fall under FERC jurisdiction. Generators that commit to sell their entire excess power to the EDC under NET Metering rules or to the EDC under the DPUCapproved tariff will be subject to state rules and such Generators can file an application directly with the EDC. State (DPUC) jurisdictional interconnection projects are administered by the EDC, while FERC jurisdictional projects are administered by the Independent System Operator – New England, Inc. (ISO-NE). FERC Jurisdictional Interconnections: Generators seeking to Interconnect to the EPS whose Interconnections fall under FERC’s jurisdiction must submit their application to ISO-NE in accordance with the procedures in the ISO-NE Transmission, Markets and Services Tariff (ISO-NE Tariff), Schedule 22 (for Generators larger than 20 MW) or Schedule 23 (for Generating Facilities up to and including 20 MW). ISO-NE will administer the interconnection process. However, prior to submitting an application to ISO-NE, Generators must contact the EDC’s Facilitator. In addition, prior to or at the same time that the Generator submits the application to ISO-NE, the Generator should provide a copy of the Interconnection application to the EDC. The EDC will establish the Generator’s queue position upon the EDC’s receipt of notification from the ISO-NE. State Jurisdictional Interconnections: 2
  5. Page 5 of 74

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 08, 2026 ICC-002 Attachment 2 Page 5 of 74 SECTION 1 The state-jurisdictional Interconnection process begins when a Generator submits an application to the EDC. The EDC will review the application and submittals and work with the customer to resolve any discrepancy and obtain any missing information. The EDC will then conclude the application review within fifteen (15) Business Days and submit the results to the Generator. Upon completion of the application review, if an Interconnection Study (Feasibility, Impact and/or Facility) is required, the EDC will provide a Study Agreement and an estimate of the costs to complete the Study. The EDC will request that the Generator execute the Agreement within fifteen (15) Business Days and pay the estimated cost of the Study. Some or all of the Studies may be required and the EDC will work with the Generator to identify the required Studies. Each Study will require its own Study Agreement. Distribution Studies usually require approximately thirty (30) Business Days for completion of each Study and may include a Feasibility Study, an Impact Study and a Facility Study. Transmission studies may be required for some Interconnections even if the Generator Interconnection falls under state rules. Transmission studies are more complex and must be conducted in accordance with applicable ISO-NE rules and procedures. These Guidelines do not address the transmission studies process required by ISO-NE. The Generator may obtain guidance from the ISO-NE Tariff, Schedule 22 and 23 and Section I.3.9. However, during the Interconnection process, the EDC will provide guidance including information concerning the scope, duration and cost of the transmission studies. At the conclusion of the studies, the EDC will submit an Interconnection Agreement (IA) to the Generator. The Generator will be required to sign the IA and submit full payment for the estimated costs for upgrades required to interconnect the Generating Facility. At the conclusion of the project, the EDC will reconcile actual vs. estimated cost and reimburse or bill the Generator accordingly. Once the upgrades are implemented, the following steps will be required to allow the Generator to interconnect to the EDC. • Provide Proof of Municipal approval for the Generating Facility. • Request the EDC to witness the commissioning test. Within ten (10) Business Days of the receipt of the Municipal approval, the EDC will witness the commissioning test and following successful completion of that test, the EDC will send a final approval authorizing the interconnection to the Generator. 3
  6. Page 6 of 74

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 08, 2026 ICC-002 Attachment 2 Page 6 of 74 SECTION 1 The following Interconnection Process Flow Chart provides an overview of the steps necessary for a successful interconnection: Figure 1: Interconnection Process Flow Chart Pre-Application Discussion & Scoping meeting & Application Submital Application Request Complete Customer submits all information No No Application Withdrawn Yes Yes Inverter based & Certified =2 MW No Conduct Application Review (30 Business Days) Generator => 5 MW Yes No Passes Screen Studies Required No Yes Yes ISO-NE Generator Interconnection Process (I.3.9 ) Conduct Studies as appropriate: 1-Feasibility Study 2-Impact Study 3- Facility Study 4- Transmission Studies No Yes Conduct Application Review (15 Business Days) No Yes Customer Signs IA & authorizes EDC modification Yes Customer installs generator and returns certificate of completion to EDC Witness Commissioning Test Studies Completed EDC issues final approval to energize. Additional Process Steps for Generators greater than 5 MW: Regardless of the Interconnection jurisdiction, each Generator wishing to interconnect a Generating Facility larger than 5 MW must comply with the ISO-NE Planning Procedure 5 (PP5), which is the procedure for a Proposed Plan Application (PPA) under Section I.3.9 of the ISO-NE Tariff. This process must be completed before the Generator may Interconnect such Generating Facility. It is important to note that the PPA process is an ISO-NE requirement, even if the Interconnection of such facility falls under state jurisdiction. 4
  7. Page 7 of 74

