Time Schedule for Docket No. 26-06-17
TITLE:
PANEL:
STAFF:
Petition for Approval of Method and Manner of Construction and Permission to Energize the Haddam Substation to East
Haddam Junction Rebuild Project (1772 AND 348 LINES)
WABHS
Coordinator: Laura L. Lupoli
Lead Staff: Quat M. Nguyen
Legal Advisor: Jay DonFrancisco
Docket Initiated: 06/26/2026 12:53:21 PM EDT
Date of last revision: 08/05/2026 12:50:00 PM EDT
External Events
Notice of Proceeding Issued
Proposed Final Decision Issued
Regular Meeting/Final Decision
Time Schedule Comment:
Location
Status
CONFIRMED
CONFIRMED
CONFIRMED
Date
07/17/2026
08/05/2026
08/12/2026
Time
11:00:00 AM
12:45:00 PM
09:00:00 AM
As listed on the current system
TS External [26-06-17] [WABHS] Last Revised: 08/05/2026