Time Schedule for Docket No. 26-06-17 TITLE: PANEL: STAFF: Petition for Approval of Method and Manner of Construction and Permission to Energize the Haddam Substation to East Haddam Junction Rebuild Project (1772 AND 348 LINES) WABHS Coordinator: Laura L. Lupoli Lead Staff: Quat M. Nguyen Legal Advisor: Jay DonFrancisco Docket Initiated: 06/26/2026 12:53:21 PM EDT Date of last revision: 08/05/2026 12:50:00 PM EDT External Events Notice of Proceeding Issued Proposed Final Decision Issued Regular Meeting/Final Decision Time Schedule Comment: Location Status CONFIRMED CONFIRMED CONFIRMED Date 07/17/2026 08/05/2026 08/12/2026 Time 11:00:00 AM 12:45:00 PM 09:00:00 AM

As listed on the current system

TS External [26-06-17] [WABHS] Last Revised: 08/05/2026

This filing on the current system (opens in a new tab)