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 08, 2026 ICC-002 Attachment 2 Page 7 of 74 SECTION 1 While the Generator is ultimately responsible for the PPA application and the associated data to be submitted to ISO-NE, the EDC will provide support to the Generator if the Generator is not a “Governance Participant” (as such term is defined in the Participants Agreement; among ISO-NE and the New England Power Pool) at the time the PPA is submitted to the EDC. Typically, the EDC will file the PPA on behalf of such nonGovernance Participant Generator. Additionally, the EDC will represent such Generator in ISO-NE proceedings in accordance with the current ISO-NE rules; provided, however, that such Generator shall remain solely responsible for, among other things: (a) the completion of the PPA and the accuracy of the information contained therein, (b) the advance payment based on a non-binding good faith estimate of all costs in connection with any required Transmission System Impact Study, and (c) the payment of all costs associated with transmission upgrades identified through the ISO-NE approval process. Each non-Governance Participant Generator wishing to Interconnect a Generating Facility larger than 5 MW must read and be familiar with PP5, Section I.3.9 of the ISONE Tariff and other relevant ISO-NE guidance on the PPA process. Further, such nonGovernance Participant Generator can communicate directly with ISO-NE to seek assistance concerning the applicable PPA requirements and associated issues. For non-Governace Participant Generators the EDC notifies ISO-NE of receipt of the Interconnection Application, under current ISO-NE practice. Further, the EDC submits a complete copy of the PPA application to ISO-NE in order to secure an ISO-NE queue position. An ISO-NE queue position will not be established by ISO-NE until all the data required by ISO-NE is complete. Governance Participants are responsible for filing their own PPA with the ISO-NE and representing themselves in connection with all ISO-NE proceedings. Interconnection Process for Generators greater than 20 MW: The time frames and processes described in these guidelines are applicable to Generating Facilities smaller than 20 MW and represent the majority of Distribution interconnections. Generating Facilities larger than 20 MW are only rarely interconnect to the EPS. However, from time to time the EDC will receive requests for Interconnecting Generating Facilities greater than 20 MW seeking an interconnection to the EPS. When this situation occurs and provided that an interconnection to the EPS is feasible and appropriate, the EDC will use these Guidelines; however, the time frames to conduct the Application Review and Studies will be adjusted in accordance with the ISO-NE Tariff, Schedule 22. 5
  8. Page 8 of 74

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 08, 2026 ICC-002 Attachment 2 Page 8 of 74 SECTION 2 2.0 Pre Application 2.1. After presenting a proposed Interconnection project for a specific site, the Generator may request information regarding the application process from an EDC Facilitator. The most current contact information for EDC Facilitators is available on each EDC’s website listed below. 2.2 The EDC Facilitator will serve as the primary point of contact for all Interconnections. Copies of these Guidelines, information and forms can be obtained from the EDC Facilitator . 2.3 The EDC Facilitator for Eversource can be contacted: by phone: [phone removed]; or by mail or courier: Eversource Energy Distributed Energy Resources Department P.O. Box 1409 Hartford, CT 06143-1409 Updated information regarding EDC Facilitator contact information can be found at https://www.eversource.com/content/ct-c/about/about-us/doing-business-withus/builders-contractors/interconnections . 2.4 The EDC Facilitator for UI can be contacted: via email: [email removed] by phone: [phone removed]; or by mail or courier: The United Illuminating Company Distributed Energy Resources Department 180 Marsh Hill Rd. Orange, CT 06477 Updated information regarding EDC Facilitator contact information can be found at https://www.uinet.com 6
  9. Page 9 of 74

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 08, 2026 ICC-002 Attachment 2 Page 9 of 74 SECTION 3 3.0 Application 3.1 Applicability 3.1.1 These Guidelines are applicable to Interconnection Requests for Generating Facilities which fall under DPUC jurisdiction. Generators unsure as to whether the proposed Interconnection is subject to these Guidelines should contact the appropriate EDC Facilitator. 3.1.2 Requests for Interconnection received by an EDC shall be processed as follows: 3.1.2.1 A request to interconnect a certified inverter-based Generating Facility no larger than 20 kW shall be evaluated under the “Guidelines for the Interconnection of Residential Single Phase Certified Inverter-Based Generating Facilities, 20 kW (ac) or Less.” 3.1.2.2 A request to interconnect a Generating Facility no larger than 2 MW shall be evaluated under either the Fast Track Process (Section 4) or the Study Process (Section 5). A description of certification criteria is set forth in Attachment I. 3.1.2.3 A request to interconnect a Generating Facility larger than 2 MW or a Generating Facility that does not meet the criteria for the Fast Track Process shall be evaluated under the Study Process (Section 5). 3.2 . Interconnection Request 3.2.1 Prior to making an Interconnection Request, Generators should contact the EDC Facilitator to determine where to apply. If an Interconnection Request is sent to an EDC in error (e.g., ISO-NE jurisdiction or wrong EDC) the EDC will return such Interconnection Request to the Generator. 3.2.2 An Interconnection Request must be in the form of Attachment I, and addressed to the appropriate EDC Facilitator. A processing fee is required with each Interconnection Request. The applicable fee is as follows: Table 1 Fees Process Generator Applicability Fast Track (1) 0-2 MW, unless Generating Facility does not qualify for the Fast Track process, or (2) is 20 kW or less, certified 7 Application Fee $500 Each Study Fee Actual Cost Based
  10. Page 10 of 74

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 08, 2026 ICC-002 Attachment 2 Page 10 of 74 SECTION 3 but did not pass the 20 kW or Less screen(s). Study 3.3 (1) is larger than 2 MW but no larger than 20 MW, (2) is 2 MW or less and is not certified, or (3) is 2 MW or less and is certified but did not pass the Fast Track Process. $1000 Actual Cost Based 3.2.3 The Interconnecting EDC shall date- and time-stamp the Interconnection Request upon receipt. Such date- and time-stamp shall used for the purposes of the timetables set forth in these Guidelines. 3.2.4 Within three (3) Business Days of the receipt of the Interconnection Request, the Interconnecting EDC shall confirm receipt of such Interconnection Request using the form attached hereto as Attachment II. 3.2.5 Within ten (10) Business Days of the receipt of the Interconnection Request, the Interconnecting EDC shall notify the Generator if such Interconnection Request is incomplete using the form attached hereto as Attachment III. The Generator will have fifteen (15) Business Days from the date of such notice to submit the listed information or to request an extension of time to provide such information. If the Generator does not provide the listed information or a request for an extension of time within such fifteen (15) day period, then the Interconnection Request will be deemed withdrawn, and such deemed withdrawal shall be subject to Section 3.8. An Interconnection Request will be deemed complete upon receipt of the listed information by the Interconnecting EDC. Insurance Requirements Generators interconnecting a Generating Facility to the EPS of an EDC shall maintain general liability insurance in the amounts set forth in the following table, per Interconnection at all times during the Interconnection. Liability Insurance Nameplate Rating* Less than 100 kW Minimum Liability Insurance Required $300,000 Greater than 100 kW to 1 MW Greater than 1 MW to 5 MW $1,000,000 $2,000,000 8

Text of ICC-002 Attachment 3.pdf

Extracted from the file · 27 pages · 91,051 characters

Text of ICC-004_Final.pdf

Extracted from the file · 1 page · 983 characters

Text of ICC-010_Final.pdf

Extracted from the file · 4 pages · 11,507 characters

Text of ICC-018_Final.pdf

Extracted from the file · 2 pages · 2,628 characters

As listed on the current system

Question(s) Answered 1, 2, 4, 10, 18, 20 (Connecticut Light and Power Company dba Eversource Energy) Date Filed: 09/22/2026